19PAT001 Specifications of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19PAT001_OF_1419_&_OF1419A_Bid_Abstract_12_19_18.pdf | ||
| RFI_Responses_12_14_18_(2).docx | DOCX document | |
| 19PAT001_A00002_SF30_Signed.pdf | ||
| RFI_Responses_12_14_18.docx | DOCX document | |
| 19PAT001_A00001_SF30_Signed.pdf | ||
| 8648736-DWG_R1-Airfield_Pavement_Maintenance.pdf | ||
| IFB_18PAT001.doc | DOC document | |
| 19PAT001_SF1442_original.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
AVIATION TRAINING CENTER MOBILE,
ALABAMA 36608-8322
SPECIFICATIONS
FOR
SAM PN: 8648736
AIRFIELD PAVEMENT MAINTENANCE
AT
AVIATION TRAINING CENTER
MOBILE, AL
OCTOBER 16, 2018
Airfield Pavement Maintenance 8648736
Pa ge
Table of Contents
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00 SUMMARY OF WORK
SECTION 01 14 00 WORK RESTRICTIONS
SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS
SECTION 01 33 00 SUBMITTAL PROCEDURES
SECTION 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
SECTION 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
SECTION 01 78 00 CLOSEOUT SUBMITTALS
DIVISION 03 - CONCRETE
SECTION 03 01 30.71 CONCRETE REHABILITATION
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
SECTION 32 11 16.13 SAND-CLAY SUBBASE COURSE
SECTION 32 11 20 BASE COURSE FOR RIGID PAVING
SECTION 32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY
PAVEMENTS
SECTION 32 16 15 CONCRETE BLOCK PAVEMENTS
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00 Page 1
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00 SUMMARY OF WORK
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
BASE BID: Aircraft Concrete Joint sealant: Saw or mechanically remove existing joint material and prepare joints for application of FAA approved material suitable for aircraft operations and defined within specifications.
BASE BID: Aircraft Concrete Pavement Replacement: Remove and replace the full depth of indicated concrete panels at the GSE buildings access pad and laydown area. Remove and replace concrete panels on the northern side of the fuel farm parking shed. Cut remove and replace portions of 2 concrete panels within the GST hangar access drive. Both the current and new pavement section are comprised of Portland cement concrete pavement reinforced with welded wire fabric.
In general, lay out and mark all areas of replacement identified in these documents. Demo and remove areas to be replaced to the nearest joint or saw cut. Dispose of all debris off site. Cut panels full depth to produce vertical edges. Install forms as necessary to retain and support concrete. Roll existing sub grade materials to achieve maximum density.
Install full depth entrained concrete to match existing adjacent concrete as specified within. Install expansion joint material. Install crack control joints where applicable and indicated. Apply curing compound and or provide protection against elements necessary to promote curing of new installation.
BASE BID: Aircraft Concrete Crack Repair: Remove all unsound concrete, down to solid concrete as specified. Repair as indicated.
BID OPTION 1: Storm Water Ditch Repair: Remove and replace the full depth of the indicated concrete panels at the upper pond dike. Replace with geotextile and interlocking matrix of cellular concrete blocks.
BID OPTION 2: MWR Concrete Drive: Remove and replace 6-inch-thick concrete driveway for Bldgs. S35 and S53. Replace with compacted base and 6 inch pad. Increase turning radius of north pad by adding 10 linear feet.
1.1.2 Location
The work is located at the Aviation Training Center, 8501 Tanner Williams Road, Mobile AL 36608.
1.2 CONTRACT DRAWINGS
The following drawings accompany this specification and are a part thereof.
Drawing No. S398772479G001 S398772479C101 S398772479C102 S398772479C103 S398772479C401 S398772479C402 S398772479C403 S398772479C501
Two sets of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the COR a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
SECTION 01 11 00 Page 2
SECTION 01 11 00 Page 3
1.5.1 Notification Prior to Excavation
Notify the COR at least 15 days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 14 00 Page 1
SECTION 01 14 00 WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Contracting Officer/COR approval is required for submittals Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The COR will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period, between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires COR approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the COR.
