Statement of Work Summary: US Coast Guard PAC-3DSF Dive Force Management
This is a Statement of Work (SOW) prepared by the US Coast Guard PAC-3DSF Dive Force for the offload of a hyperbaric recompression chamber (RCC) and ancillary equipment (AE) from the USCGC Polar Star at US Coast Guard Base Seattle. The contractor must provide all necessary labor, materials, equipment, and transportation to safely remove the RCC (estimated weight 30,000 lbs) from the vessel's flight deck and load it onto a commercial shipping truck for transport. The work location is US Coast Guard Base Seattle, 1519 Alaskan Way S., Pier 46, Seattle, WA 98136, with a primary performance date of April 17, 2026, and a backup date of April 18, 2026, subject to operational and weather-related feasibility.
The contractor must supply a crane with a minimum load capacity of 30,000 lbs capable of lifting at 100-150 feet from the pier and 10-20 feet above the pier, along with a certified crane operator and qualified rigger/signal person for the entire operation. If the shipping truck is delayed, the contractor shall offload the RCC and AE to a designated area on Pier 46 as directed. The contractor is responsible for coordinating with the Base Seattle Point of Contact regarding timing and scheduling, ensuring compliance with OSHA and USCG safety regulations, providing all required personal protective equipment, and submitting a written quote detailing pricing, lifting capacity, labor, and transportation. The vendor must maintain an active registration in the System for Award Management (SAM) at the time of quote submission and comply with all applicable federal, state, and local laws and regulations. A specification sheet for the RCC and AE is referenced as an attachment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REVISION 3_SOW.pdf | ||
| SF30_Amendment P00002.pdf | ||
| Solicitation_SF30.pdf | ||
| REVISION 2_SOW.pdf | ||
| ODF 26 RCC SPEC SHEET.pdf | ||
| ODF 26 LOAD OUT LIST.pdf | ||
| 70Z08426QPCAR0001.pdf | ||
| SOW.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US COAST GUARD PAC-3DSF DIVE FORCE
MANAGEMENT
STATEMENT OF WORK
OFFLOAD OF HYPERBARIC RECOMPRSSION CHAMBER AND
ANCILLARY EQUIPMENT
PREPARED BY DVC DANNY DARDER
PAC-3DSF DIVE FORCE MANAGER
TABLE OF CONTENTS
SECTION PAGES
OBJECTIVE .............................................................................. PAGE 3
SCOPE OF WORK ................................................................... PAGE 3
LOCATION OF WORK ........................................................... PAGE 3
PERIOD OF PERFORMANCE ............................................... PAGE 3
PERFORMANCE REQUIREMENTS .................................... PAGE 4
DESCRIPTION OF RCC AND AE ......................................... PAGE 4
VENDOR REQUIREMENTS .................................................. PAGE 4
POINT OF CONTACTS ........................................................... PAGE 5
ATTACHMENTS ...................................................................... PAGE 5
1. OBJECTIVES
The objective of this contract is to provide all necessary labor, materials, equipment, and transportation to safely remove the hyperbaric recompression chamber (RCC) and ancillary equipment (AE) from the USCGC Polar Star, located at US Coast Guard Base Seattle, and load it onto a commercial shipping truck for transport.
2. SCOPE OF WORK
The contractor shall:
Provide a crane with sufficient capacity and reach to safely lift the RCC and each AE
(RCC estimated weight: 30,000 lbs) from the CGC Polar Star’s flight deck to the pier and subsequently onto a commercial shipping truck.
Supply all necessary personnel, including a certified crane operator and a qualified rigger/signal person, for the duration of the operation.
Coordinate with the designated Base Seattle Point of Contact (POC) regarding the timing and location of the offload.
If the shipping truck is delayed, offload the RCC and AE to a designated area on Pier 46 as directed by the Base Seattle POC.
Provide a written quote detailing pricing, lifting capacity, labor, and transportation.
3. LOCATION OF WORK
US Coast Guard Base Seattle 1519 Alaskan Way S.
Pier 46 Seattle, WA 98136
4. PERIOD OF PERFORMANCE
The work shall be performed on April 17, 2026.
If the primary date is not feasible due to operational or weather-related issues, the backup date for performance is April 18, 2026.
The contractor shall coordinate with the Base Seattle POC to confirm the final schedule.
5. PERFORMANCE REQUIREMENTS
5.1 Crane and Equipment Specifications
Crane must have a minimum load capacity of 30,000 lbs at over 100 - 150 feet from the pier and about 10 – 20 feet above the pier to lift from the side of CGC Polar Star’s flight deck.
Contractors shall verify all lift parameters and provide confirmation in their written quote.
5.2 Personnel
Certified crane operator and qualified rigger/signal person must be present for the entire operation.
5.3 Coordination
Contractor shall coordinate with the Base Seattle POC for scheduling and designated staging area if offload to truck is delayed.
5.4 Safety
All work must be performed in accordance with OSHA and USCG safety regulations.
Contractor is responsible for site safety and shall provide all required personal protective equipment (PPE) for their personnel.
6. DESCRIPTION OF RCC AND AE
See attached specification sheet for detailed description, dimensions, and weight.
7. VENDOR REQUIREMENTS
Vendor must have an active registration in the System for Award Management (SAM) at the time of quote submission (www.sam.gov).
Vendor must comply with all applicable federal, state, and local laws and regulations.
Attachments:
RCC and AE Specification Sheet