ATTACHMENT-2_SPECIFICATION_TERRAPIN_R0_dtd_042519_jeb.pdf

PDF 2 MB Posted

Attached to
USCGC TERRAPIN DRYDOCK Federal contract opportunity
Solicitation number
70Z080-20-Q-P4500400
Issued by
Department of Homeland Security US Coast Guard

About this file

Attachment-2 Specification USCGC TERRAPIN

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC TERRAPIN (WPB 87366)

SPECIFICATION FOR DRYDOCK REPAIRS

FY2020

Developed By: James E Beechey

(Rev-0, 25 April 2019)

USCGC TERRAPIN (WPB-87) DRYDOCK AVAILABILITY FY2020

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ............................................................................... vii Consolidated List of Critical Inspection Items ............................................................................................. ix Principal Characteristics ................................................................................................................................ x General Requirements WORK ITEM 1: Structural Analysis, 3D Laser Scan, Perform WORK ITEM 2: Ultrasonic Thickness Measurements, Perform WORK ITEM 3: U/W Body, Preserve (100%) WORK ITEM 4: Hull Plating Freeboard, Preserve “100%” WORK ITEM 5: Tank, Dirty Oil, Clean and Inspect WORK ITEM 6: Tank, Oily Water, Clean and Inspect WORK ITEM 7: Tanks (Mp Fuel Service), Clean And Inspect WORK ITEM 8: Decks, Exterior (Main Deck), Preserve WORK ITEM 9: Capastic Fairing, Depth Sounder, Renew WORK ITEM 10: Main Engine/Reduction Gear, Realign WORK ITEM 11: Intermediate Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 12: Aft Water-Lubricated Propulsion Shaft Bearings, Renew WORK ITEM 13: Intermediate Bearing Carriers, Renew WORK ITEM 14: Aft Bearing Carriers, Renew WORK ITEM 15: Stern Tube Interior Surfaces, Preserve 100% WORK ITEM 16: Propellers, Renew WORK ITEM 17: Speed Log, Skin Valve, Renew WORK ITEM 18: Sea Water System, Perform Maintenance WORK ITEM 19: Stern Launch Door, Remove, Inspect and Reinstall WORK ITEM 20: Cathodic Protection/Zinc Anodes, Renew WORK ITEM 21: Drydock WORK ITEM 22: Temporary Services, Provide - Cutter WORK ITEM 23: Sea Trial Performance, Support, Provide WORK ITEM 24: Fathometer Transducer, Renew WORK ITEM 25: Oily Water Separator, Remove WORK ITEM 26: Propulsion Shaft and Shaft Seals, Replace WORK ITEM 27: Rudder Assemblies, Renew WORK ITEM 28: Main Mast, Modify WORK ITEM 29: Interior Deck Covering System, Renew WORK ITEM 30: Multi-Cable Transit Assembly, Renew WORK ITEM 31: Critical Coated Surface(s), Preserve WORK ITEM 32: Windows, Pilothouse, Renew WORK ITEM 33: Stanchion(s), Repair WORK ITEM 34: Pilothouse Deck, Inspect and Preserve iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 085-001, Rev -, Tank Capacity Curves

Coast Guard Drawing 87 WPB 085-011, Rev C, Lifting Slings

Coast Guard Drawing 87 WPB 085-012, Rev A, Lifting Cradle

Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan

Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion

Coast Guard Drawing 87 WPB 113-001, Rev F, Platform Plating & Framing

Coast Guard Drawing 87 WPB 113-002, Rev B, Galley/Mess Deck Bilge Access

Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & BHD’s

Coast Guard Drawing 87 WPB 117-001, Rev G, Transverse Sections

Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads

Coast Guard Drawing 87 WPB 151-001, Rev L, Superstructure Details

Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details

Coast Guard Drawing 87 WPB 165-001, Rev F, Transducer Details

Coast Guard Drawing 87 WPB 167-002, Rev B, CG Schedule of Doors, Manholes, Windows, and

Hatches.