SECTION 01 14 00 Page 2
1.2.4 Occupied Building[s]
The Contractor shall be working around existing buildings which are occupied.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the COR.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, and fire alarm, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, and electrical. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the COR giving reasonable advance notice when such operation is required.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 1
SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
1.2 SUPERVISION
1.2.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.2.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.10 20 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.2.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
SECTION 01 30 00 Page 2
1.3 PRECONSTRUCTION
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer and COR to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work. Major subcontractors who will engage in the work must also attend.
1.4 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer and COR a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
SECTION 01 33 00 SUBMITTAL PROCEDURES
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work).
Certificates of insurance
Surety bonds
List of proposed Subcontractors
List of proposed products
Construction progress schedule
Submittal register
Schedule of prices or Earned Value Report
Health and safety plan
Work plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
SD-04 Samples
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
SD-05 Design Data
SD-06 Test Reports
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
SECTION 01 33 00 Page
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.1.2 Approving Authority
Office or designated person authorized to approve submittal.
1.1.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Contracting Officer/COR approval is required for submittals. Submit the following in accordance with this section.
Submittal Register; G
1.3 SUBMITTAL REGISTER AND DATABASE
Prepare and maintain submittal register, as the work progresses. Use electronic submittal register program furnished by the Government or any other format. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.
Column (f): Indicate approving authority for each submittal.
The database and submittal management program will be furnished to Contractor via email upon request.
1.3.1 Use of Submittal Register
Submit submittal register as an electronic database, using submittals management program furnished to Contractor. Submit with QC plan and project schedule. Verify that all submittals required for project are listed and add missing submittals.
1.3.2 Contractor Use of Submittal Register
Update the following fields with each submittal throughout contract.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) List date of submittal transmission.
Column (q) List date approval received.
1.3.3 Approving Authority Use of Submittal Register
Update the following fields.
Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.
Column (l) List date of submittal receipt.
Column (m) through (p) List Date related to review actions.
Column (q) List date returned to Contractor.
1.3.4 Copies Delivered to the Government
Deliver one copy of submittal register updated by Contractor to Contracting Officer/COR with each invoice request. Deliver in electronic format, unless a paper copy is requested by Contracting Officer.
1.4 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received from QC Manager.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date submittals.
1.4.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
1.5 DISAPPROVED OR REJECTED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the
Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.6 STAMPS
Stamps used by the Contractor on the submittal data to certify that the submittal meets contract requirements is to be similar to the following:
| CONTRACTOR |
| (Firm Name) | | Approved | | Approved with corrections as noted on submittal data and/or | | attached sheets(s) |
| SIGNATURE: |
| TITLE: |
| DATE: |
Print Form Save As E-mail
U.S. Army Corps of Engineers (USACE)
TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR
MANUFACTURER'S CERTIFICATES OF COMPLIANCE
For use of this form, see ER 415-1-10; the proponent agency is CECW-CE.
DATE TRANSMITTAL NO.
SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)
TO: FROM: CONTRACT NO. CHECK ONE:
THIS IS A NEW TRANSMITTAL
THIS IS A RESUBMITTAL OF
TRANSMITTAL
SPECIFICATION SEC. NO. (Cover only one section with each transmittal) PROJECT TITLE AND LOCATION THIS TRANSMITTAL IS FOR: (Check one)
FIO GA DA CR
DA/CR
DA/GA
ITEM
NO.
(See
Note 3)
DESCRIPTION OF SUBMITTAL ITEM
(Type size, model number/etc.)
SUBMITTAL
TYPE CODE
(See Note 8)
NO.
OF
COPIES
CONTRACT DOCUMENT
REFERENCE
CONTRACTOR
REVIEW
CODE
VARIATION
Enter "Y" if requesting a variation
(See Note 6)
USACE
ACTION
CODE
(Note 9)
SPEC.
PARA. NO.
DRAWING
SHEET NO.
a. b. c. d. e. f. g. h. i.
REMARKS I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.
NAME OF CONTRACTOR
SIGNATURE OF CONTRACTOR
SECTION II - APPROVAL ACTION
ENCLOSURES RETURNED (List by item No.) NAME AND TITLE OF APPROVING AUTHORITY SIGNATURE OF APPROVING AUTHORITY DATE
ENG FORM 4025, MAY 2017 PREVIOUS EDITIONS ARE OBSOLETE. Page 1 of 2
Print Form Save As E-mail
INSTRUCTIONS
1. Section I will be initiated by the Contractor in the required number of copies.
2. Each Transmittal shall be numbered consecutively. The Transmittal Number typically includes two parts separated by a dash (-). The first part is the specification section number. The second part is a sequential number for the submittals under that spec section. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.
