This Statement of Work (SOW) details the United States Coast Guard Aviation Logistics Center's requirements for evaluation, calibration, and potential repair of six Air Data Pressure Test Sets (NSN 4920-01-662-3920, Part Number ADTS-3350ER). The contractor (Testvonics Inc.) will be responsible for comprehensive calibration services, including providing calibration certificates, applying calibration decals, and performing functional inspections and repairs as needed. If additional repairs are required beyond the initial evaluation, the contractor must submit a detailed repair estimate to the Contracting Officer for written approval.
Key contractual terms include a 60-day turnaround time, firm-fixed pricing, and the potential to expand the order to up to ten total units within one year of award. The solicitation allows for optional additional units at the same pricing and terms. Repair processes are tightly controlled, requiring detailed documentation, traceability to Original Equipment Manufacturer (OEM) specifications, and written authorization for any repairs exceeding the initial evaluation and calibration price. The anticipated award date is 15 July 2025, with quotations due by 14 July 2025 at 4:30 p.m. Eastern Time, to be submitted via email to Geneva.K.James@uscg.mil.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Terms and Conditions.pdf | ||
| Justification and Approval for Other Than Full and Open Competition.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMBINED SYNOPSIS/SOLICITATION 70Z03825QE0000061
STATEMENT OF WORK (SOW)
CONTRACTOR REQUIREMENTS
Evaluation and Calibration
1. The United States Coast Guard (USCG), Aviation Logistics Center (ALC) will furnish the items listed in the
Schedule for evaluation and calibration.
2. The items under this order are tracked in the USCG’s Asset Computerized Maintenance System
(ACMS). ACMS is the internal management information system used by the USCG to record maintenance and repair actions on aircraft and related systems and components.
3. Items under this order will be shipped to the Contractor with a Significant Component History
Report (SCHR) and a Component Repair Record (CRR). The SCHR records the maintenance history of serial number tracked items. The CRR remains with its corresponding part until the part is determined to be Beyond
Economical Repair (BER) and scrapped. (NOTE: written approval from the Contracting Officer is required prior to scrapping a serial number tracked item.) The Contractor is required to ensure that the SCHR remains with and is returned with the correct part. The Contractor shall retain a copy of the SCHR for 90 Calendar days.
4. In the event that items under this order require repairs which are subsequently reviewed and approved by the
Contracting Officer, the Contractor shall complete and provide a CRR for the repaired items(s). The CRR shall include the NSN, PN, SN, Nomenclature, date of repair, purchase order number, line-item number, a description of all maintenance/repairs that were incorporated. The Contractor’s in-housework may be used to satisfy this requirement if it includes all the required information.
5. The Contractor shall distribute the CRR (or its equivalent) as follows:
• Pack the original, completed CRR with the repaired component.
• Email one (1) copy to the Purchasing Agent at Geneva.K.James@uscg.mil no later than five (5) business days following completion of the repair effort; and
• Retain a copy of each report for 90 calendar days.
6. The items under this order require calibration. Calibration shall be performed after each recertification cycle and shall include adjustments and correction so that the item performs at an acceptable level. Calibration shall also encompass identifying and determining the causes of errors and performing the corrective action(s) when applicable. Calibration shall consist of a comparison of the device under test with a calibration standard of known accuracy. The calibration standard shall be traceable to a national or international standard.
7. Each The contractor shall provide the following:
a) A certificate of calibration for each unit to include a certificate number, name or initials of person performing the calibration, calibration date, unit type, unit manufacturer, unit model number, unit serial number, adjustment or service performed, calibration results, a description of calibration type, type of calibration procedure performed. The certificate of calibration shall be emailed to Purchasing Agent at
Geneva.K.James@uscg.mil and attached to the parking slip when returning the RFI item.
b) A decal on the unit to indicate current calibration. The decal shall include the calibration date, name or initials of person performing the calibration, month and year of when next calibration is due, unit serial number and the name of the company performing calibration.
• Decals shall be applied in such a manner that will not cause damage to the equipment or later when the decal is removed.
