This document is Amendment 02 to Request for Proposals (RFP) No. 72011524R00002 for the Green Economy Activity. The amendment clarifies the payment of fee structure for the contract. Specifically, it deletes the statement that the contract is Cost Plus Fixed Fee (CPFF), and indicates that USAID anticipates awarding a CPFF contract, but offerors are free to propose other types of awards, including Cost-No-Fee. The amendment states that since contract type can significantly impact technical performance, offerors can discuss their preferred contract type when explaining their technical approach. The overall purpose of the Green Economy Activity is to build the capacity of the Kyrgyz Republic to adapt to and mitigate the effects of climate change in its economy to develop a "green economy." The solicitation is being issued by the US Agency for International Development Central Asia Kazakhstan.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMENDMENT 03 (RFP) No. 72011524R00002.pdf | ||
| Attachment J.2 LCP Kyrgyz Republic.xlsx | XLSX spreadsheet | |
| ATTACHMENT J.3 STREAM Regional Factsheet.pdf | ||
| 72011524R00002-01.pdf | ||
| RFP 72011524R00002 Green Economy Activity.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 02 to RFP No. 72011524R00002
Clarification to the Answer to the Question #8
QUESTION 8. B.6 PAYMENT OF FEE - (a) This is a Cost-Plus Fixed Fee (CPFF) contract. The total amount of fee, if any, that can be earned has been set at the time of award and does not vary with actual cost.
Cost Reimbursement with no fee will also be considered. Can USAID review and clarify the language in Section B.6(a) of the RFP that states “This is a Cost-Plus Fixed Fee Contract” but also includes the statement that “Cost reimbursement with no fee will also be considered”. Kindly review/clarify or remove the latter statement.
ANSWER: Delete “This is a Cost Plus Fixed Fee (CPFF) contract.” at B.6.(a).
USAID anticipates the award of a Cost Plus Fixed Fee (CPFF) award, however, offerors are free to propose other types of awards, including Cost-No-Fee awards. Since contract type can significantly impact technical performance, offerors that wish to discuss contract type can do so when explaining their technical approach.