This is a Statement of Work (SOW) for drydock repairs and maintenance of the USCGC HAMMER (WLIC-75302), a 75-foot Coast Guard tender, and its associated 68-foot barge (68014). The SOW specifies 99 work items covering comprehensive vessel restoration and preservation, including hull plating renewal and inspection via ultrasonic side scan testing, underwater body and freeboard surface preservation using specified coating systems, propulsion system overhauls (shafting, seals, bearings, propellers), rudder assembly service, tank cleaning and preservation, structural repairs (welding, cracked welds, degraded welds), cathodic protection anode renewal, deck preservation with non-skid coatings, mast preservation, sea valve and strainer overhauls, spud winch and well servicing for the barge, door replacements, exhaust piping renewal, and drydocking support services. Government-furnished property includes propeller shafts, propellers, keel coolers, rudder assemblies, winch components, fathometer transducers, and replacement doors with estimated costs totaling approximately $266,000.
The contract requires compliance with Surface Forces Logistics Center (SFLC) Standard Specifications for general requirements, welding and allied processes, fire prevention and response, and ship structure preservation, along with numerous commercial standards (ASTM, SSPC/NACE, MIL-PRF, ASME, ABS) and Coast Guard technical publications. Quality assurance includes critical inspection items to be completed within the first 25 percent of the contract period, comprehensive coating thickness and surface profile measurements per SSPC-PA 2 standards, environmental monitoring, and contractor-provided fire watch personnel and environmental management. The work is to be performed at a commercial contractor facility with specifications developed as of June 2, 2026 (Revision 0), incorporating requirements for solvent cleaning, surface preparation to specified standards (SSPC-SP 10, SP-11, SP WJ-2), preservation system applications, and touch-up work matching existing adjacent surfaces per SFLC Standard Specification 6310.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 70ZU0127QPBPL0001_HAMMER_QUESTIONS.pdf | ||
| Attachment 1_ScheduleOfServices_HAMMER_DD_FY27.xls | XLS spreadsheet | |
| 70ZU0127QPBPL00010002_US signed.pdf | ||
| 70ZU0127QPBPL0001_1_US.pdf | ||
| Attachment 3 - SOW Addendum.pdf | ||
| Attachment 2_SOW_HAMMER_DD_FY27.pdf | ||
| Attachment 1_ScheduleOfServices_HAMMER_DD_FY27.xls | XLS spreadsheet | |
| 70ZU0127QPBPL0001_0_US.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC HAMMER (WLIC 75302)
USCG 68A BARGE (68014)
SPECIFICATION FOR DRYDOCK REPAIRS
FY2027
Developed By: Robert J Stankovich
(Rev-0, 2 June 2026)
USCGC HAMMER (WLIC-75A) DRYDOCK AVAILABILITY FY2027
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ........................................................................................................................................... v Consolidated List of References ................................................................................................................... vi Consolidated List of Government-furnished Property .............................................................................. xiii Consolidated List of Critical Inspection Items ............................................................................................ xv Principal Characteristics - Tender ............................................................................................................ xvii Principal Characteristics - Barge ............................................................................................................. xviii General Requirements WORK ITEM 1: Fire Prevention Requirements WORK ITEM 2: Hull Plating, Side Scan, Ultrasonic Testing - Tender WORK ITEM 3: U/W Body, Preserve, 100 percent - Tender WORK ITEM 4: Hull Plating Freeboard, Preserve, Partial - Tender WORK ITEM 5: Hull Plating Freeboard, Preserve, 100 Percent - Tender WORK ITEM 6: Hull and Structural Plating, General, 10.2 lbs. Steel, Renew - Tender WORK ITEM 7: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew - Tender WORK ITEM 8: Hull and Structural Plating, General, 15.3 lbs. Steel Plate, Renew - Tender WORK ITEM 9: Hull And Structural Plating, General, 20.4 lbs. Steel Plate, Renew - Tender WORK ITEM 10: Hull and Structural Plating, General, 7.5 lbs., 3/16 in. Steel Plate, Renew - Tender ... 40 WORK ITEM 11: Hull and Structural Plating, General, 7.65 lbs. Steel Plate, Renew - Tender WORK ITEM 12: Hull And Structural Plating, General, Cracked Steel Welds, Repairs - Tender WORK ITEM 13: Hull and Structural Plating, General, Degraded Weld, Steel, Repair - Tender WORK ITEM 14: Appendages, U/W, Leak Test - Tender WORK ITEM 15: Propulsion Shaft Rope Guards, Inspect WORK ITEM 16: Appendages, U/W, Internal, Preserve - Tender WORK ITEM 17: Voids, Non-Accessible, Leak Test - Tender WORK ITEM 18: Voids, Non-Accessible, Internal Surfaces, Preserve WORK ITEM 19: Tanks, MP Fuel Service, Clean and Inspect - Tender WORK ITEM 20: Propulsion Shafting, Strain Gage Alignment, Inspect WORK ITEM 21: Propulsion Shafting; Remove, Inspect, and Reinstall WORK ITEM 22: Propulsion Shaft Seals, Mechanical Clean and Inspect WORK ITEM 23: Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renew WORK ITEM 24: Propulsion Shaft Bearings, External, Check Clearances WORK ITEM 25: Propulsion Shaft Bearings, External, Renew WORK ITEM 26: Stern Tube Interior Surfaces, Preserve, 100 Percent WORK ITEM 27: Propeller s, Remove, Inspect, and Reinstall WORK ITEM 28: Propeller, Minor Repairs and Reconditioning, Perform WORK ITEM 29: Keel Coolers, Clean, Inspect and Hydro WORK ITEM 30: Fathometer Transducer, Renew – Tender WORK ITEM 31: Sea Valves and Waster Pieces, Overhaul Or Renew WORK ITEM 32: Sea Strainers, All Sizes, Renew WORK ITEM 33: Rudder Assembly, Remove, Inspect And Reinstall WORK ITEM 34: Rudders, Preserve, 100 Percent WORK ITEM 35: Hull Fittings (Mooring and Towing), Inspect and Test - Tender WORK ITEM 36: Sewage Holding Tanks, Clean and Inspect - Tender WORK ITEM 37: Tanks (Sewage Holding), Preserve, 100 percent - Tender WORK ITEM 38: Tanks (Sewage Holding), Preserve, Partial - Tender WORK ITEM 39: Tanks, Fuel, Preserve, 100 Percent - Tender WORK ITEM 40: Tanks, MP Fuel Service, Preserve, Partial - Tender WORK ITEM 41: Decks - Exterior, Preserve, Non-Skid MIL-PRF-24667 System, iii (Rev-0)
WORK ITEM 42: Superstructure, Preserve, 100 Percent WORK ITEM 43: Superstructure, Preserve, Partial WORK ITEM 44: Exhaust Stacks, Exterior, Preserve WORK ITEM 45: Exhaust Stacks (Exterior), Preserve - Partial WORK ITEM 46: Cathodic Protection, Zinc Anodes, Renew, - Tender WORK ITEM 47: Drydock - Tender WORK ITEM 48: Temporary Services, Provide - Tender WORK ITEM 49: Sea Trial Performance, Support, Provide WORK ITEM 50: Main Mast, Preserve, 100% WORK ITEM 51: Main Mast, Preserve - Partial WORK ITEM 52: Hull Plating, Side Scan, Ultrasonic Testing, Barge - Barge WORK ITEM 53: Hull and Structural Plating, General, 10.2 lbs. Steel, Renew - Barge WORK ITEM 54: Hull and