3. The "Item No." for each entry on this form will be the same "Item No." as indicated on ENG FORM 4288-R.
4. Submittals requiring expeditious handling will be submitted on a separate ENG Form 4025-R.
5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.
6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column h, and enter a statement in the Remarks block describing he detailed reason for the variation.
7. ENG Form 4025-R is self-transmitting - a letter of transmittal is not required.
8. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.
Submittal types are the following:
SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports
SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout
9. For each submittal item, the Contractor will assign Submittal Action Codes in column g of Section I. The U.S. Army Corps of Engineers approving authority will assign Submittal Action Codes in column i of Section I. The Submittal Action Codes are:
A -- Approved as submitted. F -- Receipt acknowledged.
B -- Approved, except as noted on drawings. Resubmission not required. X -- Receipt acknowledged, does not comply with contract requirements, as noted.
C -- Approved, except as noted on drawings. Refer to attached comments. G -- Other action required (Specify)
Resubmission required. K -- Government concurs with intermediate design. (For D-B contracts) D -- Will be returned byseparate correspondence. R -- Design submittal is acceptable for release for construction. (For D-B contracts) E -- Disapproved. Refer to attached comments.
10. Approval of items does not relieve the contractor from complying with all the requirements of the contract.
ENG FORM 4025, MAY 2017 Page 2 of 2
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION
Airfield Pavement Maintenance
A C T I V I T Y
N O
R A N S M I T T
L
S P E
DESCRIPTION
ITEM SUBMITTED
R A G # R A
H
G
V
C T L A O S R S I A F / I E C A R T E I V O W N R
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH
REMARKS
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
T I
D
DATE
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
TO OTHER
REVIEWER
DATE RCD
FROM OTH
T I
ACTION
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 14 00 SD-01 Preconstruction Submittals
List of Contact Personnel 1.2.1.1 G 01 33 00 SD-01 Preconstruction Submittals Submittal Register 1.3 G 01 45 00.10 20 SD-01 Preconstruction Submittals QC Plan 1.6 G 01 78 00 SD-11 Closeout Submittals As-Built Drawings 3.1 G Record Drawing 3.2 G 03 01 30.71 SD-05 Design Data Job-Mix Formula 1.4.1.1 G SD-06 Test Reports Epoxy Resin Binder 2.1.1.1 G SD-08 Manufacturer’s Instructions Epoxy 2.1.1 G 32 01 19 SD-03 Product Data Equipment 3.1 SD-04 Samples Material 2.3 G SD-06 Test Reports Certified Copies of the Test 1.3.1 G Reports 32 11 16.13 SD-06 Test Reports sieve and particle size analysis 3.4.2.1 G sieve and particle size analysis 3.4.2.1 G Liquid limit 2.1 G
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES
TITLE AND LOCATION
T I V I
A N S M I T T
R A G # R A
V
C T L A O S R S I A F / I E C A R T E I V O W N R
CONTRACTOR:
SCHEDULE DATES
CONTR/
DATE RCD
T I
AUTH/
DATE RCD
T I
ACTION
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
32 11 16.13 Plasticity index 2.1 G California Bearing Ratio 2.1 G
Smoothness test 3.4.2.2 G
Field density tests 3.4.2.3 G
Laboratory density tests 3.4.2.4 G
Thickness tests 3.4.2.5 G
32 11 20 SD-03 Product Data
Plant, Equipment, and Tools 1.4 G
SD-06 Test Reports
Initial Tests 2.2.1 G
In-Place Tests 3.9.1 G
Test Results 1.5 G
32 13 14.13 SD-03 Product Data
Diamond Grinding Plan 2.1.6 G
Dowels 2.7.1 G
Dowel Bar Assemblies 2.7.2 G
Equipment 2.9
Proposed Techniques 3.1.2 G
SD-06 Test Reports
Batch Plant Manufacturer's 1.3.1 G
Inspection Report
Sampling and Testing 1.3.5.2 G
Sampling and Testing 2.1.3.1 G
Diamond Grinding of PCC 2.1.6 G
Surfaces
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES
TITLE AND LOCATION
T I V I
A N S M I T T
R A G # R A
V
C T L A O S R S I A F / I E C A R T E I V O W N R
CONTRACTOR:
SCHEDULE DATES
CONTR/
DATE RCD
T I
AUTH/
DATE RCD
T I
ACTION
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
32 13 14.13 Mixer Performance (Uniformity) 2.9.2.3 G Testing
Survey 2.1.2
Certified Copies Of Laboratory 2.1.3
Test Reports
Report 3.9.1
SD-07 Certificates
Contractor Quality Control Staff 1.3.1 G
Laboratory Accreditation and 1.3.2
Validation
Commercial Laboratory 1.3.2.2 G
32 16 15 SD-04 Samples
Concrete Paving Block 2.1.2 G
SD-06 Test Reports
Tests, Inspections and 2.2
Verifications
SECTION 01 42 00 Page
SECTION 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.