Coast Guard Drawing 87 WPB 171-001, Rev W, Mast Details

Coast Guard Drawing 87 WPB 182-001, Rev C, Main Engine & Generator Foundations

Coast Guard Drawing 87 WPB 243-003, Rev -, Propulsion Shaft Details

Coast Guard Drawing 87 WPB 245-003, Rev A, Propeller Details

Coast Guard Drawing 87 WPB 256-001, Rev AC, Seawater Cooling Piping

Coast Guard Drawing 87 WPB 304-001, Rev C, Wireway Arrangement

Coast Guard Drawing 87 WPB 304-002, Rev A, Wireway Penetration Details

Coast Guard Drawing 87 WPB 331-001, Rev P, Lighting System Deck Plan

Coast Guard Drawing 87 WPB 423-001, Rev W, Speed Log & Depth Sounder System

Coast Guard Drawing 87 WPB 561-001, Rev K, Steering System Details

Coast Guard Drawing 87 WPB 562-001, Rev A, Rudder Details

Coast Guard Drawing 87 WPB 583-001, Rev W, RIB Deployment Structure

Coast Guard Drawing 87 WPB 593-002, Rev E, Oily Water Separator Piping

Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements v (Rev-0)

Coast Guard Drawing 87 WPB 602-001, Rev E, Visual ID and Draft Mark Plan

Coast Guard Drawing 87 WPB 612-001, Rev N, Handrail Details

Coast Guard Drawing 87 WPB 621-001, Rev J, Joiner Work Details

Coast Guard Drawing 87 WPB 631-001, Rev M, Ship’s Painting Schedule

Coast Guard Drawing 87 WPB 633-001, Rev A, Cathodic Protection

Coast Guard Drawing 87 WPB 634-001, Rev G, Deck Coverings & Details

Coast Guard Fleet Drawing FL 2804-12, Rev -, U.S.C.G. Emblem

Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters

NAVSEA Drawing 803-921865, Rev R, Cathodic Protection Hull Zinc Anodes

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 4499, Jun 2018, SWBS 243, Stern Tube Seal-Model 442C

Coast Guard Technical Publication (TP) 4506, Wartsila TM-EL-68839, Issue A, Mar 2005, Rudderstock

Seal Type EL

Coast Guard Technical Publication (TP) 4593D, July 2011, SWBS 243, Manufacturer's Instruction Book, 87' WPB Propulsion Shaft Seal - Type F.S.E.

Coast Guard Technical Publication (TP) E-424-0230, SWBS 424, June 2006, Electromagnetic Log User’s

Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior

Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary

Services

OTHER REFERENCES

ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) F992, 2006, Standard Specification for Valve Label Plates

Bollinger Shipyard, USCG CPB Project MTU-FA 771903, 07 Feb 2000, Engine/Gearbox Plant

Alignment Instructions 8V396 TE94/Flange Mounted BW 255

Commercial Item Description (CID) A-A-59313, Nov 2003, Thread Compound; Antiseize, Zinc Dust-

Petrolatum

Commercial Item Descriptions (CID) A-A-59316, Nov 2016 Abrasive Materials for Blasting

MIL-A-18001, Dec 2015, Anodes, Sacrificial Zinc Alloy (Commercially Accepted - ASTM B418)

MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning

MIL-A-46106B, Adhesive-Sealants, Silicone, RTV, One-Component vi (Rev-0)

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required

MIL-DTL-15562G, Matting or Sheet, Floor Covering; Insulating For High Voltage Application

MIL-PRF-24139, Mar 1987, Grease, Multipurpose, Water Resistant.

MIL-PRF-24613A, Nov 2007, Deck Covering Materials, Interior, Cosmetic Polymeric

MIL-PRF-24635, 2009, Coating Systems, Weather-Resistant, Exterior Use

MIL-PRF-24647, Apr 2013, Paint System, Anticorrosive and Antifouling, Ship Hull

MIL-PRF-3135H, Sept 2008, Deck Covering Underlay Materials

SAE-AMS-S-8802D, Sealing Compound, Fuel Resistant, Integral Fuel Tanks and Fuel Cell Cavities

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2013, Cork and

Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 12/NACE No.5, 2002, Surface Preparation and Cleaning of Metals by

Waterjetting Prior to Recoating

The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, 2007, Near-White Blast Cleaning vii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

8 N Slip Resistant Sheets NSN: 7220-01-F11-2238 1 KT 5,352.24

10 Y *Alignment kit 1 ea. 5000.00

11 N Thordon bearing, Grade Orange (5.5"

OD x 4" ID x 7.87"

