This Addendum No. 1, dated August 26, 2024, is issued by the State of Michigan Department of Natural Resources for the North Country Trail over Carp River Bridge Replacement project (DTMB File #751/22371.ABG). The addendum modifies the original contract documents dated July 26, 2024, and incorporates updates prior to the bid date of Wednesday, August 28, 2024. Key modifications include the addition of Wagner CFTUSA to the bridge supplier list for the prefabricated FRP pedestrian bridge special provision and clarification regarding stainless steel bearings, which may be eliminated if the bridge supplier proposes and the Engineer approves FRP bearings as an alternative. A pre-bid meeting attendance record and site photos are attached for contractor reference.
The addendum establishes an important environmental requirement: all tree clearing must be approved by the Michigan Department of Natural Resources prior to removal. Contractors are required to mark trees designated for removal and request an on-site meeting with MDNR personnel to review the clearing plan before proceeding with any removal activities. This clarification ensures compliance with state environmental regulations and project-specific requirements for the bridge replacement work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22371 Advertisment.pdf | ||
| 22371 Specifications.pdf | ||
| 22371 Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
751_22371_ABG Addendum 01 Page 1 of 1
ADDENDUM NO. 1
DATE: August 26, 2024
PROJECT: North Country Trail over Carp River – Bridge Replacement
OWNER: State of Michigan Department of Natural Resources
DTMB FILE #: 751/22371.ABG
BID DATE: Wednesday, August 28, 2024
The following shall be incorporated into the Contract Documents dated July 26, 2024.
GENERAL
1. Pre-Bid Meeting Attendance Record is attached.
2. Site photos attached for information only.
PROJECT MANUAL
1. Special Provision for Prefabricated FRP Pedestrian Bridge (not re-issued):
Add to a. Description: bridge supplier list
3. Wagner CFTUSA
2. Special Provision for Stainless Steel Bearings (not re-issued): Can be eliminated if FRP bearings are to be used by the bridge supplier and approved by the Engineer.
PLAN SHEETS
None.
CLARIFICATIONS
1. All tree clearing must be approved by the MDNR prior to removing any trees. Contractor to mark trees to be removed and request an on-site meeting with the MDNR to review.
End of Addendum No. 1 not present not present