1.2 ORDERING INFORMATION
The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
444 North Capital Street, NW, Suite 249 Washington, DC 20001 Ph: 202-624-5800 Fax: 202-624-5806 E-Mail: info@aashto.org Internet: http://www.aashto.org
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
38800 Country Club Drive Farmington Hills, MI 48331-3439 Ph: 248-848-3700 Fax: 248-848-3701 E-mail: bkstore@concrete.org Internet: http://www.concrete.org
ASTM INTERNATIONAL (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 877-909-2786 Internet: http://www.astm.org
U.S. AIR FORCE (USAF)
Air Force Publishing Distribution Center Ph: 202-404-2438Internet: http://www.e-publishing.af.mil/
CRD-C DOCUMENTS available on Internet:
http://www.wbdg.org/ccb/browse_cat.php?c=68 mailto:info@aashto.org http://www.aashto.org/ mailto:bkstore@concrete.org http://www.concrete.org/ http://www.astm.org/ http://www.e-publishing.af.mil/ http://www.wbdg.org/ccb/browse_cat.php?c=68
SECTION 01 42 00 Page
Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
General Services Administration 1275 First St. NE Washington, DC 20417 Ph: 202-501-1231 Internet: http://www.gsaelibrary.gsa.gov/ElibMain/home.do Obtain documents from:
Acquisition Streamlining and Standardization Information System
(ASSIST)
Internet: https://assist.dla.mil/online/start/; account registration required
Not used
Not used mailto:pubs-army@usace.army.mil http://www.publications.usace.army.mil/ http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx http://www.gsaelibrary.gsa.gov/ElibMain/home.do
SECTION 01 45 00.10 20 Page
SECTION 01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
EM 385-1-1 (2014) Safety and Health Requirements
Manual following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
QC Plan; G
Submit a QC plan within 15 calendar days after receipt of Notice of Award.
1.3 INFORMATION FOR THE CONTRACTING OFFICER
Prior to commencing work on construction, the Contractor can obtain a single copy set of the current report forms from the Contracting Officer.
The report forms will consist of the Contractor Production Report, Contractor Production Report (Continuation Sheet), Contractor Quality Control (CQC) Report, CQC Report (Continuation Sheet), Preparatory Phase Checklist, Initial Phase Checklist, Rework Items List, and Testing Plan and Log.
1.4 QC PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. The QC program consists of a QC Manager, a QC plan, a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, and QC certifications and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations which comply with the requirements of this contract. The QC program shall cover on-site and off-site work and shall be keyed to the work sequence. No work or testing may be performed unless the QC Manager is on the work site.
1.4.1 Preliminary Work Authorized Prior to Acceptance
The only work that is authorized to proceed prior to the acceptance of the QC plan is mobilization of storage and office trailers, temporary utilities, and surveying.
1.4.2 Acceptance
Acceptance of the QC plan is required prior to the start of construction.
The Contracting Officer reserves the right to require changes in the QC plan and operations as necessary, including removal of personnel, to ensure the specified quality of work. The Contracting Officer reserves the right to interview any member of the QC organization at any time in order to verify the submitted qualifications.