(200mm) LG)

PN: F54615-02-8-1 NSN: 3120-

21-914-2012

2 ea. 525.03

12 N Thordon bearing, Grade Orange (5.5"

OD x 4" ID x 11.41"

(290mm) LG)

PN: F54615-02-8-0 NSN: 3120-

21-914-2011

2 ea. 558.05

13 N **Intermediate bearing carrier

NSN: 3130-01-F11-2388 P/N:

87 WPB 243-001, Item 17

2 ea. 591.86

14 N **Aft bearing carrier NSN: 3130-01-F11-2200 PN:

87 WPB 243-001, Item 14

2 ea. 1931.31

16 Y Starboard Propeller

(RH)

PN: 706-3351.00 RH NSN:

2010-01-457-0573

1 ea. 9153.07

16 Y Port Propeller (LH) PN: 706-3350.00 LH NSN:

2010-01-459-0421

1 ea. 9542.05

16 N *Propeller Nut Wrench N/A 1 ea. 200.00

16 N Propeller Nut PN: 5317350 NSN: 2010-01-

458-9217

2 ea. 322.07

16 N Propeller Nut, Locking PN: 5317355 NSN: 5310-01-

458-9125

2 ea. 285.10

16 N Anode, Propeller Nut PN: 87WPB243001ITEM39

NSN: 5342-01-481-8403

2 ea. 153.06

17 Y 3” Ball Valve NSN: 4810-01-517-8110 PN:

LV071A

1 ea. 5622.11

17 Y Doppler Speed Log

Measurement Rod

NSN: 6605-01-470-1266 1 ea. 5823.22

18 N Iron body/ Stainless steel stem/ bronze disk

(flanged) 8”

PN: J022929-512431A NSN:

4820-01-613-5021

2 ea. 563.25

18 N Iron body/ Stainless steel stem/ bronze disk

(wafer) 8”

PN: 22929-112431A NSN:

4820-01-615-9571

2 ea. 521.46

18 N Iron body/ Stainless steel stem/ bronze disk

(flanged) 3”

PN: 22925-5124 NSN: 4820-

01-650-0975

2 ea. 226.51

18 N Iron body/ Stainless steel stem/ bronze disk

(wafer) 3”

PN: 22925-1124316 NSN:

4820-01-332-6811

2 ea. 214.14

19 N Valve assy, manifold PN: USCG-MNFLD-87 NSN: 1 ea. 496.08 viii (Rev-0)

4820-01-535-0136

20 N Anode, corrosion preventive

PN: 899Y105 NSN: 5342-00-

813-6058

15 ea 57.37

21 Y *Transducer Cover

Plate

N/A 2 ea. 50.00

24 Y ***Transducer, sonar, w/ adapter ring

PN: 87-WPB-165-001 NSN:

5845-01-641-9744

1 ea. 1552.41

26 Y Propeller Shaft NSN: 2010-01-458-9175 2 ea. 10,195.95

26 N Installation Kit, Shaft

Seal

NSN: 5330-01-F18-5381 2 ea. 9443.00

27 Y Rudder Assembly, port NSN: 2040-01-461-1944 1 ea. 6113.36

27 Y Rudder Assembly, starboard

NSN: 2040-01-461-1943 1 ea. 5971.93

27 N Upper Roller Bearing NSN: 3110-01-512-5534 2 ea. 287.43

27 N Wartsila EL Seals Kit PN: H75492-01 NSN: 2040-01-

565-9776

2 ea. 7243.42

27 N Lower Bearing PN: TBF113090 NSN: 3120-

20-000-7677

2 ea. 405.81

29 N Panel, Deck, 5/8"x48"x96", Aluminum 5052-H32

Core, 1/4" Cell, 0.063"

6061-T6 Face Sheets, Natural Mill Finish

PN: SPXC-1000-1000D NSN:

2040-01-F19-5621

14 Ea. 654.00

32 N Window, marine (Pos

1)

NSN: 2090-21-914-9464 1 ea. 2,332.64

32 N Window, marine (Pos

7)

NSN: 2090-21-914-8549 1 ea. 2,477.80

32 N Window, marine (Pos

16)

