This is an Amendment of Solicitation issued by the United States Coast Guard (USCG) Base Commercial Supplies Support (West) located at Coast Guard Island, Building 54C, Alameda, California. Amendment P00002, effective August 17, 2026, extends the solicitation closing date to August 28, 2026. The amendment references the original solicitation number 70Z08426QDL940025, dated August 6, 2026, and provides replies to additional questions received after the initial question cutoff date.
The attachment contains five questions and answers clarifying trailer specifications for what appears to be a commercial supplies support requirement. Key specifications clarified include: minimum interior height of 7 feet 0 inches; a 2-5/16 inch tow ball receiver installed at the front-center of the trailer floor with stainless-steel trim on exterior corners; interior LED lighting operating on a 120V system powered by an integrated generator, controlled by a dedicated wall switch; premium black coin flooring on both the interior floor and interior surface of the rear ramp door for slip resistance; and a steel trailer frame with aluminum walls rather than a fully aluminum construction. Offerors must acknowledge receipt of this amendment prior to the extended closing date of August 28, 2026, by completing items 8 and 15 and returning the form, acknowledging receipt on each copy of their offer, or by separate letter or electronic communication referencing the solicitation and amendment numbers.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Standard Form 30 - Amendment P00001.pdf | ||
| Revision 1_Statement of Work MSRTW Trailer.pdf | ||
| Statement of Work MSRTW Trailer.pdf | ||
| Solicitation_70Z08426QDL940025.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
P00002
Terry Craft
This amendment is issued to provide replies to additional questions received after the cutoff date for questions/clarifications that was deemed relevant to this requirement (Attachment 1).
Closing date is extended to 8/28/2026
70Z084 USCG Base Commercial Supplies Support (West), Coast Guard Island, Bldg 54C Alameda, CA, 94501
Same as issued by
70Z08426QDL940025
1 1
08/17/2026
08/06/2026
08/17/2026
Attachment 1
Additional Question & Answers
1. The Statement of Work does not specify a minimum interior height. Would an interior height of 6 feet 10 inches be acceptable?
Minimum interior height: 7ft 0in
2. Section 3.1 requires an “integrated winch plate and stainless-steel trim on all corners.” Please confirm whether the Government requires one winch plate installed at the front-center of the trailer floor and stainless-steel trim installed on the exterior around each corner of the trailer.
We don’t need a winch plate to install a winch to “pull something out” as in getting a vehicle unstuck, but we do have a 2-5/16 inch tow ball on our trucks and need the appropriate sized receiver on the trailer so we can hook the trailers up to the tow ball on our F-450 trucks and tow the trailers behind them, which needs to be installed at the front-center of the trailer floor, and stainless-steel trim installed on the exterior around each corner of the trailer.
3. Section 3.3 requires overhead LED lighting throughout the interior, controlled by a dedicated wall switch. Should the interior lighting operate on a 120V system powered by the integrated generator, or on a separate 12V system?
Yes, the interior lighting should operate on a 120V system powered by the integrated generator.
4. Section 3.3 requires premium black coin flooring for slip resistance and durability.
Should the same black coin flooring also be installed on the interior surface of the rear ramp door?
Yes, the same black coin flooring should also be installed on the interior surface of the rear ramp door (prevents slips/falls when loading/off-loading gear to and from the trailer).
5. Can you tell me if you are looking for a fully aluminum trailer or just the exterior walls?
Steel trailer frame with aluminum walls.
| 2026-08-17T14:16:25-0700 | |
| CRAFT.TERRY.E.1273021260 |