1.4.3 Notification of Changes
Notify the Contracting Officer, in writing, of any proposed change, including changes in the QC organization personnel, a minimum of seven calendar days prior to a proposed change. Proposed changes shall be subject to the acceptance by the Contracting Officer.
1.5 QC ORGANIZATION
1.5.1 QC Manager
1.5.1.1 Duties
Provide a QC Manager at the work site to implement and manage the QC program. In addition to implementing and managing the QC program, the QC Manager may perform the duties of project superintendent. The QC Manager is required to attend the Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by others.
1.5.1.2 Qualifications
An individual with a minimum of 10 years combined experience as a superintendent, inspector, QC Manager, project manager, or construction manager on similar size and type construction contracts which included the major trades that are part of this contract. The individual must be familiar with the requirements of the EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.
1.5.2 Alternate QC Manager Duties and Qualifications
Designate an alternate for the QC Manager to serve in the event of the designated QC Manager's absence. The period of absence may not exceed two weeks at one time, and not more than 30 workdays during a calendar year.
The qualification requirements for the Alternate QC Manager shall be the same as for the QC Manager.
1.6 QC PLAN
1.6.1 Requirements
Provide, for acceptance by the Contracting Officer, a QC plan submitted in a three-ring binder that covers both on-site and off-site work and includes the following with a table of contents listing the major sections identified with tabs.
I. QC ORGANIZATION: A chart showing the QC organizational structure and its relationship to the production side of the organization.
II. NAMES AND QUALIFICATIONS: In resume format, for each person in the QC organization. Include the CQM for Contractors course certification required by the paragraph entitled "Construction Quality Management Training".
III. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONAL: Of each person in the QC organization.
IV. OUTSIDE ORGANIZATIONS: A listing of outside organizations such as architectural and consulting engineering firms that will be employed by the Contractor and a description of the services these firms will provide.
V. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager and stating that they are responsible for managing and implementing the QC program as described in this contract. Include in this letter the QC Manager's authority to direct the removal and replacement of non-conforming work.
VI. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving and managing submittals. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval.
VII. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraphs "Accredited Laboratories" or "Testing Laboratory Requirements", as applicable.
VIII. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test.
IX. PROCEDURES TO COMPLETE REWORK ITEMS: Procedures to identify, record, track and complete rework items.
X. DOCUMENTATION PROCEDURES: Use Government formats.
XI. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, has the same control requirements and work crews. The list shall be cross-referenced to the Contractor's Construction Schedule and the specification sections. For projects requiring a Progress Chart, the list of definable features of work shall include but not be limited to all items of work on the schedule. For projects requiring a Network Analysis Schedule, the list of definable features of work shall include but not be limited to all critical path activities.
XII. PROCEDURES FOR PERFORMING THREE PHASES OF CONTROL: For each
DFOW provide Preparatory and Initial Phase Checklists. Each list shall include a breakdown of quality checks that will be used when performing the quality control functions, inspections, and tests required by the contract documents. The preparatory and initial phases shall be conducted with a view towards obtaining quality construction by planning ahead and identifying potential problems.
1.7 COORDINATION AND MUTUAL UNDERSTANDING MEETING
During the Pre-Construction conference and prior to the start of construction, discuss the QC program required by this contract. The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, and the coordination of the Contractor's management, production and the QC personnel. At the meeting, the Contractor will be required to explain how three phases of control will be implemented for each DFOW.
Contractor's personnel required to attend shall include the QC Manager, project manager, and superintendent. Minutes of the meeting will be prepared by the QC Manager and signed by both the Contractor and the Contracting Officer. The Contractor shall provide a copy of the signed minutes to all attendees. Repeat the coordination and mutual understanding meeting when a new QC Manager is appointed.
1.8 QC MEETINGS
After the start of construction, the QC Manager shall conduct QC meetings once every two weeks at the work site with the superintendent and the foreman responsible for the ongoing and upcoming work. The QC Manager shall prepare the minutes of the meeting and provide a copy to the Contracting Officer within two working days after the meeting. As a minimum, the following shall be accomplished at each meeting:
a. Review the minutes of the previous meeting;
b. Review the schedule and the status of work and rework;
c. Review the status of submittals;
d. Review the work to be accomplished in the next two weeks and documentation required;
e. Resolve QC and production problems (RFIs, etc.);
f. Address items that may require revising the QC plan; and
g. Review Accident Prevention Plan (APP).