• Decals shall not be applied as to hinder the reading of any display.
mailto:Geneva.K.James@uscg.mil
8. If, after visual and functional inspections, an item is found to require repairs, the Contractor shall submit a repair estimate to the Contracting Officer. The quotation shall be valid for at least thirty (30) days and shall include the following:
• A description of each discrepancy found
• Number of labor hours per discipline required to complete each discrepancy
• Cost of part(s)
• Total dollar amount for each discrepancy
• Total dollar amount for complete list of discrepancies
• Estimated repair turnaround time (TAT)
• Purchase order and applicable line item
9. The Contractor must receive a written modification signed by the Contracting Officer that authorizes the repairs prior to the commencement of work. Once the repair quotations are received, the contracting Officer will respond via a written modification within thirty (30) days as to whether the quotes are approved or declined. If approved, the Contractor will be given the quoted TAT (calculated form the date modification is issued) to complete the repairs and return the items to the USCG. If a quote is declined, the contractor will be authorized the firm-fixed evaluation and calibration price established in the order. In addition, the contacting officer will provide instructions regarding Whether the item should be returned as-is or scrapped at the contractor’s facility.
10. The USCG shall not be liable for any amount expended by the Contractor in excess of the applicable firm fixed price reflected in the schedule unless prior written authorization has been given by the Contracting Officer.
Once any repairs have been approved in writing by the Contracting Officer, the following paragraphs apply to the repair process:
11. Items shall be repaired and returned to ready-for-issue (RFI) condition in accordance with (IAW) the Original
Equipment Manufacturer (OEM) minimum functional performance specifications. The Contractor shall correct all deficiencies found in the evaluation. This shall include the replacement of missing or broken parts and the removal of any' foreign matter or corrosion.
12. Work under this purchase order shall be performed at the Contractor's facility. The Contractor shall provide all necessary parts, materials, labor, tooling, test equipment and facilities to evaluate and repair the items listed in this purchase order at the firm-fixed prices listed in the schedule (or modification). The Contractor shall perform all repairs IAW applicable OEM's Component Maintenance Manuals (CMMs), other repair specifications in lieu of an applicable CMM. and/or applicable test/acceptance criteria. Any deviations must be approved by the USCG.
13. The Contractor must have access to required CMMs. repair specifications, test/acceptance criteria and/or any other required data to ensure that all items are tested and repaired IAW the OEM's current specifications and procedures. Original design or functional capabilities of the end item and parts thereof shall not be changed unless authorized or directed by the requirements of this SOW.
14. The Contractor must have access to all applicable documents and obtain current editions of all applicable documents. The USCC does not own, nor can it provide the technical documents specified herein. The closing date the receipt of offers, order award, and/or delivery date will not be delayed pending receipt of these documents for any Contractor.
15. Parts of an item found to be in a serviceable condition as a result of functional testing shall be reused. Missing parts and parts found to be defective or that require replacement by OEM instructions shall be replaced with parts meeting the OEM's specifications and drawings or as otherwise authorized in writing by the Contracting Officer.
Replacement parts shall be new and accompanied by traceability to the OEM. The cost for parts that are replaced systematically during repair shall be included in the price listed in schedule for these operations.
16. The USCG will provide disposition instructions (either to scrap the item at the Contractor's facility or to return the item to ALC) for all items that are determined BER. The Contractor shall not dispose of an item until they have been notified by a written modification to the order. When returning the item to ALC, the items shall be clearly marked as "BER" with the supporting evidence.
17. The USCG shall not be liable for any amount expended by the Contractor in excess of the applicable firm fixed price reflected in the schedule unless prior written authorization has been given by the Contracting Officer.
18. ALC considers items RFI upon acceptance. Items determined to be non-RFI upon installation or operation may be returned to the Contractor for correction at Contractor's expense. Deficiencies will be described in a Product
Quality Deficiency Report (PQDR) and sent to the Contractor prior to the return of any item.
File details come from the government source that posted it. Updated .