7368480 SpecsAsOne SIGNED.pdf
PDF 2 MB Posted
- Solicitation number
- N400857368480
About this file
This is a Request for Proposals (RFP) for a repair project at Marine Corps Air Station (MCAS) Cherry Point, North Carolina. The project involves repairing a failed slope and concrete cracks at Building 4185 Transfer Station, with a contract number of 7368480. The work includes concrete rehabilitation, surface preparation, repair of structural concrete, waterproofing, and painting of steel surfaces. The project will require geotextile installation, gabion placement, and landscaping establishment.
Key technical requirements include repairing concrete surfaces, addressing slope failures, applying fluid-applied waterproofing, and coating steel retaining wall surfaces. The project specifications detail precise requirements for concrete rehabilitation, including surface preparation, reinforcement repair, and coating applications. The work will be performed at MCAS Cherry Point, with a focus on restoring the structural integrity and functionality of the Transfer Station facility. Contractors must comply with detailed technical specifications covering earthwork, concrete repair, waterproofing, painting, and landscape restoration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP B4185 Transfer Station.pdf | ||
| 7368480 DrawingsAsOne SIGNED.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, MID-ATLANTIC
MARINE CORPS AIR STATION, CHERRY POINT, NORTH CAROLINA
REPAIR FAILED SLOPE AND CONCRETE CRACKS B4185 TRANSFER STATION
AT THE
MARINE CORPS AIR STATION
CHERRY POINT, NORTH CAROLINA
PROJECT: 7368480
DESIGNED BY:
DESIGN MANAGEMENT AND ENGINEERING DIVISION
MCAS, CHERRY POINT, NC
SPECIFICATION PREPARED BY:
FRANK BURNS, PE
SPECIFICATION APPROVED BY:
Design Director: _____________________________________________
PATRICK FAULKNER, PE
Date: ___________________ heather.perry Typewritten Text on behalf of heather.perry Typewritten Text
2025 MAY 7
Repair Failed Slope and Cracked Concrete B4185 Transfer Station 7368480
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 14 00 11/22, CHG 4: 02/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 16.00 20 08/18, CHG 1: 08/20 SMALL PROJECT CONSTRUCTION PROGRESS
SCHEDULES
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 80 00 04/15 REPORTS
DIVISION 02 - EXISTING CONDITIONS
02 83 00 11/18 LEAD REMEDIATION
DIVISION 03 - CONCRETE
03 01 00 02/18 REHABILITATION OF CONCRETE
03 30 00 02/19, CHG 9: 08/24 CAST-IN-PLACE CONCRETE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 14 00 08/23 FLUID-APPLIED WATERPROOFING
DIVISION 09 - FINISHES
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 36 00 02/21 GABIONS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 92 23 04/06, CHG 1: 08/21 SODDING
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS Page 2
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/24
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. REVISION NO. NAVFAC DWG NO. TITLE
G001 0 12912911 Cover Sheet
G002 0 12912912 General Notes
CE01 0 12912913 Existing Conditions Plan
CU01 0 12912914 Repair Plan
CU02 0 12912915 Repair Details Sh. 1
CU03 0 12912916 Repair Details Sh. 2
CU04 0 12912917 Repair Details Sh. 3
-- End of Document --
DOCUMENT 00 01 15 Page 1
SECTION 01 11 00
SUMMARY OF WORK
02/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes repairs to the Transfer Station, Bldg. 4185 and incidental related work.
1.2.2 Location
The work is located at MCAS Cherry Point, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
SECTION 01 11 00 Page 1
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 4: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contract Personnel
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. The Transfer Station will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the activity.
c. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Working Hours
Regular working hours will consist of an 8 1/2 hour period , between 7 a.m. and 3:30 p.m., Monday through Friday, , excluding Government holidays.
1.4.2 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number, and project title. Based on the justification provided, SECTION 01 14 00 Page 1 the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in accordance with requirements of EM 385-1-1 . Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.4.3 Occupied Buildings
Work will be in an existing building which is occupied.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
1.5 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:
1.5.1 MCAS Cherry Point Regulations
No employee or representative of the contractor will be admitted to the work site without an Identification Badge or is specifically authorized admittance to the work site by the FEAD, Facilities Engineering & Acquisition Division.
