This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the U.S. Coast Guard Civil Engineering Unit Providence on May 27, 2026. Amendment Number 0001 modifies solicitation 70Z0G126BCCODCH01, dated May 5, 2026, for Requisition/Purchase Request 16677450. The amendment is not extended and must be acknowledged by all potential offerors with their bid submissions. The contracting officer is located at USCG Civil Engineering Unit Providence, 475 Kilvert Street, Suite 100, Warwick, RI 02886, and can be contacted through Code 51283.
The amendment provides three substantive changes: (1) an updated Attachment 3 containing the Wage Determination (General Decision Number MA20260001 Modification Number 1, dated May 18, 2026); (2) Request for Information (RFI) responses to 14 questions regarding project completion timelines, work restrictions, cable reuse, concrete foundations, bollards, site visits, generator specifications, and cable terminations; and (3) Attachment 6 containing the Pre-Bid Site Visit Sign In Sheet. Key RFI responses clarify that contract completion is 270 calendar days from notice to proceed, existing concrete pads may be reused if new switches fit, existing cables may be cut-splice-extended inside new switches, new cable terminations are required, and existing 15kV cables should remain. The project involves replacement of existing MV switches and related electrical infrastructure. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
05/27/2026
4. REQUISITION/PURCHASE REQ.
5. PROJECT NO. (If applicable)
16677450
6. ISSUED BY CODE 51283 7. ADMINISTERED BY (If other than Item 6) CODE 51283
Contracting Officer USCG Civil Engineering Unit Providence 475 Kilvert St., Suite 100 Warwick, RI 02886
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
TO ALL POTENTIAL OFFERORS
AMENDMENT MUST BE ACKNOWLEDGED WITH YOUR BID
9A. AMENDMENT OF SOLICITATION NO.
70Z0G126BCCODCH01
9B. DATED (SEE ITEM 11)
05MAY2026
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ x ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return ___ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment amends the solicitation as followed:
1. Provide Updated Attachment 3 - Wage Determination: General Decision Number MA20260001 Modification Number 1 Dated 18 May 2026, Provide Request for Information (RFI) Responses (#1-#14) & Provide Attachment 6 - Pre-Bid Site Visit Sign In Sheet
See Continuation Page(s)
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
CAM ORMISTON
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
This solicitation is hereby amended to reflect the following changes:
1. Provide Updated Attachment 3 - Wage Determination: General Decision Number MA20260001 Modification Number 1 Dated 18 May 2026
2. Provide Request for Information (RFI) Responses (#1-#14)
3. Provide Attachment 6 - Pre-Bid Site Visit Sign In Sheet
Request for Information Responses:
Question 1: Is there a desired completion date for this project?
Response 1: In accordance with section F.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK the contract completion date is 270 calendar days after the issuance of notice to proceed.
Question 2: Are there any restrictions on when the planned outages can occur?
Response 2: This will be coordinated at the kickoff meeting and is dependent upon the issuance of the notice to proceed.
Question 3: Are there any working day / hour restrictions?
Response 3: See spec 1.2.2 Working Hours.
Question 4: The design calls for the replacement of the existing concrete foundations. If the new switches fit on the existing concrete pads, would it be acceptable to re-use?
Response 4: Yes.
Question 5: If the existing MV cables are not long enough to reach the bushings on the new MV switches, would it be acceptable to cut-splice-extend the existing cables inside the new switches, or will the cables need to be cut back to the last manhole and replaced between the MH and Switch?
Response 5: Yes, acceptable to cut-splice-extend the existing cables inside the new switches.
Question 6: Can you provide any information on the type/size of the existing MV cables?
Response 6: Everything we know is on the drawing.
Question 7: The design calls for generator support for any outage beyond 4-hours. Is there any building load / consumption data available?
Or should generators be sized based on the building transformer size?
Response 7: This will be determined in the design phase of this project.
Question 8: The design includes a detail for concrete bollards and plan drawings show bollards as existing. Could you clarify how many new bollards should be included in this proposal?
Response 8: Bollards are existing no new bollards needed unless you must remove, then You must replace. The details were provided so that you know existing conditions
Question 9: If needed, could a contractor schedule a site visit to review work and take measurement?
Response 9: Yes, coordinate with the contact specialist, Chris Hunsberger at Christopher.L.Hunsbeger2@uscg.mil.
Question 10: The drawings indicate that existing cables and conduits are to be reused. Please confirm. whether existing cable terminations are also intended to be reused, or if new terminations are required.
Response 10: New terminations are required.
Question 11: In the event that a temporary generator is required during shutdown activities, please clarify where the temporary generator is to be connected in order to provide temporary power during the shutdown period.
Response 11: This will be determined in the design phase of this project.
Question 12: Please confirm the anticipated size/capacity of the temporary generator to be carried for this application. Would a 15 kVA generator be considered?
mailto:Christopher.L.Hunsbeger2@uscg.mil
Response 12: This will be determined in the design phase of this project.
Question 13: Can you please verity if the new slabs are Pre-Cast of Cast-In-Place?
Response 13: The United States Coast Guard does not care whether it is pre-cast or cast-in-place. Refer to question 4 and response 4.
Question 14: On E-601 there are (2) “existing to remain provide 15kv cables “. Can you please clarify if we’re leaving the existing or providing new 15kv cable.
Response 14: Existing to remain.