NSN: 2090-21-914-9462 1 ea. 3,084.93

34 N Anti-fatigue matting

(556 cushion ease solid

3’ x 3’

NSN: 7220-01-598-6144 15 ea. 55.42

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter ix (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

3 U/W Body, Preserve (100%)

18 Sea Water System, Perform Maintenance

19 Stern Launch Door, Remove, Inspect and Reinstall

21 Drydock

26 Propulsion Shaft and Shaft Seals, Replace

27 Rudder Assemblies, Renew

34 Pilothouse Deck, Inspect and Preserve x (Rev-0)

PRINCIPAL CHARACTERISTICS

87' WPB

PHYSICAL

Length overall 87'

Length between perpendiculars 81' 7"

Depth 10' 11"

Maximum beam 19.4'

Draft, mean to design waterline 5' 9"

Height of highest projection 50.2'

Full load displacement 93.5 long tons

Minimum operating displacement 83.9 long tons

Displacement, light ship 77.9 long tons

Framing Longitudinal

Bulkheads Four watertight bulkheads located below the Main Deck

Anchor 40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset

HULL

Hull/main weatherdeck material ABS Grade AH 36

Superstructure 5086 Aluminum

MACHINERY

Main propulsion Two MTU 8V396TE94, sequential turbo-charged diesels

Reduction gears Two ZF Type BW 255

Propulsion shaft Two AQUAMET 22, 101.6mm

Shaft diameter 4"

Shaft seal Two John Crane mechanical seals

Shaft bearing, intermediate Thordon Elastomeric Bearing

Shaft bearing, aft Thordon Elastomeric Bearing

Number of propellers 2

Number of blades 5

Diameter of propeller 1040mm

Pitch 1230 mm fixed

Shaft RPM 828

Rudders Two 316L Stainless Steel

Ship's service generators Two Man Model D08241F01 diesel with Stanford 60KW Generator

TANK CAPACITIES

3-9-1-f (fuel oil) 1402 gal

3-9-2-f (fuel oil) 1402 gal

3-12-2-f (waste oil) 86 gal

3-12-1-f (oily water) 86 gal

3-7-0-q (sewage collection) 352 gal

3-7-1-q (grey water) 52 gal

3-12-1-w (fresh water) 200 gal

3-12-2-w (fresh water) 200 gal

1 (Rev-0)

00000_0618_FLT

REC_00000_FLT_Commercial Project @ Contractor’ Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes

(provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at

Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, 3 (Rev-0) and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix A, Requirements For

Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint

Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of

SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay

(RRL) wire rope or Dyform-18, rotation resistant wire rope."

3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

4 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

5 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

6 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

7 (Rev-0)

TIME

8 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

9 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

10 (Rev-0)

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-0)

10000_MWS_0718_87WPB

WORK ITEM 1: Structural Analysis, 3D Laser Scan, Perform

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform 3D laser scan of the cutter’s exterior hull shell, deck and dock floor locations/deformations and provide results in 3D CAD format.

1.2 Government-furnished property.

None

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan

Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion

Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep. The Contractor shall provide the services of a Qualified Technical Representative who has the experience and knowledge to conduct a three-dimensional laser scan model identifying hull and deck deformations in 3D CAD format.

3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on

13 (Rev-0) their résumé.

3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

NOTE

The USCG conducts structural analysis efforts requiring accurate measurement of the hull shape including both global and local deformations.

Measurements of hull global and local deformations are evaluated relative to the design hull lines is a key part of this hull strength analysis and implications on shafting alignment.

3.2 Three dimensional laser scan. The Contractor shall perform a 3D laser scan of the cutter’s hull (sides, bottom and transom), shaft skegs (and shafting if in place) and the dock floor to obtain the 3D point cloud and provide a registered, reduced point cloud data set.

3.2.1 The 3D laser scan point cloud accuracy shall be within +/- 2 mm local scans and 5mm global scan alignment for the hull and deck surfaces. A point cloud reduction process shall be conducted to determine the shell plating deformations including an average of the deck nonskid covering to show the underlying plate deformations by averaging points over a 20 mm grid on the hull. The point cloud of hull appendages shall be reduced over a 1mm grid.