IMPORTANT NOTE: FEAD personnel (Construction Managers, Engineers/Architects, Engineering Technicians, Contract Specialists, or Contract Surveillance Representatives) will not receive, process, re-transmit, or otherwise handle IN ANY WAY Personally Identifiable Information (PII) related to the badging process. Do NOT forward any of this information to the FEAD.
1.5.2 Contractor Access to MCAS Cherry Point and Outlying Areas
1. Documentation requirements for granting access to MCAS Cherry Point for commercial and contract employers and employees. This document is an aid in meeting ASO 5560.6C requirements and is not a substitute for the order.
2. The Pass & Identification Office at Building 251 will issue credentials to authorized contractors. Sub-Contractors and suppliers must coordinate through the Prime-Contractor.
3. Criminal Activity. In accordance with ASO 5560.6C, the below list of criminal activities within an applicant's record are considered not in the best interest of the Marine Corps and will be grounds for automatic denial of access aboard the Installation:
a. Conviction for espionage, sabotage, sedition, treason, terrorism, armed robbery, or murder.
b. Felony conviction for a firearms or explosives violation, regardless of the date of conviction.
c. Conviction of crimes encompassing sexual assault or rape.
SECTION 01 14 00 Page 2
d. Conviction of crimes encompassing child molestation, or the possession or production of child pornography.
e. Conviction of trafficking in persons.
f. Conviction of drug possession with intent to sell or distribute.
g. Convicted of three or more misdemeanor violations, or attempted violations, within the previous 10 years of the following offenses:
(1) Sex crime
(2) Assault
(3) Larceny
(4) Drugs
(5) Weapons
4. Persons requesting access to MCAS Cherry Point will be denied access based on the following:
a. The individual is a registered sex offender.
b. The individual has an active arrest warrant from Federal, State, local, or other civil law enforecement authorities, regardless of offense or violation.
c. The individual has a felony conviction within the last 10 years, regardless of the offense or violation.
d. The individual's name appears on any Federal or State agency watch list for criminal behavior or terrorist activity.
e. The individual is debarred entry or access to a Marine Corps site, other DoD installations or facilities, or other Federal site or facility.
f. The individual engaged in acts or activities designed to overthrow the U.S. Government by force.
g. The individual is known to be or reasonably suspected of being a terrorist or belongs to an organization with known terrorism links/support.
h. The individual is identified in the National Crime Information Center (NCIC) known suspected terrorist (KST) file, or the Terrorist Screening Database (TSDB) report as known to be, or suspected of being, a terrorist or belonging to an organization with known links to terrorism or support of terrorist activity. If an individual is identified on the NCIC KST files or TSDB, the Provost Marshal's Office (PMO) will immediately call the NCIS Multiple Threat Alert Center (MTAC) for further coordination. The MTAC will coordinate with the Department of Justice (DOJ) or Federal Bureau of Investigation (FBI) and provide handling instructions to MCAS Cherry Point Police, Criminal Investigations Division (CID), or NCIS.
i. The individual is illegally present in the U.S.
j. The individual has knowingly submitted an employment questionnaire with false or fraudulent information.
SECTION 01 14 00 Page 3
k. The individual is a prisoner on a work-release program or currently on felony probation or parole.
l. The individual is pending any felony charge.
m. The individual has criminal arrest information that the site commander determines the person presents a threat to good order, discipline, or health and safety on the Marine Corps site.
n. Any reason the Installation Commander deems reasonable for good order and discipline.
1.5.3 Staging Area
As indicated on the plans, the Contractor staging area will be (Construction Manager to coordinate). Amount of material on site shall be kept to a minimum and shall only be material that is pertinent to the work currently being performed. All stockpiling of equipment and materials shall be closely coordinated with the Government and shall not disrupt activities at the site.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 Page 4
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of Contract Award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Indirect activities (e.g., meetings, presentations, submittals, surveys, haul road or storage yard maintenance, dust control, security) will not be cost loaded. Evenly distribute the costs across the associated construction activities. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.
1.3.2 Payment Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.
Additionally, the Schedule of Prices must be separated as follows:
a. Primary Facilities Cost Breakdown:
Defined as work on the primary facilities out to the 5 foot line.
Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes attendant construction, such as pad mounted HVAC cooling equipment, SECTION 01 20 00 Page 1 cooling towers, and transformers placed beyond the 5 foot line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 5 foot line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. Include the documents listed below in the requests for payment.
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.
b. The Estimate for Voucher/Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government. Use NAVFAC Form 4330, unless otherwise directed by the Contracting Officer, on NAVFAC Contracts when a Monthly Estimate for Voucher is required.
c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.
d. Monthly Work-hour report.
e. Updated Construction Progress Schedule and tabular reports required by the contract.
f. Contractor Safety Self Evaluation Checklist.
g. Updated submittal register.
h. Solid Waste Disposal Report.
i. Certified payrolls.
j. Updated testing logs.
k. Other supporting documents as requested.
SECTION 01 20 00 Page 2
1.5.2 Submission of Invoices
Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR
32.103 Progress Payments Under Construction Contracts:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this Contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21 and the contract.
e. Failure to submit accurate monthly schedule updates in accordance with the contract.
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site, but not installed, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
SECTION 01 20 00 Page 3
c. Provide the Contracting Officer with documentation (e.g., Purchase Orders or Material Contracts) to justify payment for materials in advance of installation. When appropriate, include the Defense Priorities and Allocations System (DFAS) ratings (e.g., DX or DO) on purchase orders or material contracts to ensure timely delivery.
d. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.
Requests for progress payment consideration for such items must be supported by documents establishing their value (e.g., paid invoices) and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.
e. Ensure materials are adequately insured and protected from theft and exposure. Provide insurance documentation (e.g., Builder's Risk Insurance) which covers the overall value of the materials to be paid in advance of installation.
f. Provide a written consent from the surety company with each payment request for offsite materials.
g. Materials to be considered for progress payments prior to installation must be stored either in Hawaii, Guam, Puerto Rico, or the Continental United States. Other locations are subject to written approval by the Contracting Officer.
h. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 20 00 Page 4
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map Progress and Completion Pictures
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD) or one set of digital photographs in the agency construction management system of record, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD or with the submission in the agency construction management system of record as a digital file. Include a date designator in file names.
Photographs provided are for unrestricted use by the Government.
1.5 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide
SECTION 01 30 00 Page 1 other insurance coverage as required by North Carolina law.
1.6 SUPERVISION
1.6.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section01 45 00 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.6.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a QC representative is required on the Contract, then that individual must also have fluent English communication skills.
1.6.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and QC meetings. The superintendent, or qualified alternate, must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.6.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.7 PRECONSTRUCTION MEETING
prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, QC, schedule of prices, shop drawings, submittals, cybersecurity, prosecution
SECTION 01 30 00 Page 2 of the work, government acceptance, final inspections, and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.7.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), QC Manager, and major subcontractors.
1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:
1.8.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.8.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.9 PARTNERING
Host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government
SECTION 01 30 00 Page 3 must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget, and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, PWD, FEAD, Contractor, key subcontractors, and the DOR (regardless of whether the contract is a design-build or a design-bid-build) are required to participate in the Partnering process.
1.9.1 Team-Led (Informal) Partnering
a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.
b. The Initial Team-led Partnering session may be held concurrently with the meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.
c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
d. The Partners will determine the frequency of the follow-on sessions.
e. Participants will bear their own costs for meals, lodging, and transportation associated with Partnering.
1.10 MOBILIZATION
Mobilize to the jobsite within 60 calendar days after contract award .
Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 30 00 Page 4
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS) 08/23
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Systems Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or email submission, including originals or copies, of the documents are not permitted unless identified within the contract.
All government contracting specialist/officer, legal, and command communications will remain the same.
1.2 USER PRIVILEGES
The Contractor's key staff may be provided access to eCMS. Contact the COR for eCMS account access. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
Additional project roles may be assigned for workflow. The COR makes the final decision on roles for the project. User's ability to view and edit documents may be lowered at the discretion of the COR.
Only one eCMS user account is required regardless of the number of user's projects. Notify the COR within seven calendar days if a contractor user is no longer associated with company or project so they can remove them from any open record and inactivate them from the project.
1.2.1 eCMS Subcontractor Users
If the contractor's user is a subcontractor, the subcontractor must be registered under the name of their company and email. For example, it is common for contractors to contract QC Managers. The QC Manager's account should be under their company's name and email reducing the number of eCMS accounts required.