1.9 THREE PHASES OF CONTROL
The three phases of control shall adequately cover both on-site and off-site work and shall include the following for each DFOW.
1.9.1 Preparatory Phase
Notify the Contracting Officer at least two work days in advance of each preparatory phase. Conduct the preparatory phase with the superintendent and the foreman responsible for the definable feature of work. Document the results of the preparatory phase actions in the daily CQC Report and in the QC checklist. Perform the following prior to beginning work on each definable feature of work:
a. Review each paragraph of the applicable specification sections;
b. Review the contract drawings;
c. Verify that appropriate shop drawings and submittals for materials and equipment have been submitted and approved. Verify receipt of approved factory test results, when required;
d. Review the testing plan and ensure that provisions have been made to provide the required QC testing;
e. Examine the work area to ensure that the required preliminary work has been completed;
f. Examine the required materials, equipment and sample work to ensure that they are on hand and conform to the approved shop drawings and submitted data;
g. Review the APP and appropriate Activity Hazard Analysis (AHA) to ensure that applicable safety requirements are met, and that required Material Safety Data Sheets (MSDS) are submitted; and
h. Discuss specific controls used and the construction methods and the approach that will be used to provide quality construction by planning ahead and identifying potential problems for each DFOW.
1.9.2 Initial Phase
Notify the Contracting Officer at least two work days in advance of each initial phase. When construction crews are ready to start work on a DFOW, conduct the Initial Phase with the foreman responsible for that DFOW.
Observe the initial segment of the work to ensure that it complies with contract requirements. Document the results of the Initial Phase in the daily CQC Report and in the QC checklist. Perform the following for each
DFOW:
a. Establish the quality of workmanship required;
b. Resolve conflicts;
c. Ensure that testing is performed by the approved laboratory; and
d. Check work procedures for compliance with the APP and the appropriate AHA to ensure that applicable safety requirements are met.
1.9.3 Follow-Up Phase
Perform the following for on-going work daily, or more frequently as necessary, until the completion of each DFOW and document in the daily CQC Report and in the QC checklist:
a. Ensure the work is in compliance with contract requirements;
b. Maintain the quality of workmanship required;
c. Ensure that testing is performed by the approved laboratory;
d. Ensure that rework items are being corrected; and
e. Assure manufacturers representatives have performed necessary inspections, if required.
1.9.4 Additional Preparatory and Initial Phases
Additional preparatory and initial phases shall be conducted on the same DFOW if the quality of on-going work is unacceptable, if there are changes in the applicable QC organization, if there are changes in the on-site production supervision or work crew, if work on a DFOW is resumed after substantial period of inactivity, or if other problems develop.
1.9.5 Notification of Three Phases of Control for Off-Site Work
Notify the Contracting Officer at least two weeks prior to the start of the preparatory and initial phases.
1.10 SUBMITTAL REVIEW AND APPROVAL
Procedures for submission, review, and approval of submittals are described in the submittal section of the specification.
1.11 TESTING
Except as stated otherwise in the specification sections, perform sampling and testing required under this contract.
1.11.1 Accreditation Requirements
Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. The laboratory's scope of accreditation must include the appropriate ASTM standards (i.e.; E 329, C 1077, D 3666, D 3740, A 880, E 543) listed in the technical sections of the specifications. Laboratories engaged in Hazardous Materials Testing shall meet the requirements of OSHA and EPA.
The policy applies to the specific laboratory performing the actual testing, not just the "Corporate Office."
1.11.2 Laboratory Accreditation Authorities
Laboratory Accreditation Authorities include the National Voluntary Laboratory Accreditation Program (NVLAP) administered by the National Institute of Standards and Technology, the American Association of State Highway and Transportation Officials (AASHTO), International Accreditation Services, Inc. (IAS), U. S. Army Corps of Engineers Materials Testing Center (MTC), the American Association for Laboratory Accreditation (A2LA), the Washington Association of Building Officials (WABO) (Approval authority for WABO is limited to projects within Washington State), and the Washington Area Council of Engineering Laboratories (WACEL) (Approval authority by WACEL is limited to projects within the NAVFAC WASH and Public Works Center Washington geographical area).