3.2.1.1 The Contractor shall convert the 3D laser scan (3D Point cloud) to a point cloud format that can be used in Rhino 3D version 5.0. The Contractor shall digitally remove staging interferences located around the hull of the Cutter.

3.2.1.2 The Contractor shall compare the measured 3D point cloud and meshed surfaces to the hull lines based NURBS surface developed by US Coast Guard SFLC to determine dimensional deviations from the lines based NURBS surface. The dimensional deviations shall be rendered in the Rhino 3D in 1mm increments and colors to show the dimensional gradients. The Contractor shall position the hull relative to the 3D hull surface in coordination with the US Coast Guard.

3.3 Report. The Contractor shall provide a neatly organized model using layers and color contour images of the surface comparisons. The Contractor shall provide the 3D point cloud in Rhino 3D 5.0 format files and deliver them in electronic format by ftp or mailed CDs to the USCG within 2 weeks after conducting the 3D Laser Scan.

3.3.1 The report shall include all photographs, illustrations, charts, graphs, tables, calculations, text, analyses, algorithms, conclusions and recommendation deliverables developed as a part of this project.

The Coast Guard will review the report, and may provide feedback or conduct discussions with the

Contractor prior to acceptance.

14 (Rev-0)

3.3.2 The report shall be delivered to USCG with a document cover letter to the following address:

Commanding Officer (SFLC-ESD-NAME)

USCG Surface Forces Logistics Center (Mail Stop 25)

2401 Hawkins Point Road

Baltimore, MD 21226-5000

Attn: Mr. Karl Stambaugh

3.3.3 Data rights. All data regardless of form or medium shall be the sole property of the US Coast Guard and shall not be released without the written consent of the US Coast Guard.

4. NOTES

This section is not applicable to this work item.

15 (Rev-0)

11000_MWS_1118_87WPB

WORK ITEM 2: Ultrasonic Thickness Measurements, Perform

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to perform up to 250 thickness measurements (UT shots) of hull plating and frames, by ultrasonic methods.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 085-013, Rev B, Docking Plan

Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion

Coast Guard Drawing 87 WPB 163-001, Rev H, Sea Chest Details

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

16 (Rev-0)

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec

0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Sea chest grates

Tight interior spaces

3.2 UT measurements. Using Coast Guard Drawings 87 WPB 085-013 and 87 WPB 111-001 as guidance, the Contractor shall perform up to 250 UT measurements in locations designated by the Coast

Guard Inspector in accordance with SFLC Std Spec 0740, Appendix C. Submit a CFR.

NOTE

Fifty of the 250 UT shots shall be conducted over the 1/4” sea chest plating in both sea chests beneath the sea chest grates as shown on Coast Guard

Drawing 87 WPB 163-001.

3.2.1 The Contractor shall create a sketch to show all locations selected for measurement and record all measurements in Table 1 (UT Measurements Summary Sheet - Port/Stbd Shell) provided at the end of this item.

3.2.2 The Contractor shall provide a detailed sketch showing the UT measurements/locations and complete Table 1 and provide in the CFR. The CFR shall itemize all areas requiring repairs along with repair recommendations, including complete work scope proposal, for each area.

17 (Rev-0)

TABLE 1 - UT MEASUREMENTS SUMMARY SHEET PORT/STBD SHELL

SHOT # STRAKE # FWD/MID/AFT ORIG PL MEASURED PL PERCENT

PLATE # TOP/MID/BOT THICKNESS THICKNESS WASTAGE

18 (Rev-0)

63130_0617_FLT

REC_63130_100Percent_FLT_87' WPB (ALL) (1118)

WORK ITEM 3: U/W Body, Preserve (100%)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve U/W body surfaces.

NOTES

1. The purpose of the preservation tasks covered by this item is to completely remove all existing coatings and recoat the U/W body surfaces with a new coating system.