1.2.2 Users with Multiple Roles
Users may have multiple roles associated with their account within eCMS.
Roles are used in workflow. When a user is added to the project, they will be assigned the default role when the user was created. Contact the COR to change or add roles to the user for the project.
1.2.3 Loss of Privilege
Users may lose privilege to access eCMS at the discretion of the COR and/or Contracting Officer. The eCMS is a collaborative system that allows flexibility of use and does not restrict all inappropriate user actions. User activities are logged into eCMS in visible and background
SECTION 01 31 23.13 20 Page 1 data collection. Users found to use eCMS in an inappropriate action may have their eCMS access revoked. Examples include, but are not limited to, fraudulent representations, sharing user accounts with others, and changing approved records without the consent of the COR. Depending on the severity of the infraction, the users can lose eCMS access for a period of time, permanently for the project, or lose eCMS access for any project. The contractor may appeal the suspension in writing to the Contracting Officer within 14 calendar days of notice. The appeal must identify the infraction, supporting information, and steps to ensure the infraction will not happen in the future.
1.3 SUBMITTALS
Government approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contractor's Personnel
For Division 1 government-approved Pre-Construction submittals, combine into a single Pre-Construction Submittal Package, annotated with SD Type of SD-01. Pre-Construction submittal package approval date will be used as a KPI.
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
NAVFAC eCMS requires a web-browser (platform-neutral) and Internet connection. For best results, recommend using browser in InPrivate/Incognito mode; Internet speeds greater than 40mbps when uploading files, computers with high RAM and Solid State Drives, "White List" eCMS website, Zip or Split files for better uploading. Non-NAVFAC Users are not to use VPN when using eCMS per NAVFAC IT.
The use of eCMS is required by the Contractor and all associated costs and time necessary to utilize eCMS will be borne by the Contractor with no allowance for time extensions and at no additional cost to the government.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing, and management of electronic submittals, RFIs, daily reports, and other files and will require access to the eCMS.
Project personnel roles which must be filled as applicable in the eCMS include, at a minimum, the Contractor's Project Manager (KTR-PM), Superintendent (KTSUPT), QC Manager (KTR-QC), Principal (KTR-PRIN), and Site Safety and Health Officer (KTR-SSHO). Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users.
Internal design deliberations under a D-B contract are managed outside of eCMS. Besides the D-B DOR Representative, D-B design team members are neither required nor encouraged to create user accounts in eCMS. Users are highly recommended to take eCMS live or online training prior to use.
See https://www.navfac.navy.mil/Business-Lines/Design-and- Construction/About-Us/Design-and-Construction-Documents/Electronic-
SECTION 01 31 23.13 20 Page 2
Construction-Management-System-eCMS/ for eCMS useful information
Provide the following information:
Company Name Name (First, Last) Email Address Project Role (CQM, SSHO, Superintendent, CM, PM, Principal) Existing or New eCMS User
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
In conformance with the Freedom of Information Act (FOIA), DoD INSTRUCTION
5200.48 CONTROLLED UNCLASSIFIED INFORMATION (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED INFORMATION" (CUI). NAVFAC eCMS must only be used for the transaction of unclassified information associated with construction projects.
Controlled Unclassified Identification (CUI) documents may be loaded into eCMS with the appropriate markings.
1.5.1 Markings on CUI Documents
Contractor's proprietary information, or documents determined by the originator in accordance with CUI guidance, should be marked CUI.
Proprietary information not marked CUI can be released under the Freedom of Information Act (FOIA). Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on Unclassified
(U) documents.
1.6 eCMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract. Utilize eCMS to transfer all submittals, RFIs, daily reports, and other files required by contract to be forwarded to the government.
Full eCMS use is required. All Submittals/Information to use eCMS Modules including, but not limited to, RFIs, Daily Reports, Meeting Minutes, Communications, Issues, Punch Lists, Checklists, and Flysheets, unless otherwise directed by the COR or Contracting Officer.
1.6.1 Restricted Information
Personally Identifiable Information (PII) transmittal such as credit card, driver's license, passport, social security, and payroll number are not permitted in eCMS. Name, address, and email are permitted.
