This is a Questions & Answers document for solicitation 70Z03825QK0000007 for CAD/CAM/CNC Support Services for the US Coast Guard. The document contains seven contractor questions and government responses addressing various aspects of the Performance Work Statement (PWS).

Key clarifications include: required PPE (safety glasses, steel toe shoes, chemical resistant gloves, and respirators), confirmation that all equipment except safety equipment is provided by the Coast Guard, drivers license requirements (state-issued only), and permission to create a fillable Past Performance template. The document also clarifies that while confined space requirements are included in all ALC service contracts, CAD/CAM/CNC staff have not historically needed to enter confined spaces. Additionally, it addresses personnel removal policies, confirming that government approval is required to rehire any individual previously removed from a contract at the government's request. The period of performance dates are referenced in Attachment 1, which is not included in this document.

View the file

Other files for this federal contract opportunity

Other files attached to CAD/CAM/CNC Support Services, newest first.
File Type Posted
A00003 Questions and Answers.pdf PDF
Attachment 2 - Terms and Conditions.pdf PDF
Attachment 5 - CBA.pdf PDF
Attachment 6 - Non-Disclosure Agreement (NDA) DHS Form 11000-6.pdf PDF
Attachment 3 - Performance Work Statement.pdf PDF
Attachment 1 - Schedule of Services - 70Z03825QK0000007.xlsx XLSX spreadsheet
Attachment 4 - Past Performance Information Sheet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A00001 to 70Z03825QK0000007 Questions and Answers

Solicitation Document Question

1.

PWS

Can you clarify the period of performance dates and the start date for this contract?

Answer: Please refer to “Attachment 1 – Schedule of Services – 70Z03825QK0000007” for period of performance dates.

2.

PWS 10.5

What are the required PPEs? How do we provide them within our price given that there is no ODC CLIN?

Answer: Generally, the required PPE includes Safety Glasses, Steel Toe Shoes, Chemical resistant gloves, and possibly respirators. The company shall provide further PPE deemed necessary after a worksite assessment post-award.

3.

PWS 10.8

Confined space entry – what depth are we responsible for? Are we responsible solely for certifying the space Gas free and safe to enter or do we need all the equipment to ventilate the space such as Rhine Air machines and respiratory equipment, and fuel cell non-sparking tools and lighting?

Answer: This section is included in all ALC’s service contracts, but to date CAD/CAM/CNC has not had to go into a confined space. This does not mean that the situation will never arise.

4.

PWS 14.2

What equipment are you specifically talking about? Will it be provided or will it have to be provided, and does it include safety equipment? What safety equipment will need to be repurchased? Will this be purchased from the incumbent contractor?

Answer: All equipment (excluding safety equipment) the CAD/CAM/CNC staff uses for day-to-day operations is provided by the Coast Guard. (e.g., Computers, Software, Industrial Machines and tools)

5. PWS – 5.6

Please clarify the “removal of personnel from the CAD contract or any Government contract” as highlighted in the PWS statement below.

This clearly states that we must request approval before proposing an employee that was removed from any Government Contract at the direction or request of the Contracting agency – not removed by the contractor

Answer: Correct. If an individual is removed at the request of the Government, they must request approval by the Government to rehire the individual.

A00001 to 70Z03825QK0000007 Questions and Answers

6. PWS 10.4.2

Please clarify the license requirements as highlighted in the PWS statement below. Are we talking about drivers' license only or other specific licenses (OSHA, etc.)?

This clearly states driver’s license: All Contractor personnel shall have and maintain a valid state driver's license in order to operate a motorized vehicle on government facilities. A copy of each license shall be provided to the Government administering Contract Specialist and COR.

Answer: A state issued driver’s license.

7.

Past

Performance Template

Government has provided a past performance (PP) template as a PDF file for PP write up. However, it is not a fillable PDF document. Does government intent to provide a fillable PDF file OR is it okay for us to create one on our own as long as it covers all the requested information in the government provided template?

Answer: It is acceptable to create one if all requested information is provided.