2. U/W body surfaces are as defined in 4.1 (Definitions) and exclude areas covered by docking blocks, unless the vessel is fleeted for the express purpose of preserving blocked areas.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 583-001, Rev W, RIB Deployment Structure

Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements

Coast Guard Drawing 87 WPB 602-001, Rev E, Visual ID and Draft Mark Plan

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2015, Solvent Cleaning

19 (Rev-0)

3. REQUIREMENTS

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.1.5.1 Fairing inspection

3.2.3 Post-surface preparation cleaning and inspection

3.1.2 Tech Rep. The Contractor shall refer to SFLC Std Spec 0000, paragraphs 3.2.4.2.1 (Painting contractor certification program requirement) and 3.2.4.2.2 (Coating Tech Rep), for applicable requirements.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness. Specific areas/equipment/components to be protected include, but are not limited to:

All scuppers and overboard discharges.

Waterline area where U/W body coating system interfaces with freeboard coating system

(unless freeboard surfaces are also being preserved).

Fathometer transducer surfaces.

Sea valve openings.

Propeller shaft bearings and seals.

Rudder bearings.

Propellers.

Zinc anodes (unless anodes are being renewed).

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Sea chest grating.

Hydraulic stern door rams.

Hydraulic hoses and piping.

Stern door gaskets.

High density molecular weight plastic pads in the boat ramp.

NOTE

The capastic fairing is not to be removed simply as an interference for 100% near white blasting unless it is found to be failing.

3.1.5 Initial inspection. Prior to removing the existing coating system, the Contractor shall inspect and verify whether all draft marks have permanent markings (weld beads or impressions), showing their location on the hull. Submit a CFR.

20 (Rev-0)

3.1.5.1 Fairing inspection. Prior to preservation preparation, inspect the capastic fairing condition. Submit a CIR.

3.1.6 Water used in preparation and washing procedures. The Contractor shall ensure that water used in all surface preparation tasks, including pre-surface preparation wash and water jetting, is of sufficient purity and quality that it does not prevent the surface being cleaned from achieving the required degree of surface cleanliness or non-visible contamination criteria.

3.1.6.1 Ensure that surface preparation water does not contain sediments or other impurities that are destructive to the proper functioning of the cleaning equipment.

3.1.6.2 Ensure that all water used in any surface preparation or cleaning procedures is captured, contained, and all spent water disposed of in accordance with all Federal, state and local regulations.

3.1.7 Surface preparation optional methods. The Contractor has the option of using either high/ultrahigh pressure water jetting or abrasive blasting to achieve the required surface preparation, prior to application of the coating system specified in 3.2 (Preservation requirements). The Contractor may add abrasives to the water jet stream, for one or both of the following reasons:

Achieving greater productivity.

Achieving the required surface profile.

NOTES

1. Existing coating system on the U/W body surfaces may have a nominal thickness in excess of that which was originally installed, because of “patch-coats” applied during past drydock availabilities.

2. Water jetting without abrasive addition does not provide any additional anchor profile to the surface, beyond what was present after the previous surface preparation.

3.2 Preservation requirements. The Contractor shall accomplish the following tasks:

3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.

3.2.2 Surface preparation and coating application.

3.2.2.1 Perform a visual inspection of the pad studs in the RHIB notch, making note if there are any missing or damaged. Submit a CFR.

3.2.2.2 U/W body and appendages.

3.2.2.2.1 Prepare the U/W body, appendage surfaces, and RHIB notch wet deck, using the system specified for “Underwater Water (U/W) Body and Boot-Top (U/W Body and Boot-Top, Steel Hulls (Up to 12 Years), in Salt Water”, in SFLC STD SPEC 6310, Appendix A (Cutter and Boat Exterior Painting

Systems”.

3.2.2.2.2 Prior to coating application, accomplish surface inspections in accordance with Paragraph 3.2.3.

21 (Rev-0)

3.2.2.2.3 Coat the U/W body and appendage surfaces as specified below, and otherwise in accordance

SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems):

3.2.2.2.3.1 First coat, MIL-PRF-24647 Anticorrosive Epoxy, Grade A or B (Red) at 5-6 mils, DFT.

3.2.2.2.3.2 Second coat, MIL-PRF-24647 Anticorrosive Epoxy, Grade A or B (Gray) at 5-6 mils, DFT.

3.2.2.2.3.3 Third coat, MIL-PRF-24647 Non-copper Ablative, Type I, Class 2, Applications 1 & 4 (Red) at 5-6 mils, DFT (while epoxy beneath is still tacky).

3.2.2.2.3.4 Fourth coat, MIL-PRF-24647 Non-copper Ablative, Type I, Class 2, Applications 1 & 4

(Black) at 5-6 mils, DFT.