Pre-negotiation information such as cost estimates that require formal negotiations are not allowed. For example, proposed changes over the SAP level of $250k require formal negotiations. Cost estimates for LEAN, ULTRA LEAN, and Design Changes under the SAP level are at the discretion of the COR's or Contract Specialist/Officer's direction. The eCMS must
SECTION 01 31 23.13 20 Page 3 only be used for the transaction of unclassified information associated with construction projects. Controlled Unclassified Identification (CUI) documents may be loaded into eCMS with the appropriate markings.
Uploading of files directly into the Documents folder is not allowed. All documents must be uploaded using an eCMS module.
1.6.2 Naming Convention for Files
Titles of files uploaded are to be descriptive of the purpose and content of the file. For example RFI_ROOF_Leak.doc or for submittals, SUB_LIGHT_FIXTURE.pdf. Titles of file to be uploaded must only contain uppercase letters, lowercase letters, numbers, hyphens (-), underscores (_), and periods (.). Use of any other characters is not allowed and may create an error. When practicable, adding the record number to the title is desired. For example RFI_XYZ12345_ROOF_Leak.doc. Uploading files with the same title will create a new revision in eCMS. Original revision is Rev 0, the first revision is Rev 1. Uploaded files are to use the default file location regardless of the module used unless directed by the COR.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration).
Table 1 - Project Documentation Types
SUBJECT/NAME REMARKS eCMS APPLICATION
As-Built Drawings Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals
Building Information Modeling (BIM)
Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals
Construction Permits Refer to rules of the issuing activity, state or jurisdiction
Submittals
Construction Schedules (Activities and Milestones)
Submittals
Construction Schedules Submittals
SECTION 01 31 23.13 20 Page 4
SUBJECT/NAME REMARKS eCMS APPLICATION
Construction Schedules (3-Week Look ahead)
Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Meeting Minutes
DD 1354 Transfer of Real Property
When applicable, required for final billing.
Submittals
Daily Production Reports
Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
Designs and Specifications
Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals
Environmental Notice of Violation (NOV), Corrective Action Plan
Refer to rules of the issuing activity, state, or jurisdiction
Submittals
Environmental Protection Plan (EPP)
Submittals
Invoice (Supporting Documentation)
Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
Redact any PII information when loaded into eCMS
Submittals
Meeting Minutes Meeting Minutes
Modification Documents Provide final modification documents for the project. Upload into Modifications RFPs folder
Communications
SECTION 01 31 23.13 20 Page 5
Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet
1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals
Photographs Subject to base/installation restrictions Submittals
QCM Initial Phase Checklists
Meeting Minutes or Checklists
QCM Preparatory Phase Checklists
Meeting Minutes or Checklists
Quality Control Plans Submittals
QC Certifications Submittals
QC Punch List Punch Lists
Red-Zone Checklist Punch List or Checklists
Rework Items List Punch Lists
Request for Information (RFI) Post-Award
RFIs
Safety Plan Submittals
Safety - Activity Hazard Analyses (AHA)
Submittals
Safety - Mishap Reports Daily Report
Shop Drawings Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals
SECTION 01 31 23.13 20 Page 6
Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)
Refer to rules of the issuing activity, state or jurisdiction
Submittals
Submittals and Submittal Register
Submittals
Testing Plans, Logs, and Reports
Submittals
Training/Reference Materials
Submittals
Training Records (Personnel)
Redact any PII information if storing in eCMS
Submittals
Utility Outage/Tie-In Request/Approval
Submittals
Warranties/BOD Letter Submittals
Quality Assurance Reports
Checklists (Government initiated)
Non-Compliance Notices Non-Compliance Notices (Government initiated)
Other Government-prepared documents
GOV ONLY
Letters to government contracting, claims, REAs, and other Contracting Officer communications eCMS is not the primary tool to use in Contracting Officer communications. eCMS can only store documents or letters after the submission to the Contracting Officer is made.
Communications
All Othere Documents Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist
As applicable
1.6.3 RFIs Module
Create contractor RFIs using eCMS RFIs module. The contractor must confirm the numbering convention with the COR if different than eCMS
SECTION 01 31 23.13 20 Page 7 default.
If the government (GOV) response has "No" Cost or Schedule Impact, this reply is given with the expressed understanding that it does not constitute a basis for any change in the amount or time of subject contract. Information provided in this response does not authorize work not currently included in the contract. If GOV Response is "Yes" or "Potentially" then this response may require a change to the contract. If the contractor disagrees with the government's No Cost and/or No Schedule impact determination, the contractor has 14 calendar days to notify the COR and Contracting Officer in writing.
