This is a Statement of Work (SOW) for manufacturing and delivering removeable insulation covers for the USCGC MUNRO's Gas Turbine Bleed Air Hose system. The U.S. Coast Guard requires replacement insulation materials for the anti-icing bleed air system located beneath the Main Gas Turbine Module after the original insulation was inadvertently soaked with oily water, causing smoking when the turbine operates in external temperatures above 40 degrees Fahrenheit. The contract is managed by the Department of Homeland Security U.S. Coast Guard through solicitation number 70Z8526Q025799 under PR #52000PR260025799.
The contractor must manufacture two sets of reusable insulation covers with the following specifications: inner layer dimensions of 34" length by 22" width by 2" thickness, and outer layer dimensions of 45" length by 28" width by 2" thickness. Fabrication must comply with ASTM F683-99, paragraph 8, using layers of glass fiber felt for temperatures of 450 degrees Fahrenheit and above, with inside and ends wrapped in knitted wire mesh or wire-inserted fibrous glass cloth, and the outside covered with fibrous glass cloth. Covers shall be sewn and quilted with thread for uniform thickness, strength, and rigidity. The period of performance is July 1, 2026 through July 15, 2026, with delivery to USCG Base Alameda, 1 Eagle Rd, Alameda, California 94501. The contractor shall furnish all materials, equipment, and services necessary to complete the work, with the primary place of performance at the contractor's facility. The objective is to return USCGC MUNRO to Fully Mission Capable status to minimize operational impact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Bleed Air Hose Insulation_V2 UPDATED.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: 52000PR260025799
STATEMENT OF WORK
STATEMENT OF WORK (SOW)
FOR
GAS TURBINE BLEED AIR HOSE INSULATION
CGC MUNRO has a need to replace insulation covers on the Gas Turbine Bleed Air Hose. The ship’s Main Gas Turbine is currently non-operational and has an immediate need for new insulation materials as outlined in this Statement of Work (SOW).
1.0 GENERAL
1.1 BACKGROUND
USCGC MUNRO inadvertently soaked the insulation surrounding GTBA-HOSE-1 with an oily water. The hose is for the anti-icing bleed air system located underneath the Main Gas Turbine Module. Inundated insulation causes smoking when the Gas Turbine is operated in external temperatures above 40 degrees; preventing operation of the turbine.
1.2 SCOPE
The scope of this contract is defined by the efforts and tools required to support USCGC MUNRO (WMSL 755). The Contractor shall manufacture new removeable insulation covers to the dimensions and specs provided.
1.3 OBJECTIVE
The goal is to return CGC MUNRO to Fully Mission Capable (FMC) status. This is a critical need and shall be completed as soon as possible, in order to minimize negative operational impact to MUNRO’s Operational Commander.
1.4 APPLICABLE DOCUMENTS
1.4.1 Reference Documents
The following documents may be helpful to the Contractor in performing the work described in this document:
Coast Guard Drawing (CGDWG) 750-WMSL-508-001, Rev C, JUNE 2009, Piping And Machinery Insulation Schedule And L/M (ASC508001) Coast Guard Drawing (CGDWG) 750-WMSL-259_023, Rev C, OCTOBER 2014, Bleed Air Piping & Joint Ident (P1 System) Unit 2210
2.0 SPECIFIC REQUIREMENTS/TASKS
Existing insulation cover dimensions are as follows:
| Length |
| Width |
| Thickness |
| Inner Layer |
| 34” |
| 22” |
| 2” |
| Outer Layer |
| 45” |
| 28” |
| 2” |
Fabrication of reusable covers shall comply with ASTM F683-99, PARA 8, PAGE 8. For temperature 450 degrees Fahrenheit and over the covers shall be made up of layers of glass fiber felt to make up the required thickness. The inside and ends shall be wrapped with knitted wire mesh or fibrous glass cloth “wire-inserted”. The outside shall be covered with fibrous glass cloth. Covers shall be sewn and quilted with thread to provide a uniform thickness, strength and ridigity.
3.0 OTHER APPLICABLE CONDITIONS
3.1 PERIOD OF PERFORMANCE
The period of performance for this contract shall be between 01JUL2026 & 15JUL2026.
3.2 PLACE OF PERFORMANCE
The primary place of performance will be at the contractor’s facility. After completion, contractor will deliver to USCG Base Alameda, 1 Eagle Rd, Alameda CA 94501
4.0 CONTRACTOR FURNISHED PROPERTY
The Contractor shall furnish all materials, equipment, and services necessary to fulfill the requirements of this contract.
5.0 Points of Contact
USCG-SFLC-LREPL, Asset Manager: LTJG Justin Waters, 206-827-5766, justin.l.waters@uscg.mil
6.0 Imagery
Outer Lagging Inner Lagging