3.2.2.2.3.5 Fifth coat, MIL-PRF-24647 Non-copper Ablative, Type I, Class 2, Applications 1 & 4 (Red) at 5-6 mils, DFT.

3.2.2.2.3.6 Boot-top area only, apply an additional coat - MIL-PRF-24647 Non-copper Ablative, Type I, Class 2, Applications 1 & 4 (Black) at 5-6 mils, DFT.

3.2.2.3 Stern door surfaces.

3.2.2.3.1 Prepare the designated aluminum stern door external and internal surfaces (in the boot-top area), using the system specified for “Underwater (U/W) Body/Boot Top, Aluminum Hull," in SFLC Std Spec

6310 (series), Appendix A.

3.2.2.3.2 Coat the stern door U/W body surface using the system specified under 3.2.2.1.3 Top coat surfaces with scheme as shown in Coast Guard Drawing 87 WPB 602-001 (black boot top and red u/w body beneath the boot top).

3.2.2.4 Stern ladder surfaces.

3.2.2.4.1 Prepare the aluminum stern ladder surfaces using the system specified for

“Freeboard/Superstructure/Mast (Freeboard/Superstructure, Aluminum, Option I)” in SFLC STD SPEC

6310, Appendix A (Cutter and Boat Exterior Painting Systems).

3.2.2.3.2 Coat the ladder using the system specified under 3.2.2.3.1 Match the adjacent hull colors and scheme.

3.2.3 Post-surface preparation cleaning and inspection. After completion of surface preparation and prior to coating application, accomplish the following tasks and submit a CIR.

3.2.3.1 Perform a visual inspection of the prepared U/W body steel substrate.

NOTE

Lists of all authorized coating materials and suppliers, and coating colors are listed in SFLC Std Spec 6310, Appendix C (Cutter and Boat Authorized

Coatings).

22 (Rev-0)

3.2.3.2 Perform solvent cleaning of all prepared surfaces, in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations.

3.3 Draft mark painting. The Contractor shall paint all draft marks with two coats of a “Polysiloxane” or

“Silicone Alkyd Enamel” coating, at 2.0-3.0 mils DFT, white (17925).

3.4 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces). Surfaces being preserved are considered “critical-coated surfaces”.

3.5 Stern door removal. The Contractor may elect to remove the aluminum stern door, at no additional cost to the Government, to facilitate door preservation. DO NOT place or store stern door on its arms.

3.6 Precautionary measures. The Contractor shall ensure that no aluminum surfaces come in contact with copper coating, due to copper’s corrosive effect on aluminum surfaces.

3.7 AF system protective measures – in the event of prolong atmospheric exposure. If the vessel will not be refloated within the immersion time as recommended by the coating system manufacturer, the

Contractor shall employ suitable measures - including but not limited to keeping the coating system wet and away from direct sun light, to avoid film damage that may reduce or impact the final performance of the AF coating system when placed into service.

4. NOTES

4.1 Definitions.

4.1.1 U/W Body. The underwater body is defined as the areas from the bottom of the keel to the upper edge of the boot-topping, as shown on Coast Guard Drawing 87 WPB 601-001, including rudders, transducer hull rings, sea chests (including the sea chest inlet up to the final connection with the flange face at the sea chest isolation valve(s)), sea chest riser pipes, bilge keels, struts, skegs, gratings, and rope guards. Also included are the underwater body (boot top) area that extends into the RHIB wet notch deck, shown on Coast Guard Drawing 87 WPB 583-001 (normally submerged and painted black) and portion of aluminum stern door external and internal surfaces (in the boot-top area) that are normally submerged and painted black.

23 (Rev-0)

63140_0617_FLT

REC_63140_100Prcnt_FLT_87’ WPB (ALL) (1017)

WORK ITEM 4: Hull Plating Freeboard, Preserve “100%”

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve 100% of the freeboard surfaces defined in 4.1 Definition of freeboard surfaces.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 583-001, Rev W, RIB Deployment Structure

Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements

Coast Guard Drawing 87 WPB 602-001, Rev E, Visual ID and Draft Mark Plan

Coast Guard Fleet Drawing FL 2804-12,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.