1.6.4 Submittals Module
Create contractor submittals using eCMS Submittals module. The contractor must confirm the numbering convention with the COR if different than eCMS default.
1.6.5 Submittal Packages Module
Create submittal packages using the eCMS Submittal Packages module in lieu of or in addition to Related Objects. Submittal Packages track completion of the packaged submittals and is used in NAVFAC HQ's KPIs.
1.6.6 Communications Module
Create communications using the eCMS Communications module. The Communications module is used to create or document communications that are not a part of other eCMS modules. Use of Communications module will memorialize information into an eCMS record file. The following are Types of Communications:
Email Memo to File Face to Face Telephone Web Collaboration Photos Other Documents Other
Unless directed by the COR, upload documents or files that do not have a corresponding eCMS module. Choose "Photos" Type for Photos and "Other Documents" for all other documents.
1.6.7 Issues Module
Create or respond to issues using the eCMS Issues module. Respond to CPARS issues using the Issues module.
1.6.8 Meeting Minutes Module
Create or respond to Meeting Minutes using the eCMS Meetings module.
Document required contractual meetings. Dates of meetings are used in NAVFAC KPIs. Minimum meetings in eCMS include the following:
Post Award Kickoff (PAK) Pre-construction (Pre Con)
SECTION 01 31 23.13 20 Page 8
Initial and Preparatory Three Phases of Control Quality Control (QC)
1.6.9 Potential Change Items Module
Not used.
1.6.10 Daily Report Module
Create Daily Reports using the eCMS Daily Report Module. The contractor must confirm the numbering convention with the COR if different than eCMS default.
1.6.11 Punchlists Testing Logs (Legacy)
Punchlist Testing Logs is a legacy program that is being replaced by the Punch Lists Module. This module is to be used for reference of past projects. Use the Punch Lists Module for all future work.
1.6.12 Punch Lists Module
The eCMS Punch Lists module is useful more than just for Punchlists. The module includes the capability of batch editing, create items from Optical Character Recognition (OCR) plans, assign tasks, and track completion of individual items.
Create the following using the Punch Lists module:
Rework Items List DFOW List Punch-Out Inspection Pre-Final Punchlist Inspection Final Punchlist Inspection Testing Logs
1.6.13 FWD UltraLean COAR RFP Module
Not Used.
1.6.14 Non-Compliance Notices (NCN) Module
Respond to Non-Compliance Notices listed in the Non-Compliance Notices module.
1.6.15 Checklists
Use Checklist listed in the contractor's eCMS menu and as directed by the COR. Checklists capture data and is used in dashboards and KPIs.
1.6.15.1 Partnering Team Health Survey Checklist
Contractor must use the eCMS checklist to document the partnering team health survey. Partnering Team Health Survey is in accordance with the Partnering Specification of this contract.
1.6.16 Flysheets
Use Flysheets listed in the contractor's eCMS menu, if available, and as directed by the COR. Flysheets allow the contractor to print out
SECTION 01 31 23.13 20 Page 9 information from other systems and upload into eCMS. The eCMS will use OCR to capture the information as data. Flysheets capture data used in dashboards and KPIs.
1.6.17 eCMS Outage
In the case where eCMS is unavailable for 8 hours or more, paper or email may be used in the interim to maintain project schedule.
Once the system is operational, all final records are required to be recreated using the appropriate module. Subject/title of the record to include the type of record i.e., RFI/Submittal/Daily Report/Communication/Other, the identification number(s), and the statement "Processed Outside of eCMS". Example, "RFI 001 Processed Outside of eCMS".
1.6.18 User Account Activity
NAVFAC eCMS captures user data and activities that are directly related to the user's account. The user agrees through the use of eCMS, their account activities will be captured and can be displayed on eCMS printed reports.
1.7 QUALITY ASSURANCE
Requested Government response dates on Submittals must be in accordance with the terms and conditions of the Contract unless previously agreed by the COR. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.
Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.
All submittals and associated attachments must be transmitted to the Government via the COR. Transmittals are no longer required when using eCMS since approval status is tracked on the…