This is a Statement of Work (SOW) for the U.S. Coast Guard Maritime Security Response Team (MSRT) West for the purchase of eight customized ISU-90 shipping containers designed to rapidly and safely transport dive locker equipment and capabilities worldwide.
The vendor must provide four pairs of customized ISU-90 containers configured as follows: (1) Clean Gear configuration for chamber support equipment including tool boxes, spare parts, technical manuals, oxygen kits, AED devices, and chamber kits; (2) Dirty Gear configuration for high-pressure compressors, generators, voltage step-down transformers, and diesel containers; (3) SCUBA and SSDS support equipment configuration with tank racks, communication consoles, umbilicals, and dive support tool kits; and (4) Inflatable boat configuration containing two F470 RIB boats (15'5" long, 6'3" beam) with 90-horsepower outboard engines each. All containers must feature hard tie-downs for heavy equipment and shelving to maximize usable space. Four containers ship to Regional Dive Locker West in National City, California, and four ship to Regional Dive Locker East in Portsmouth, Virginia. Shipping, handling, and assembly costs must be included in the quote. The SOW includes detailed photographs and dimensions of all equipment to be loaded, including compressors, generators, hydraulic equipment, welding machines, SCUBA tanks, umbilicals, rigging lines, communication boxes, tool kits, and personnel gear bags. This is a tax-exempt U.S. Government transaction.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30 - A0001.pdf | ||
| Questions v1.pdf | ||
| Schedule - MSRT Containersv1.xlsx | XLSX spreadsheet | |
| SOW ISU 90s and reqs -.pdf | ||
| 70Z08426QDL940003_0_US -.pdf | ||
| Schedule - MSRT Containers.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. JUSTIFICATION:
RDLW and RDLE need to purchase customized Brand Name or Equal to ISU-90 shipping containers that are fully customized to rapidly and safely transport the dive lockers full scope of capabilities worldwide.
2. SCOPE OF SERVICES:
Vendor will provide 8 customized Brand Name or Equal to ISU-90’s per the following specifications (see table). Shipping, handling and assembly to be included in the quote and components will ship to Regional Dive Locker West and Regional Dive Locker East.
Item # Type Parts Number Description Qty Ordered
1 Sale TBD ISU 90 CLEAN
GEAR
(CHAMBER
SUPPORTING
EQUIPMENT)
2 ea.
2 Sale TBD ISU 90, DIRTY
GEAR
(CHAMBER
2 ea.
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
U.S. Coast Guard Maritime Security Response Team, MSRT West (34269) Regional Dive Locker West
1022 Bay Marina Dr.
Suite 106
National City, CA 91950
STATEMENT OF WORK FOR THE PURCHASE OF
RAPIDLY DEPLOYABLE RECOMPRESSION CHAMBER/DIVE SUPPORT BRAND
NAME OR EQUAL TO: ISU-90 SHIPPING CONTAINERS
SCOPE OF WORK FOR US COAST GUARD MSRT WEST
SUPPORT, HIGH
PRESSURE)
3 Sale TBD ISU 90, SCUBA &
SSDS
SUPPORTING
EQUIPMENT
2 ea.
4 Sale TBD ISU 90, (2) F470
INFLATABLE
BOATS
2 ea.
5 Shipping 99999026 Container Freight to National City, CA 91950
1 ea.
6 Shipping 99999026 Container Freight to Portsmouth, VA 23703
1ea.
3. DELIVERY LOCATION
REGIONAL DIVE LOCKER WEST
1022 Bay Marina Dr.
Suite 106 National City, CA 91950
REGIONAL DIVE LOCKER EAST
4000 Coast Guard BLVD.
Portsmouth, VA 23703
4. This is a U.S. Government transaction and is tax exempt.
ISU-90 Configuration. RDLW/RDLE Note: all ISU’s must have hard tie downs for heavy equipment. All space in ISU must have a purpose or a shelf. We are looking for compatibility.
Shipping information.
A. RDLW, ISU-90 One, Two, Three and Four Configuration. (1-4) ISU-90 Total.
The four ISU’s will be shipped to:
a. CONTAINER FREIGHT TO NATIONAL CITY, CA 91950 B. RDLE, ISU-90 One, Two, Three and Four Configuration. (1-4) ISU-90 Total.
The four ISU’s will be shipped to:
a. CONTAINER FREIGHT TO PORTSMOUTH, VA, 23703
1. Eight ISU-90’s to be configured in the following manor. i.e. ISU-90 (One), two each.
ISU-90 (Two) Two each and so forth.
a. ISU-90 (One), Clean Gear, ISU-90 used for Chamber support equipment.
i. Side A. Small Parts Cabinets 8-Drawer 86019-009
1. Two chamber tool boxes. See Fig-10
2. Support equipment, parts for the chamber and three Scruber
Canisters. 8-Drawer Cabinet? See Fig-15 and 16
3. Tech Manuals. Two Drawers?
4. Oxygen and HP air charging hoses. See Fig-19
5. Oxygen Kit See Fig-9
6. AED, this is a small medical device used to shock and restart the heart in the event of an emergency. Small footprint.
7. Chamber Kits A and B. See Fig-22
8. TRCS Door (3) Strong Backs See Fig-17
9. TRCS Nato Rig Protectors. See Fig-14
ii. Side B.