1.11.3 Capability Check
The Contracting Officer retains the right to check laboratory equipment in the proposed laboratory and the laboratory technician's testing procedures, techniques, and other items pertinent to testing, for compliance with the standards set forth in this contract.
1.11.4 Test Results
Cite applicable Contract requirements, tests or analytical procedures used. Provide actual results and include a statement that the item tested or analyzed conforms or fails to conform to specified requirements. If the item fails to conform, notify the Contracting Officer immediately.
Conspicuously stamp the cover sheet for each report in large red letters "CONFORMS" or "DOES NOT CONFORM" to the specification requirements, whichever is applicable. Test results shall be signed by a testing laboratory representative authorized to sign certified test reports.
Furnish the signed reports, certifications, and other documentation to the Contracting Officer.
1.12 QC CERTIFICATIONS
1.12.1 Contractor Quality Control Report Certification
Each CQC Report shall contain the following statement: "On behalf of the Contractor, I certify that this report is complete and correct and equipment and material used and work performed during this reporting period is in compliance with the contract drawings and specifications to the best of my knowledge except as noted in this report."
1.12.2 Invoice Certification
Furnish a certificate to the Contracting Officer with each payment request, signed by the QC Manager, attesting that as-built drawings are current and attesting that the work for which payment is requested, including stored material, is in compliance with contract requirements.
1.12.3 Completion Certification
Upon completion of work under this contract, the QC Manager shall furnish a certificate to the Contracting Officer attesting that "the work has been completed, inspected, tested and is in compliance with the contract."
1.13 COMPLETION INSPECTIONS
1.13.1 Punch-Out Inspection
Near the completion of all work or any increment thereof established by a completion time stated in the Contract clause "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager shall conduct an inspection of the work and develop a punch list of items which do not conform to the approved drawings and specifications.
Include in the punch list any remaining items of the "Rework Items List", which were not corrected prior to the Punch-Out inspection. The punch list shall include the estimated date by which the deficiencies will be corrected. A copy of the punch list shall be provided to the Contracting Officer. The QC Manager or staff shall make follow-on inspections to ascertain that all deficiencies have been corrected. Once this is accomplished, the Contractor shall notify the Government that the facility is ready for the Government "Pre-Final Inspection".
1.13.2 Pre-Final Inspection
The COR and QC manager will perform this inspection to verify that the facility is complete and ready to be occupied. A Government pre-final punch list may be developed as a result of this inspection. The QC Manager shall ensure that all items on this list are corrected prior to notifying the Government that a "Final" inspection with the customer can be scheduled. Any items noted on the "Pre-Final" inspection shall be corrected in a timely manner and shall be accomplished before the contract completion date for the work or any particular increment thereof if the project is divided into increments by separate completion dates.
1.13.3 Final Acceptance Inspection
The QC Manager, the superintendent, or other Contractor management personnel and the Contracting Officer will be in attendance at this inspection. Additional Government personnel may be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the "Pre-Final Inspection". Notice shall be given to the Contracting Officer at least 14 days prior to the final inspection. The notice shall state that all specific items previously identified to the Contractor as being unacceptable will be complete by the date scheduled for the final acceptance inspection.
1.14 DOCUMENTATION
Maintain current and complete records of on-site and off-site QC program operations and activities. The forms identified under the paragraph "INFORMATION FOR THE CONTRACTING OFFICER (Contracting Officer)" shall be used. Reports are required for each day work is performed. Account for each calendar day throughout the life of the contract. Every space on the forms must be filled in. Use N/A if nothing can be reported in one of the spaces. The superintendent and the QC Manager must prepare and sign the Contractor Production and CQC Reports, respectively. The reporting of work shall be identified by terminology consistent with the construction schedule. In the "remarks" section in this report which will contain pertinent information including directions received, problems encountered during construction, work progress and delays, conflicts or errors in the drawings or specifications, field changes, safety hazards encountered, instructions given and corrective actions taken, delays encountered and a record of visitors to the work site. For each remark given, identify the Schedule Activity No. that is associated with the remark.
1.14.1 Quality Control Validation
Establish and maintain the following in a series of three ring binders.
Binders shall be divided and tabbed as shown below. These binders shall be readily available to the Government's Quality Assurance Team during all business hours.
a.…