RISE_IDIQ_RFP_Questions_and_Answers.xlsx

XLSX spreadsheet 78 KB Posted

Attached to
Regional Integration and Stronger Economies (RISE)
Solicitation number
72062319R00003
Issued by

About this file

This document provides answers to additional questions regarding a Regional Integration and Stronger Economies (RISE) Indefinite Delivery Indefinite Quantity (IDIQ) contract opportunity with the US Agency for International Development Kenya. USAID intends to award up to five IDIQ contracts to support regional integration across trade, agriculture, policy, resilience, finance and investment in East Africa. One contract may be set aside for small businesses. The maximum value of task orders across all contracts is capped, but not allocated between awardees. Consent to subcontract will be determined at the task order level. Eligible countries include those in East Africa. Offerors have flexibility to redistribute pages between technical proposal sections as long as overall page limits are met.

RISE IDIQ RFP_Questions and Answers

View the file

Other files

File Type Posted
SF_30_Amendment_2.pdf PDF
SF_30_Amendment__01.pdf PDF
USAID_East_Africa_Stocktake_Report_2018.pdf PDF
Statusof_Tradein_FoodStaples_inEAC_briefOct2016_(7).docx DOCX document
RFP_72062319R00003-Amendment_01.pdf PDF
Attachment_J.6_-_Questions_and_Answers.xlsx XLSX spreadsheet
StatusofTrade_inFoodStaples_in_East&SouthernAfrica2018.pdf PDF
CountryProfiles_EA_Seed_Assemt_10.26._2018.pdf PDF
EA_Seed_Assessment_Report_26_October_2018.pdf PDF
USAID_East_Africa_Stocktake_Report_Annexes_2018.pdf PDF
USAID_East_Africa_Stocktake_Report_2018.pdf PDF
USAID_East_Africa_Stocktake_Report_Annexes_2018.pdf PDF
SF_30_Amendment__01.pdf PDF
Attachment_J.6_-_Questions_and_Answers.xlsx XLSX spreadsheet
Country_Profiles_EA_Seed_Assessment_26_October_2018.pdf PDF
EA_Seed_Assessment_Report_26_October_2018.pdf PDF
RFP_72062319R00003-Amendment_01.pdf PDF
Status_of_Trade_in_Food_Staples_in_EAC_brief_October_2016_(7).docx DOCX document
Status_of_Trade_in_Food_Staples__in_East_and_Southern_Africa_-_2018.pdf PDF
SF_30.pdf PDF
East_Africa_Stocktake_Report.pdf PDF
Assessment_to_Support_the_Promotion_of_Regional_Seed_Trade_in_East_Africa_(2018.10.26).pdf PDF
Status_of_Trade_in_Food_Staples_in_Eastern_and_Southern_Africa_-_Annual_Brief_(December,_2018).pdf PDF
RFP___72062319R00003_-_Amendment___1.pdf PDF
Attachment_J.6_-_Questions_and_Answers.xlsx XLSX spreadsheet
Status_of_Trade_in_Food_Staples_among_East_Africa_Community_Partner_States_-_Annual_Brief_(October,_2016).docx DOCX document
Country_Profiles_-_EA_Seed_Assessment_(2018.10.26).pdf PDF
RISE_IDIQ__RFP__72062319R00003.pdf PDF
RISE_IDIQ__Attachment_J.1__Budget_Template.xlsx XLSX spreadsheet
RISE_IDIQ__Attachment_J.3__Past_Performance_Matrix.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Amendment 2- Questions and Answers
Request for Proposal (RFP) # 72062319R00003

USAID/Kenya and East Africa (USAID/KEA) Regional Integration and Stronger Economies (RISE) Indefinite Delivery Indefinite Quantity (IDIQ)

