TE-3 REQUIRED DELIVERY DAYS.pdf
PDF 467 KB Posted
- Solicitation number
- 70Z08424RWOPL0003
About this file
This document is a technical exhibit that specifies the required delivery days for the overhaul and outfitting of various types of buoys under a federal contract opportunity with the U.S. Coast Guard.
The document outlines the calendar day requirements for completing the overhaul and color change of different buoy types, with the largest or single buoy requiring 26 calendar days and subsequent buoys requiring fewer days, ranging from 2 to 8 days. Examples are provided for calculating the total delivery days when multiple buoys are included in a single task order. The delivery timeline starts from the date of the task order, with any delay in the availability of the buoy affecting the required delivery date.
This technical exhibit is associated with the federal contract opportunity for "Buoy Overhaul and Maintenance for Coast Guard District 13," solicitation number 70Z08424RWOPL0003. The U.S. Coast Guard is the responsible federal agency for this contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4. - Past Performance Questionnaie (revised).docx | DOCX document | |
| TE-4_Estimated Color Schemes (revised).pdf | ||
| Amendment 00001.pdf | ||
| Drawings.pdf | ||
| Solicitation 70Z08424RWOPL0003.pdf | ||
| Attachment 2. Schedule of Services.xls | XLS spreadsheet | |
| TE-5 FOAM BUOY REPAIR.pdf | ||
| TE 1a_PRS_2020.pdf | ||
| Attachment 4. - Past Performance Questionaire.docx | DOCX document | |
| Attachment 5 - Reserved for SCA Wage Determination.pdf | ||
| TE-4 _Estimated Color Schemes.pdf | ||
| TE 1b_QASP_2020.pdf | ||
| Attachment 3. Spec 507-B.pdf | ||
| Attachment 1 - PWS.pdf | ||
| TE-2_GFP.pdf | ||
| TE-6_Forms.pdf | ||
| Attachment 6 -Drawings.pdf | ||
| Solicitation 70Z08424RWOPL0003.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0002
TECHNICAL EXHIBIT 3
REQUIRED DELIVERY DAYS
The Contractor is required to complete the overhaul and/or outfitting of the buoy, to included transportation within the number of calendar days. If a buoy is not available for overhaul at the time of the work request, the delivery date shall be determined using the date the buoy is actually available. The date of the task order shall be the basis for determining the required delivery date. See examples below for calculating multiple buoys on a task order.
CLIN Buoy type Work required Calendar days for largest or a single buoy
*Calendar days for each subsequent buoy
OOO1AA
9X35LWR
Overhaul 26 8 Color Change 11 4
OOO1AB
9X32LR and 9X32LBR
Overhaul 26 8 Color Change 11 4
OOO1AC
9X20BR/GR
Overhaul 26 8 Color Change 11 4
OOO1AD
8X26LBR, 8X26LGR,
8X26LR, 8X26LWR
Overhaul 26 8 Color Change 11 4
OOO1AE
8X21LBR and 8X21LR
Overhaul 26 8 Color Change 11 4
OOO1AF
7X20L1
Overhaul 26 8 Color Change 11 4
OOO1AG
7X17LR
Overhaul 26 8 Color Change 11 4
OOO1AH
6X20LBR and 6X20LR
Overhaul 16 4 Color Change 10 3
OOO1AJ
5X11LNR and 5X11LCR
Overhaul 16 4 Color Change 10 3
OOO1AK
INR and ICR
Overhaul 16 4 Color Change 10 2
OOO1AL
2NR and 2CR
Overhaul 10 3 Color Change 8 2
OOO1AM
3NR and 3CR
Overhaul 10 2 Color Change 8 2
OOO1AN
5NR and 5CR
Overhaul 10 2 Color Change 8 2
OOO1AP
3NI and 3C1
Overhaul 10 2 Color Change 8 2
OOO1AQ 5NI and 5C1 Overhaul 10 2
Color Change 8 2 OOO1AR 5X9LFR Overhaul 10 2 OOO1AS 2NFR and 2CFR Overhaul 10 2 OOO1AT 3NFR and 3CFR Overhaul 10 2 OOO1AU 4NFR and 4CFR Overhaul 10 2
* Used when there are multiple buoys on one task order.
AMENDMENT 0002
Example 1: Task order for (1) 9x35, (10) 2NR, and (3) 7x20L1.
(1) 9x35 26 Days (includes shipping days)
(10) 2NR 10 x 3 = 30 Days (no shipping)
(3) 7x20 u 3 x 8 = 24 days (no shipping)
Total Days:
80 days to deliver buoys
Example 2: Task order for (60) 1 NR
(1) INR 16 Days (includes shipping)
(59) INR 59 x 4 = 236 days (no Shipping)
Total Days:
252 days to deliver buoys