Attachment H - Acceptance Process. This attachment is submitted to provide the Coast Guard's acceptance process for deliverables.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70Z07918QMNJ00100
DEPARTMENT OF HOMELAND SECURITY
ELECTRONIC CHART PROVISION TO
COAST GUARD CUTTERS
for
USCG NAVCEN
Attachment III - Acceptance Process
ENC and RNC QA/QC Checks on USCG Systems for All CD Regions
I) VEGA ECS– Install Electronic Charts
1) Install BSB/RNC format charts.
⇒ Verify selected region disc corresponds to provided region map ⇒ Insert region CD ⇒ Tools > Charts ⇒ Select “View Importable Charts” ⇒ Select BSB tab in Charts dialog ⇒ Select “plus “Add/Update” button ⇒ Location (default) D:\BSBSCHART ⇒ Next ⇒ Check for any charts with errors ⇒ Verify accuracy at max ranges ⇒ Verify charting regions ⇒ Verify chart display at various scales ⇒ Note any charts with errors (for further evaluation) ⇒ Install
2) Install ENC format charts.
⇒ Select ENC tab in Charts dialog ⇒ Select “plus “Add/Update” ⇒ Location (default) D:\ENC_ROOT ⇒ Next ⇒ Check for any charts with errors.
⇒ Verify accuracy at max ranges ⇒ Verify charting regions ⇒ Verify chart display at various scales ⇒ Note any charts with errors (for further evaluation) ⇒ Install
II) CG ECDIS – Install Electronic Charts
1) Install BSB/RNC format charts
⇒ Verify selected region disc corresponds to provided region map ⇒ Insert Region CD ⇒ Close CD Dialog/Folder – left click small square ⇒ Install RNCs: Load tab > RNCs > Copy ⇒ Check install summary for errors ⇒ Install ENCs: Load tab > ENCs > Copy ⇒ ENCs detected > hit OK ⇒ Check install summary for errors
III) VEGA ECS – Evaluate Performance of RNCs and ENCs
1) Select one (1) major East Coast waterway/port area for evaluation purposes
⇒ Verify chart display at all available scales.
⇒ Select three major and three minor Aids to Navigation (ATON) in the area:
(1) (2) (3) (4) (5) (6)
⇒ Compare ATON information (position, characteristics, etc) between the ENC chart, RNC chart, and Light List data. Note any discrepancies in the section below:
⇒ Perform a query of the chart data in the software for all six AToN and compare to Light List and Coast Pilot information. Note any discrepancies in the section below:
⇒ Compare ENC chart data to online NOAA ENC data. Note any discrepancies in the section below:
2) Select one (1) major West Coast waterway/port area for evaluation purposes.
⇒ Verify chart display at all available scales.
⇒ Select three major and three minor Aids to Navigation (ATON) in the area:
(1) (2) (3) (4) (5) (6)
⇒ Compare ATON information (position, characteristics, etc) between the ENC in the section below:
3) Select one (1) major East Coast waterway/port area for evaluation purposes.
⇒ Verify chart display at all available scales.
⇒ Select three major and three minor Aids to Navigation (ATON) in the area:
(1) (2) (3) (4) (5) (6)
⇒ Compare ATON information (position, characteristics, etc) between the ENC in the section below:
4) Select one (1) major West Coast waterway/port area for evaluation purposes.
⇒ Verify chart display at all available scales.
⇒ Select three major and three minor Aids to Navigation (ATON) in the area:
(1) (2) (3) (4) (5) (6)
⇒ Compare ATON information (position, characteristics, etc) between the ENC in the section below:
IV) Electronic Chart Acceptance Process Summary
1) Taking into account any noted discrepancies in the above procedure, the proposed
USCG electronic chart portfolio (CIRCLE ONE) IS / IS NOT accepted as a production product.
Date of test:
Name of tester:
2) If charts are NOT accepted, the noted discrepancies of this test will be shared with the contractor so that charts can be corrected and re-evaluated.