Below are the responses to additional questions and responses that are incorporated into the solicitation through Amendment #2
The RFP has NOT been amended in response to these comments and questions
If there is any inconsistency between this document and the amended RFP issued with Amendment #1, this document takes precedence
QUESTIONANSWER
1Teaming agreements are common agreements made between the prime contractor and subcontractors within an IDIQ consortium. Responses to questions 15, 19, 20 and 113 make reference to joint ventures as well as 1) teaming agreements, 2) partnerships and 3) official teaming arrangements. Is USAID using these terms synonymously?Yes, these terms are synonymous
2Can USAID please confirm that offerors are to paste an image of the Excel matrix into the Word or PDF file of the proposal itself so that it takes no more than three pages in the proposal, and that offerors will also submit the Excel file.Confirmed, Offerors may just provide the matrix in Excel. However, the Excel file may not exceed the 3-page limit
3USAID’s response to question 4 suggests that, as along as Offerors are within the 20-page limit for RISE and the 25-page limit for RAMS, offerors are free to assign page limits to sections. However, “not to exceed” page limit language remains in the amended RFP for each section of the RISE technical proposal. Can USAID please confirm that Offerors may redistribute page allocation between sections as long as Offerors adhere to the overall 20-page limit for RISE?Confirmed, pages may be redistributed between sections as long as Offerors adhere to the 20-page limit and the section limits are not exceeded
4In reference to the response to question 35, could USAID elaborate on what non-cost factors will be used to determine best value?Please see section M of the RFP
5Page 19, Section C.3 Objectives mentions the 5 technical areas: cross border trade and market systems, access and scaling up of technologies, regional resilience, regional policy environment and finance and investment. Page 100, Section L.7(ii) 2 corporate capability, (b) notes experience managing regional trade, agriculture, policy, resilience, finance and investment. Does USAID consider the bolded items to be synonymous?No, these are related but not synonymous
6USAID states in its response to question 54 that the table in section B.6.2 had been updated. The table on page 13 of the amended RFP does not include any changes from the original RFP. Could USAID please confirm Table 2 in B.6.2 in the amended RFP is updated and correct?Yes, it is correct, the initial table was replaced with a PDF version of the same
7Question 91 states “For TO1 budget, please confirm that bidders should not propose ceiling indirect rates.” USAID’s response refers to ceiling daily rates so can USAID please confirm that offerors are not expected to build their budget using ceiling daily rates but can use rates that reflect estimated salaries of the individuals they anticipate to hire in roles provided they do not exceed proposed ceiling daily rates.Confirmed
8USAID’s response to question 15 states that consent to subcontract will be sought at the task order level.
a. Given that many prime contractors have developed a consortium for this IDIQ, does this mean USAID would like offerors to submit consent to subcontract for the same subcontractors on every task order?Consent must be sought in accordance with FAR 44.201-1
8b. Additionally, page 105 of the amended RFP still states that Part 8 of the cost proposal should include consent to subcontract and that it will be granted with the award of the RISE IDIQ. This indicates that consent will be given at the IDIQ level rather than on a task order by task order basis. Can USAID please clarify this?Please response to question 8a above
9Can USAID please clarify which countries RISE will target?Please refer to the RFP, Section F.3 Place of Performance
10In regards to question 31 in Attachment J.6_Questions and Answer, can USAID confirm that since the Past Performance must be submitted in Excel format using the provided template, it must be submitted as a separate document, similar to how budget Excel spreadsheets are submitted? If so, must offerors make sure that it is printable to three pages in order to comply with the 20-page limit of the IDIQ technical proposal or is the past performance section now exempt from that page count?Please see response to question 2 above
11If possible, please clarify the number of Awards USAID KEA intends to make under this IDIQ – is it to a single applicant, or multiple ? The language on page 1 of the RFP is unclear.

“USAID anticipates awarding up to five (5) Multiple Award Indefinite Delivery, Indefinite Quantity (“IDIQ”) Contracts. USAID anticipates one (1) of the five (5) contracts may be “set aside” for award to small business concerns … The maximum aggregate dollar value of task orders awarded to all contractors cannot exceed this contract ceiling. This ceiling is not being subdivided among the number of awardees nor is it being multiplied by the number of awardees. There is no guarantee on the number of task orders that the successful contractors will receive or the amount of money beyond the minimum order guarantee set forth in the RFP.” As stated, USAID intends to issue multiple IDIQs