Q&A_4.docx

DOCX document 251 KB Posted

Attached to
Drydock Repair for Coast Guard Cutter KUKUI
Solicitation number
70Z085-18-Q-P4544400
Issued by

About this file

Question & Answer 4

View the file

Other files

File Type Posted
Amendment_02-KUKUI_DD.doc DOC document
Amendment_01-KUKUI_DD.doc DOC document
Attachment_2,_Updated_Specification,_Rev_4.pdf PDF
Q&A_6.docx DOCX document
Q&A_3.docx DOCX document
Q&A_2.docx DOCX document
Q&A_5.docx DOCX document
Q&A_7.docx DOCX document
Q&A_1.docx DOCX document
KUKUI_RFQ,_May_3,_2018.zip ZIP file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A 4, Offeror’s questions will be answered by an Amendment.

1. Offeror’s questions concerning this solicitation shall be submitted in writing, and must be submitted on the attached “Request for Clarification” form. One question should be submitted per form. Each form should indicate the name of the offeror’s firm.

2. Questions may be submitted via email to Andrew.G.Jacobs@uscg.mil.

REQUEST FOR CLARIFICATION

Submit requests not later than May 18, 2018

Offeror’s Name:

Date:

Question No.

FY18 Dockside for USCGC KUKUI

RFQ Number:
70Z085-18-Q-P4544400

SOLICITATION SECTION:

PARA NO.

DEFINITE/OPTIONAL ITEM NO.
D-19
PARA NO.

TITLE:

Preserve EDG Room

QUESTION:

1. Work Item 19 identifies that one roll of electrical matting is to be government furnished. Paragraph 3.3 only directs to prepare and coat the designated deck surface in accordance with SFLC Std. Spec 6310, Appendix B for “Metal Decks – No Application of Deck Coverings”. What is the GFM for? Is the intent to have the electrical matting subsequently installed? Is underlayment required to fair and level the steel deck? If so, the directive to follow Appendix B for “Metal Decks - No application of Deck Coverings” is incorrect and should be revised. Please advise.

1. What deck covering/coatings currently exist in the EDG Room (01-78-3-E)?

RESPONSE:

The mating is to be placed in front of the switch board after the deck is painted. It does not have to be adhered and is not placed throughout the compartment just the approximately 8ft section in front of the switch board. Please see attached photo for clarification.

Attachment 4 image1.jpeg