Structural Plating, General, 12.75 lbs. Steel Plate, Renew - Barge WORK ITEM 55: Hull and Structural Plating, General, 15.3 lbs. Steel Plate, Renew - Barge WORK ITEM 56: Hull And Structural Plating, General, 20.4 lbs. Steel Plate, Renew - Barge WORK ITEM 57: Hull and Structural Plating, General, 7.5 lbs., 3/16 in. Steel Plate, Renew - Barge WORK ITEM 58: Hull and Structural Plating, General, 7.65 lbs. Steel Plate, Renew - Barge WORK ITEM 59: Hull And Structural Plating, General, Cracked Steel Welds, Repairs - Barge WORK ITEM 60: Hull and Structural Plating, General, Degraded Weld, Steel, Repair - Barge WORK ITEM 61: Appendages, U/W, Leak Test - Barge WORK ITEM 62: Appendages, U/W, Internal, Preserve - Barge WORK ITEM 63: Voids (Accessible, Weather Deck Exposed), Inspect- Barge WORK ITEM 64: Tanks, MP Fuel Service, Clean and Inspect - Barge WORK ITEM 65: Voids, Accessible, Clean and Inspect - Barge WORK ITEM 66: Accessible Voids, Preserve, 100 Percent - Barge WORK ITEM 67: Tanks, Fuel, Preserve, 100 Percent - Barge WORK ITEM 68: Tanks, MP Fuel Service, Preserve, Partial - Barge WORK ITEM 69: Accessible Voids, Preserve, Partial - Barge WORK ITEM 70: U/W Body, Preserve, 100 percent - Barge WORK ITEM 71: Hull Plating Freeboard, Preserve, Partial - Barge WORK ITEM 72: Hull Plating Freeboard, Preserve, 100 Percent - Barge WORK ITEM 73: Superstructure, Preserve, 100 Percent - Barge WORK ITEM 74: Superstructure, Preserve, Partial - Barge WORK ITEM 75: Cathodic Protection, Zinc Anodes, Renew - Barge WORK ITEM 76: Temporary Services, Provide - Barge Barge WORK ITEM 77: Sea Trial Performance, Support, Provide - Barge WORK ITEM 78: Sea Valves and Waster Pieces, Overhaul Or Renew - Barge WORK ITEM 79: Sea Strainers, Duplex, All Sizes, Overhaul - Barge WORK ITEM 80: Spuds, Overhaul - Barge WORK ITEM 81: Spud Wells, Preserve - Barge WORK ITEM 82: Spud Winches, Inspect & Service - Barge WORK ITEM 83: Spud Winch es, Renew - Barge WORK ITEM 84: Spud Wells, Inspect - Barge WORK ITEM 85: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 86: Drydock - Barge WORK ITEM 87: Boat Davit Winch, Shrink Wrap WORK ITEM 88: Buoy and Cargo Handling Crane, Shrink Wrap WORK ITEM 89: Pusher Knee Repair WORK ITEM 90: Fiddley Door, Replace WORK ITEM 91: Passageway Door, Replace WORK ITEM 92: Galley Door, Replace iv (Rev-0)
WORK ITEM 93: Crew Head Door, Reinstall WORK ITEM 94: Engine Coolant System Piping, Renew [Barge] WORK ITEM 95: Bulwark Repair WORK ITEM 96: Barge Engine Exhaust Piping, Renew WORK ITEM 97: Independent NACE Inspector (Level 3), Provide WORK ITEM 98: Tenting, Provide WORK ITEM 99: Lead-Based Paint and Asbestos-Containing Material, Perform Spot Abatement v (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
vi (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
75 WAGL 2200--008, Rev C, Steering System Arrangement For Jastram S2-16-2-35
75 WAGL 2200--009, Rev B, Flanking Steering System Arrangement For Jastram S2-16-2-35
75 WAGL 2200-010, -Rev D, Main Rudder Stock And Fittings For Jastram S2-16-2-35 Steering System
75 WAGL 2200-011, Rev D, Flanking Rudder Stock And Fittings For Jastram S2-16-2-35 Steering System
75 WAGL 2200--012, Rev D, Rudder Post Installation For Jastram S2-16-2-35 Steering System
APM: Ensure all references are latest version in CG-LIMS. If editing a WI's References, change the same ref. in the Spec's Consolidated List of References and contact the SES section chief to change the source WI. Ensure any MS Word “Comments” and Tracked Changes are removed before uploading the Spec package or delivering to CPD.