1. TRCS TL Patients Skid Fig-13
2. Dive Crews Gear. Four Personnel See Fig-37 mailto:Ted.d.walker@uscg.mil mailto:manuel.e.severino@uscg.mil mailto:daniel.l.waddell@uscg.mil
3. Mission Gear Load Out. Various. Box 1 is referring to ancillary gear related to the Recompression Chamber. These items may include personal gear bags and other portable items of similar size.
b. ISU-90, (Two), Dirty Gear, used for Chamber Support Equipment. High Pressure Compressor, Generator.
i. Side A & B. Note: heavy equipment is placed on the bottom. Tie- Downs required.
1. Chamber Compressor. See Fig-1
2. Chamber Generator. See Fig-2
a. 440/220 Volts Step down for RCC support See Fig-5
b. Dolly See Fig-36
3. PAM VAN/ISO lifting Slings. See Fig-41
4. PAM VAN Power Cord. See Fig-18
5. PAM VAN Lighting Rod Kit. See Fig-23
ii. Side B.
1. (Two) 5 Gallon Diesel Containers.
2. Lifting Slings for the TRC and TL only. See Fig-29
3. TRC Cover See Fig-30
4. TL Cover See Fig-30
5. (3) TRC Wheels. See Fig-
6. (4) TL Wheels. See Fig-
c. ISU-90, (Three), SCUBA and SSDS Support Equipment.
i. Side A.& B. Note: heavy equipment is placed on the bottom. Tie-
Downs required.
ii.
1. SCUBA Tanks Racks. Required, four sets of Double Tanks and twelve signal tanks. See Fig-11
2. XLDS Consol See Fig-24
3. (2) XLDS 1 and 2 support boxes. See Fig-28
4. (1) CAOS Rack. See Fig-25
5. (3) 300’ umbilical’s. See Fig-32
6. XLDS Communication. Box See Fig-42
7. XLDS Support Kit. Fig-43
8. Dive Support Tool Kits See Fig-26
9. Dive Accommodation Ladder. See Fig-27
iii. Side B.
1. Dive Personnel gear. Ten See Fig-37
d. ISU-90, (Four), (2) F470 inflatible boats. Boats are 15’”5 (4.7 meter) Long inflatble RIB boat with a beam of 6’3” (1.9 meters).
i. Side A & B. Note: heavy equipment is placed on the bottom. Tie-
Downs required.
ii.
1. Boat One
2. 90hp outboard Engine
3. Boat Two
4. Engine Two, see line item 2.
Information related to equipment that will be loaded into each
ISU.
High Pressure Compressor for Recompression Chamber
Measurements: L47” x W33” x H36”
Weight: 440 lbs.
Fig-1
Generator for Recompression Chamber
Measurements: L44” x W29.5 x H
Weight:?
Fig-2
Support Equipment RCC Bison Emergency HPU Pumps
Measurements: L28” x W29” x H19.5”
Weight: ?
Fig-3
Bison HPU, support equipment for RCC lift system
Measurements: L26” x W31” H23”
Fig-4
440/220 Volts Step down for RCC support
Measurements: L17” x W26” x H45”
Fig-5
Hydraulic QPAK
L55” x W39” x H41” without the wheels
L48” x W41” x H38” with the wheels
Weight: GVRW 960 lbs
Fig-6
Blue Miller Welder
L44” x W31” x H46.5”
Fig-7
Hydraulic Hose Real
L34” x W39” x H42”
Weight: GRWT 465 lbs
Fig-8
Oxygen Kit
L25” x W21” x H9”
Weight: GRWT ? lbs
Fig-9
Two Chamber Toolbox’s. Note: Both kits are the same size.
L24” x W15” x H18.5”
Fig-10
SCUBA Tanks
L26” x W17.5” x H30” Six SCUBA Tanks
Fig-11
Dive First Aid Kit
L32” x W” x H12”
Weight: GRWT lbs
Fig-12
TRCS TL Patients Skid
L58.5” x W23” x H6”
Fig-13
TRCS Nato Ring protectors
L34” x W16” H3”
Fig-14
CO2 Scrubber Canister
Three Canisters L9.5” x C6”
Fig-15
Spare Parts for the Chamber
Several dozen such packages.
Fig-16
TRCS Door Three Strong backs
L28” x W2” x H5”
Fig-17
PAM VAN Power Cord
Fig-18
Oxygen Hoses
Fig-19
Medical Kit
L12” x W8” x H8”
Fig-20
Chamber Supervisor Kit
L20” x W12.5” x H18”
Fig-21
Chamber Primary Kit A and B
L24” x W19” x H12”
Fig-22
Lightning Rod Kit for the PAM VAN
L44” x C5”
Fig-23
XLDS Console
L29” x W27” x H15”
Fig-24
CAOS RACK
L41.5” x W36” x H19”
Fig-25
Dive Tool Kits
L23” x W17” x H 33”
Fig-26
Accommodation Ladder.
Fig-27
(2) XLDS Kit-1 and 2
L34” x W30” H17.5”
Fig-28
Lifting Slings for TRC and TL
Fig-29
(2) Covers for TL and TRC
Fig-30
XLDS Support Hoses and Manifold
Fig-31
(3) XLDS Umbilical’s
L41” x W32” x H16”
Fig-32
General Lines for rigging.
Fig-33
Canopy
L21” x W13” x H65”
Fig-34
Dolly
Fig-36
Dive Crew Bag
L44” x W25” x H17”
Fig-37
TRCS Wheels
(6)
(1)
Fig-38
Dive Streator
Fig-39
Books and Manuals
Fig-40
PAM VAN Lifting Slings
L34” x W30” x H18”
Fig-41
XLDS Communication Box
L15.5 x W13” x H7”
Fig-42
XLDS Support Kit
L17” x W9” x H13”
Fig-43