About this file
This document is an Addendum 1 for a state construction project issued by the Michigan Department of Natural Resources (DNR) and Department of Technology, Management and Budget (DTMB) for the Felch Field Office Basement Water Management and Foundation Repair. The project involves basement repair work at the DNR Felch Field Office located in Felch, Michigan, with a mandatory pre-bid conference scheduled for March 4, 2020, at 2:00 PM. The electronic bid due date is March 18, 2020, at 2:00 PM, with bid questions accepted until March 11, 2020, at 1:00 PM. The project scope includes removing exterior sidewalk, installing gutters and downspouts, providing positive drainage, constructing a wood-framed closet with basement access, abandoning select basement utilities, installing concrete masonry units in basement windows, and filling the basement area with clean fill. The contract substantial completion date is set for June 26, 2020.
The project requires a 5% bid security, with performance and payment bonds required for bids over $50,000. Builders Risk Insurance will not be provided by the State of Michigan. Bidders must submit electronically through the SIGMA website and are restricted to representing only one bidder during the mandatory site walkthrough. The project utilizes NIGP codes spanning construction and facility maintenance categories, and bidders must use specified materials without "or equal" substitutions. Contact for site examination is Dan McNamee, FRD Unit Manager, and technical questions can be submitted via email to the project manager, Joshua W. Paquet of GEI Consultants of Michigan, P.C.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawings.pdf | ||
| Addendum No. 2.pdf | ||
| 751_19266 Bid Addendum 3.pdf | ||
| Advertisement.pdf | ||
| DCSpec.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A1-2000-1
BASEMENT WATER MANAGEMENT
FELCH FIELD OFFICE DTMB FILE NO. 751/19266.JBB
ADDENDUM NO. 1
Index No.: 7612 File No.: 751/19266.JBB
Department of Natural Resources Project Name: Felch Field Office Basement Water Management and Foundation Repair
Subject: Request for Bids – Addendum 1
DATE: Wednesday, February 21, 2020
ORIGINAL BID DATE: Wednesday, March 4, 2020
REVISED BID DATE: Wednesday, March 18, 2020
TO: All Bidders
INTENT: This Addendum is issued to revise and clarify the content of the project bid documents as a result of the pre-bid conference meeting that was held on Wednesday, February 19, 2020.
ATTACHMENTS: 1. Revised Project Advertisement
2. Revised Bid Summary Sheet
ADDENDUM ITEM WRITE UP:
- Item 1 – Bid Extension o The bidding for the project is being extended. As such, an additional pre-bid conference meeting will be held at the Felch Field Office. The following describes the revised bid deadline for the project:
Additional Mandatory Pre-bid Conference Meeting – Wednesday, March
4th at 2 PM Eastern Standard Time. Location: Felch Field Office.
Bid Questions Due – Wednesday, March 11th by 1 PM Eastern Standard
Time Electronic Bid Due Date – Wednesday, March 18th
- Item 2 – Project Advertisement Update o Replace the existing project advertisement and bid summary with the attached.
Bidder shall acknowledge receipt of this Addendum at the bottom of the Bid Summary form to be submitted as part of the greater bid.
End of Addendum 1
GEI Consultants of Michigan, P.C.
Joshua W. Paquet, P.E.
Project Manager
DTMB-0415 (R 10/17)
PROJECT ADVERTISEMENT
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN & CONSTRUCTION DIVISION
This form is required for the advertisement of all construction projects. (1984 PA 431)
TO:
Design and Construction Division
DATE
February 21, 2020
FROM:
Department of Natural Resources
PROJECT MANAGER
Jeffrey Barsch
DTMB FILE NUMBER
751/19266.JBB
ACCOUNTING TEMPLATE
Not Applicable
ADVERTISEMENT DATE
February 3, 2020
ELECTRONIC BID DUE DATE
March 18, 2020
PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)
Felch Field Office Basement Water Management and Foundation Repair, DNR Felch Field Office (N 45.996420, W 87.824413) located on M-69 just east of the Calumet Mine Road/M-69 Intersection in Felch, Michigan.
WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION
The mandatory Pre-bid Conference and Site Walkthrough is scheduled for March 4th, 2020; at 2:00 PM Eastern time at the DNR Felch Field Office.
Mandatory Yes No
NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.
DESCRIPTION OF WORK:
Removal of exterior sidewalk, installation of gutter and downspouts, providing positive drainage along exterior of building, constructing a wood framed closet with access to the existing basement, abandoning select utilities within basement, installation of concrete masonry units within basement windows and filling basement area with clean fill.
5% Bid Security:
Required
Not Required
NIGP CODES: 90922, 91051, 91024, 91065, 91066, 91078, 91080, 91200, 91244, 91427, 91438, 91450, 91455, ACCEPTING QUESTIONS UNTIL: Wednesday, March 11, 2020 by 1:00 PM Local Time. Submit questions in writing via email to jpaquet@geiconsultants.com
Documents may be obtained from:
https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
PSC/Agency: GEI Consulants of Michigan, P.C
Address: 109 West Baraga Avenue, Marquette, MI 49855
Phone: 906-629-1389
Email: jpaquet@geiconsultants.com
Fax: N/A Approved by: Department of Technology, Management and Budget / Design and Construction Division
Bidding and Contract Document (R 2/19) Project Name: Felch F.O. Basement File No. 751/19266.JBB
50K Spec (R 2/19)
BID SUMMARY
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN AND CONSTRUCTION DIVISION
3111 W. St. Joseph Street Lansing, Michigan 48917
Bids must be submitted electronically through the SIGMA website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
FILE NUMBER
751/19266.JBB
INDEX NUMBER
DEPARTMENT/AGENCY
751 – Natural Resources
CONTRACT TIME(S)
June 26, 2020 – Substantial Completion
PROJECT NAME
Felch Field Office Basement Water Management and Foundation Repair
LOCATION
Felch, MI
BID OPENING DATE
Wednesday, March 18th at 2:00 pm Local Time
FOR AN EXAMINATION OF THE SITE CONTACT:
Dan McNamee, FRD Unit Manager, 906-875-5025 (W)
SEE SECTION 00100 INSTRUCTIONS TO BIDDERS AND SECTION 00700 GENERAL CONDITIONS PROVIDED WITH THE BIDDING DOCUMENTS.
BID: WE PROPOSE TO FURNISH, PERFORM AND COMPLETE THE ENTIRE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS IN
CONSIDERATION OF THE BID PRICE (S) STATED BELOW.
FIRM NAME AND COMPLETE ADDRESS TELEPHONE NUMBER and E-MAIL ADDRESS
□ Qualified Disabled Veteran
FEDERAL I.D. NUMBER (LAST 4 ONLY)
(protected information required for processing payments)
BIDDER'S SIGNATURE AND TITLE DATE
WITNESS' SIGNATURE DATE
By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan-Based Business Certifications.
*Protected information required for processing payments.
Base Bid (from Bid Schedule) (Include specified Allowance): ............................................... ……….Dollars $______________________
Builders Risk Insurance is NOT provided by the State of Michigan.
BID GUARANTEE REQUIRED: A FIVE (5) PERCENT BID SECURITY IS REQUIRED FOR ALL BIDS. A PERFORMANCE BOND AND A
PAYMENT BOND IS REQUIRED ON ALL BIDS OVER $50,000.00.
NOTE: BIDDERS ARE CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL OF THE CONDITIONS OF THE CONTRACT AS SET
FORTH THROUGHOUT THE BIDDING AND CONTRACT DOCUMENTS.
Project Scope of Work:
The project is located at the Department of Natural Resources Felch Field Office. Removal of exterior sidewalk, installation of gutters and downspouts, providing positive drainage along exterior of building, constructing a wood framed closet with access to the existing basement, abandoning select utilities within basement, installation of concrete masonry units within basement windows and filling basement area with clean fill.
The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.
Contract Time(s): June 26, 2020 – Substantial Completion
Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________
This Bid Summary is intended to serve as a summary page. Failure to complete this Bid Summary may be cause for the Bid to be rejected.