Coast Guard Drawing _________________
Coast Guard Drawing 225B WLB 601-002 Rev K, Booklet of General Drawings
Coast Guard Drawing 225B-WLB 601-001, Rev P, General Arrangements Inboard and Outboard Profiles
Coast Guard Drawing 68 CGB 0700-003, Rev. -, 68FT Steel Barge Docking Block Arrangement (“A” and “B” Class)
Coast Guard Drawing 68 CGB 1101-001, Rev -, Structural Sections and Details
Coast Guard Drawing 68 CGB 1201-001, Rev B, Deck Fittings & Spud
Coast Guard Drawing 68 CGB 2602-001, Rev A, 68 CG Barge & Stern Log Spud Well Details
Coast Guard Drawing 68 CGB 2901-002, Rev-, Tank CAPACITY - 95% Tables
Coast Guard Drawing 68 CGB-1101-1, Rev -, Structural Sections & Details
Coast Guard Drawing 68B CGB 0103-8, Rev -, General Arrangement Plan and Outboard Profile
Coast Guard Drawing 68B CGB 0103-8, Rev 1, General Arrangement Plan and Outboard Profile
Coast Guard Drawing 68B CGB 2901-004, Rev -, Curves of Form
Coast Guard Drawing 68B-CGB 1103-1, Rev C, Lines, Plating & Deck & Bottom Framing Plans
Coast Guard Drawing 68-CGB 1101-1, Rev -, Structural Sections & Details
Coast Guard Drawing 68-CGB-103-3, Rev 1, Hold Arrangement
Coast Guard Drawing 68-CGB-103-3, Rev 1, U.S. Coast Guard 68 Foot Barge Hold Arrangement
Coast Guard Drawing 68-CGB-103-4, Rev -, 68 Ft. CGB Barge Booklet of General Plans
Coast Guard Drawing 68-CGB-2901-2, Rev -, Tank Capacity Tables
Coast Guard Drawing 75 WAGL 0103-4, Rev A, Booklet of General Plans vii (Rev-0)
Coast Guard Drawing 75 WAGL 0103-4, Rev B, Booklet of General Plans
Coast Guard Drawing 75 WAGL 0500-001, Rev -, Lines and Offsets
Coast Guard Drawing 75 WAGL 0700-003, Rev -, 75FT “A” Class Towboat Docking Block Arrangement
Coast Guard Drawing 75 WAGL 0700-004, Rev A, Docking Plan
Coast Guard Drawing 75 WAGL 103-7, Rev -, Outboard Profile and Inboard Profile
Coast Guard Drawing 75 WAGL 1101-001, Rev -, Shell Expansion and Bulwark Details
Coast Guard Drawing 75 WAGL 1101-002, Rev A, Hull Structure and Main Deck Plating Plan
Coast Guard Drawing 75 WAGL 1101-003, Rev A, Hull Structure and Transverse Sections
Coast Guard Drawing 75 WAGL 1101-005, Rev -, New Grid Cooler Pocket P/S to Suit 80MDDCD
SSDG
Coast Guard Drawing 75 WAGL 1107-2, Rev -, Upper Dkhouse, Wheelhse & Stack
Coast Guard Drawing 75 WAGL 1107-3, Stack Mods to Suit 80MDDCD SSDG
Coast Guard Drawing 75 WAGL 1702-1, Rev B, Masts & Rigging
Coast Guard Drawing 75 WAGL 1906-002, Rev -, Grip Cooler - Cathodic Protection
Coast Guard Drawing 75 WAGL 2901-004, Rev +, Curves of Form
Coast Guard Drawing 75 WAGL 4103-004, Rev B, Jacket Water Mods to Suit 80MDDCD SSDG
Coast Guard Drawing 75 WAGL 4103-007, Rev B, Jacket Water Mods to Suit IF1312 MDE
Coast Guard Drawing 75 WLIC 85-1, Rev-, Booklet of General Plans
Coast Guard Drawing 75 WLIC 123-2, Rev-, Sewage Tank
Coast Guard Drawing 75 WLIC 261-1, Rev A, Diagram – FO Service Systems
Coast Guard Drawing 75 WLIC 261-2, Rev B, Arrangement – FO Service Systems
Coast Guard Drawing 75 WLIC 593-2, Rev B, Arrangement Vacuum Flush System
Coast Guard Drawing 75B WAGL 4301-005, Rev D, Shafting Installation to Suit IF 1312 MDE (VISE &
MALLET)
Coast Guard Drawing 75B WAGL 4301-006, Rev C, Shafting Installation to Suit IF 1312 MDE
(SLEDGE)
Coast Guard Drawing 75B-WAGL-1203-1, Rev -, Window Schedule & Details
Coast Guard Drawing 75B-WAGL-1203-1, Rev 2, Window Schedule & Details
Coast Guard Drawing 75D WAGL 4301-003, Rev E, Shafting Installation to Suit IF 1312 MDE
Coast Guard Drawing 75D-WAGL-1602-7, Rev -, Door Schedule & Exterior Door Details
Coast Guard Drawing 75-WAGL 4301-4, Rev -, Shafting Arrgt & Details to Suit IF1312 MDE
Coast Guard Drawing 75-WAGL 4301-4, Rev D, Shafting Arrgt & Details to Suit IF1312 MDE
Coast Guard Drawing 75-WAGL 4301-4, Rev E, Shafting Arrgt & Details to Suit IF1312 MDE
Coast Guard Drawing 75-WAGL 4301-5, Rev N, Shafting Machining Details to Suit If 1312 MDE
Coast Guard Drawing 75-WAGL 4400-3, Rev L, Propeller to Suit IF1312 MDE
Coast Guard Drawing 75-WAGL 103-006, Rev C, Booklet of Gen Plans (75301-75302)
Coast Guard Drawing 75-WAGL 1101-1, Rev -, Shell Expansion & Bulwark Dets
