Attachment 5 Schedule of Services Blank Price Schedule Revised.xls
XLS spreadsheet 38 KB Posted
- Attached to
- DRYDOCK: CGC ESCANABA (DDS) DD FY23
- Solicitation number
- 70Z080-23-Q-ESCANABADD
About this file
This document provides a price schedule and statement of work for a federal solicitation seeking drydock services for the US Coast Guard Cutter Escanaba. The solicitation requests pricing for various hull preservation, inspection, and repair items to be completed while the cutter undergoes drydocking from January 11 to March 22, 2023. Offerors must submit pricing using the provided price schedule template, along with required technical documents and any signed solicitation amendments. The solicitation is issued by the Department of Homeland Security US Coast Guard to maintain one of its seagoing assets. Pricing is requested for work items including hull plating testing and preservation, underwater body inspection and preservation, propulsion system inspection and component overhaul, deck preservation, and renewal of various piping, hatches, doors and tank systems.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | |||||
| USCGC ESCANABA (WMEC-270B) DRYDOCK AVAILABILITY FY2023 | |||||
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Hull Plating, Side Scan, Ultrasonic Testing | JOB | 1 | ||
| D-002 | Hull Plating, U/W Body, Ultrasonic Testing | JOB | 1 | ||
| D-003 | U/W Body, Preserve, 100 percent | JOB | 1 | ||
| D-004 | Hull Plating Freeboard, Preserve, 100 Percent | JOB | 1 | ||
| D-005 | Appendages (U/W), Preserve (Internal) and Leak Test | JOB | 1 | ||
| D-006 | Propulsion Shaft Fairwaters And Rope Guards, Inspect | JOB | 1 | ||
| D-007 | Voids (Non-Accessible), Preserve (Internal) and Leak Test | JOB | 1 | ||
| D-008 | Mast, Preserve, 100 Percent | JOB | 1 | ||
| D-009 | Propulsion Shafting, Strain Gage Alignment, Drydock, Check | JOB | 1 | ||
| D-010 | Propulsion Propeller Shaft Coating, Inspect and Test | JOB | 1 | ||
| D-011 | Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect and Repair or Renew | JOB | 1 | ||
| D-012 | Controllable Pitch Propellers, Clean and Inspect | JOB | 1 | ||
| D-013 | Controllable Pitch Propeller (CPP) System, Inspect and Service | JOB | 1 | ||
| D-014 | Controllable Pitch Propeller (CPP) Hubs, Remove, Inspect and Reinstall | JOB | 1 | ||
| D-015 | Fathometer Transducer, Renew | JOB | 1 | ||
| D-016 | Sea Valves and Waster Pieces, Overhaul Or Renew | JOB | 1 | ||
| D-017 | Sea Strainers, Duplex, All Sizes, Overhaul | JOB | 1 | ||
| D-018 | Sea Strainers, Simplex, All Sizes, Clean and Inspect | JOB | 1 | ||
| D-019 | Rudder Assemblies, Inspect and Repair | JOB | 1 | ||
| D-020 | Superstructure, Preserve, 100 Percent | JOB | 1 | ||
| D-021 | Cathodic Protection, Zinc Anodes, Renew, | JOB | 1 | ||
| D-022 | Drydock | JOB | 1 | ||
| D-023 | Temporary Services, Provide - Cutter | JOB | 1 | ||
| D-024 | Bathythermograph Launching Tube, Remove | JOB | 1 | ||
| D-025 | Doppler Speed Log, Replace | JOB | 1 | ||
| D-026 | Deep Water Sounder, Remove | JOB | 1 | ||
| D-027 | Oily Water Separator Potable Water Supply, Modify | JOB | 1 | ||
| D-028 | Weather Deck Stanchions, Handrail, and Fixtures, Renew | JOB | 1 | ||
| D-029 | Ballast Tank Air Escape and Vent Piping, Renew | JOB | 1 | ||
| D-030 | Weathertight Doors (External), Renew | JOB | 1 | ||
| D-031 | Deck Covering, Interior, Wet and Dry, Renew | JOB | 1 | ||
| D-032 | Fuel Oil Piping, Renew | JOB | 1 | ||
| D-033 | Watertight Hatches, External, Renew | JOB | 1 | ||
| D-034 | Fuel Oil Deck Connection, Renew | JOB | 1 | ||
| D-035 | JP-5 Deck Connection Risers, Renew | JOB | 1 | ||
| D-036 | Tanks, Ballast, Preserve, 100 Percent | JOB | 1 | ||
| D-037 | Tanks, Potable Water Preserve, 100 Percent | JOB | 1 | ||
| D-038 | Sewage Deck Connection, Renew | JOB | 1 | ||
| D-039 | Bilges, Preserve | JOB | 1 | ||
| D-040 | Helo Hangar Detacouple, Renew | JOB | 1 | ||
| D-041 | Fuel Oil Tank Air Escape, Renew | JOB | 1 | ||
| D-042 | Fan Coil Units, Renew | JOB | 1 | ||
| D-043 | Vent Hood (DC Shop), Renew | JOB | 1 | ||
| D-044 | Air Escapes, Renew | JOB | 1 | ||
| O-00A | Composite Labor Rate | Hour | |||
| D-00B | GFP Report | NSP | EA | NSP | |
| D-00C | Travel and Perdiem | $0.00 | JOB | $0.00 | |
| O-00Z | Laydays | Day | |||
| Total Price of Definite Items | |||||
| Total Price of Option Items | |||||
| Total Price of Definite and Optional Items |