Coast Guard Drawing 75-WAGL 1107-01, Rev -, Main Deckhouse & Upper Deck Plating
Coast Guard Drawing 75-WAGL 1201-02, Rev -, Towing Knees
Coast Guard Drawing 75-WAGL 1202-01, Rev -, Lifelines
Coast Guard Drawing 75-WAGL 4301-5, Rev N, Shafting Machining Details to Suit If 1312 MDE viii (Rev-0)
Coast Guard Drawing 75-WAGL 4400-3, Rev L, Propeller to Suit IF1312 MDE
Coast Guard Drawing 75-WAGL-0103-8, Rev B, Booklet of General Plans
Coast Guard Drawing 75-WAGL-103-008, Rev B, Booklet of General Plans
Coast Guard Drawing 75-WAGL-3301-1, Rev -, Joiner Details
Coast Guard Drawing FL 6713-203, Rev -, CRP-V850 Transducer (SS505) Adapter Assembly
Coast Guard Drawing FL-1602-89, Rev -, Fleet 26 IN x 66 IN Weathertight Door
Coast Guard Fleet Drawing FL 2602-10, Rev R, Spud Arrangements and Details
Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
Coast Guard Fleet Drawing FL-1112-18, Rev -, HU40 Series Spud Winch Foundation
Coast Guard Drawing 75-WAGL_101_5 Firemain and Bilge Piping Diagram (75301)
Coast Guard Drawing 75-WLIC_593_3 Diagram Sewage Treatment & Discharge System
Coast Guard Drawing 75B-WAGL_101_6 Main and Auxiliary Engine Cooling Diagram
Coast Guard Drawing 68B-CGB_4801_2 Jetting Water, Bilge & Cooling
Coast Guard Drawing 68B-CGB_4801_2 Jetting Water, Bilge & Cooling
NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 0309, SWBS 311, Section C, Ship Service Diesel Generator (SSDG) Series 71 - Parts Book
Coast Guard Technical Publication (TP) 3494, 09-DEC-03, Shaft Seal - Type Fse
Coast Guard Technical Publication (TP) 3494, 2013, Shaft Seal - Type FSE
Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock Seal Type EL
Coast Guard Technical Publication (TP) 4958, Section A, Amendment 1; Mar 2011, Utility Air Winch Model HU-40 Series
Coast Guard Technical Publication (TP) 5491, SWBS 256, Apr 2013, Keel Grid Cooler (Duramax)
Fire Prevention and Response
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details
Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), Latest Version, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), Latest Version, Drydocking ix (Rev-0)
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), Latest Version, Temporary Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), Latest Version, Temporary Hull Accesses
OTHER REFERENCES
American Bureau of Shipping (ABS) 2, Rule Requirements for Survey After Construction, 2014, Part 7, Appendix Section 10, Guide for Bronze and Stainless Steel Propeller Castings
American Society for Nondestructive Testing (ASNT) SNT-TC-1A, 2020, Recommended Practice for Personal Qualification and Certification in Nondestructive Testing
American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and Welding End
APM: If work is being done in DD, no cofferdam is needed; delete cofferdam protective measures paragraph 3.1.3 and above NAVSEA ref. Above NAVSEA ref is accessible on-line
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1330, 2022, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) D1709, 2008, Standard Test Methods for Impact Resistance of Plastic Film by the Free-Falling Dart Method
ASTM International (ASTM) D1922, 2008, Standard Test Method for Propagation Tear Resistance of Plastic Film and Thin Sheeting by the Pendulum Method
ASTM International (ASTM) D3951, Reapproved 2010, Standard Practice for Commercial Packaging
ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) D5363, 2016, Standard Specification for Anaerobic Single-Component Adhesives (AN)
ASTM International (ASTM) D5363, 2024; Standard Specification for Anaerobic Single-Component Adhesives (An)
ASTM International (ASTM) D882, 2009, Standard Test Method for Tensile Properties of Thin Plastic Sheeting
ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Code of Federal Regulations (CFR) Title 29, Part 1910, Occupational Safety and Health Standards
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 40, Protection of the Environment
Commercial Item Description (CID) A-A-52624, Nov 2008, Antifreeze, Multi Engine Type, Ethylene Glycol (For Caterpillar equipment applications, use CAT Extended Life Pre-Mix coolant.)
Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Anti-seize, Zinc Dust- Petrolatum
Commercial Item Description (CID) A-A-59316, Nov 2016, Abrasive Materials for Blasting
Federal Specification (Fed Spec) HH-P-151, Mar 1991, Packing; Rubber-Sheet, Cloth-Insert x (Rev-0)
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing Tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50 m, Inclusive
International Standard For Organization (ISO) 484/2, 1981, Shipbuilding - Ship Screw Propeller - Manufacturing tolerances - Part 2: Propellers of Diameter Between 0.80 and 2.50m, Inclusive
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Steel Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2018 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves
MIL PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application
MIL PRF-16173E INT AMD 1, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application
MIL-A-18001, May 2005, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)
MIL-A-22262, Mar 1996, Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required
MIL-DTL-24244, May 2000, Insulation Material, With Special Corrosion, Chloride, and Fluoride Requirements
MIL-I-16411, Nov 1988, Insulation Felt, Thermal, Glass Fiber
MIL-PRF-16173, 2006, Corrosive Preventive Compound, Solvent Cutback, Cold Application
MIL-PRF-16173, Sep 2006, Corrosion Prevention Compound, Solvent Cut-Back, Cold-Application
MIL-PRF-16173, Sep 2006, Corrosion Preventive Compound, Solvent Cutback, Cold-Application
MIL-PRF-24647, Jan 2018, Paint System, Anticorrosive and Antifouling, Ship Hull
MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application
MIL-S-45180, 1998, Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-S-45180D, 1991; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-167-1, Nov 2005, Mechanical Vibrations of Shipboard Equipment (Type I - Environmental and Type II - Internally Excited)
MIL-Y-1140, Sep 1985, Yarn, Cord, Sleeving, Cloth, And Tape- Glass
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA- PRO-160, Nov 2011, Chapter 16, Cofferdams
NAVSEA OP 4, Thirteenth Revision, May 2023, Ammunition and Explosives Safety Afloat
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
QPL-24667, Qualified Product List (Military) of Products Qualified Under Detail Specification MIL- PRF-24667, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application xi (Rev-0)
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) G-6032, 2020 Grease, Plug Valve, Gasoline and Oil Resistant, NATO Code Number G-363, Metric
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2004, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power-Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2013, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), Power Tool Cleaning)
The Society for Protective Coatings (SSPC), Paint Application Specification No. 2 (PA-2), Procedure for Determining Conformance to Dry Coating Thickness Requirements
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by Waterjetting Prior to Recoating
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No.5, 2007, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning xii (Rev-0)
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP WJ-2/NACE WJ-2, 2017, Waterjet Cleaning of Metals – Very Thorough Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2004, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Metal Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation Standard SSPC-SP 12/NACE No. SSPC-SP 12/NACE No.5, Surface Preparation and Cleaning of Steel & Other Hard Materials by High and Ultrahigh Pressure Water Jetting Prior to Recoating
The Society for Protective Coatings SSPC-SP 10/NACE No.2, Near-White Blast Cleaning
This reference is only applicable if paragraph 3.7.2 is required.
xiii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
21 Y **Propeller shaft NSN: 2010-01-557-1512 1 ea. 19,184.17 22 N Wartsila FSE H74537-
02 Face Changeout Kit
(WLP001365-002)
NSN: 01-560-3273 2 ea. 6,690.00
23 N Wartsila FSE H74537- 02 Major Overhaul Kit
(WLP001365-001)
NSN: 01-560-3274 2 ea. 7,680.00
27 Y Propeller right hand NSN: 2010-01-534-9089 1 ea. 10,129.00 27 Y Propeller left hand NSN: 2010-01-534-9095 1 ea. 10,129.00 29 Y MDE Keel Cooler NSN: 2040-01-F11-2291 PN:
SC-418DP-114
2 $10,621.50
30 N ***Fathometer Transducer, Shallow Water, 50-200 kHz
(Airmar Technology
SS505)
NSN: 5845-01-470-2500 1 ea. 343.63
33 Y **Rudder - Steering NSN: 2040-01-530-9095 2 ea. 42,634.59 33 Y **Rudder - Flanking NSN: 2040-01-531-4393 2 ea. 51707.25 33 N **Upper Rudder bearing (SKF PN
23222CC/W33)
NSN: 3110-01-F11-2241 4 ea. 709.75
33 N Rudder EL Seal, Major Overhaul Kit (WLP-
001427001)
NSN: 5330-01-646-5935 4 ea. 3,795.62
47 Y *Transducer Cover Plate
N/A 1 ea. 50.00
83 Y Winch, Drum, Power Operated (HU40-
REMAN)
NSN: 3950-01-566-3921 3 ea. 26,767.38
86 Y *Transducer Cover Plate
N/A 4 ea. 50.00
90 N M51 DB Exterior Mark A Door, M100D
Screen, 8†Light, Stainless Steel
Hardware
Omega Products 1 ea. $3000
91 N M51 DB Exterior Mark A Door, M100D
Screen, 8†Light, Stainless Steel
Hardware
Omega Products 1 ea. $6000
92 N M51 DB Exterior Mark Omega Products 2 ea. $6000 xiv (Rev-0)
A Door, M100D Screen, 8†Light, Stainless Steel Hardware
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xv (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
2 Hull Plating, Side Scan, Ultrasonic Testing - Tender
3 U/W Body, Preserve, 100 percent - Tender
14 Appendages, U/W, Leak Test - Tender
17 Voids, Non-Accessible, Leak Test - Tender
19 Tanks, MP Fuel Service, Clean and Inspect - Tender
21 Propulsion Shafting; Remove, Inspect, and Reinstall
22 Propulsion Shaft Seals, Mechanical Clean and Inspect
23 Propulsion Shaft Seals, Mechanical Overhaul and Inflatable Renew
24 Propulsion Shaft Bearings, External, Check Clearances
25 Propulsion Shaft Bearings, External, Renew
33 Rudder Assembly, Remove, Inspect And Reinstall
47 Drydock - Tender
52 Hull Plating, Side Scan, Ultrasonic Testing, Barge - Barge
61 Appendages, U/W, Leak Test - Barge
63 Voids (Accessible, Weather Deck Exposed), Inspect- Barge
64 Tanks, MP Fuel Service, Clean and Inspect - Barge
66 Accessible Voids, Preserve, 100 Percent - Barge
69 Accessible Voids, Preserve, Partial - Barge
70 U/W Body, Preserve, 100 percent - Barge
79 Sea Strainers, Duplex, All Sizes, Overhaul - Barge
86 Drydock - Barge xvi (Rev-0)
95 Bulwark Repair
96 Barge Engine Exhaust Piping, Renew xvii (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
75' WLIC (A-CLASS), TENDER
PHYSICAL
Length overall 75' 0" Depth 7' 7-3/4" Maximum beam 22' 0" Height of highest projection 32' 0" Full load draft 4' 6" LCF Draft Full load displacement 150.20 Long Tons Fresh Water Shore tie voltage requirements N/A Frame spacing 1' 6"
HULL
Hull material Steel
MACHINERY
Number of propellers 2 Number of blades 4 Diameter of propeller 48" Pitch 40" fixed
RPM 400
Shaft diameter 4.5”
TANK CAPACITIES
Fuel tanks Fresh water tanks Lube oil xviii (Rev-0)
PRINCIPAL CHARACTERISTICS - BARGE
68’ CGB (A-CLASS: 68012 – 68014), BARGE
PHYSICAL
Length overall 68' 6-1/2" Depth 7' 0" Maximum beam 28' 0" Full load draft 3' 0" Full load displacement 117 Long Tons Shore tie voltage requirements 440 VAC / 3 Phase Frame spacing 1' 0"
1 (Rev-0)
00000_0226_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-0)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3 (Rev-0)
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Strenx 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
4 (Rev-0)
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
5 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
6 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
7 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /
TIME
8 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/AMPP No. 2
SSPC-SP WJ-2/AMPP WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
9 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
10 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE…