This is a Questions & Answers document for federal contract opportunity 70Z03326Q201900002 regarding the Pease Building Rebalance Heating System.
The scope of work involves testing and balancing (TAB) the heating and ventilation systems for an 18,000 square foot facility. The Pease Building utilizes a hybrid system combining hydronic heating (with radiators located under windows in upper-level berthing rooms) supplemented by forced-air ventilation. The work encompasses approximately 23 ventilation zones served by two air handling units—AHU 2 serving the upper level and AHU 3 serving the lower level. Terminal devices within the TAB scope include hydronic radiators, approximately five VAV boxes associated with the upper-level AHU, and nine VAV boxes associated with the lower-level AHU. Official engineering drawings, mechanical documentation, and previous TAB and commissioning reports are managed by the Civil Engineering Unit (CEU) and will be made available upon request during performance; limited reference prints are available on-site. A site visit is highly recommended and available prior to quotation submission, with scheduling details provided in the solicitation instructions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers for:
70Z03326Q201900002
Pease Building Rebalance Heating System
Building square footage of the Pease Building.
The approximate square footage of the Pease Building is 18,000 sq. ft.
Availability of mechanical or HVAC drawings.
Limited reference prints are available on-site. OƯicial engineering drawings are managed by the Civil Engineering Unit (CEU) and will be made available upon request during period of performance.
Number of air handling units (AHUs) included within the scope.
There are two (2) AHUs included in the scope for the Pease Building: one serving the upper level and one serving the lower level.
Number of heating zones to be tested and balanced.
The scope includes the entire building, which consists of approximately 23 ventilation zones.
Number of terminal devices (diƯusers, radiators, VAV boxes, etc.) anticipated within the TAB scope.
The upper-level berthing rooms feature hydronic radiators under each window, along with small supply vents for forced-air heat from the main AHU. There are approximately five (5) VAV boxes associated with AHU 2 (upper level) and nine (9) VAV boxes associated with AHU 3 (lower level).
Availability of any previous TAB reports, commissioning reports, or HVAC system documentation.
Previous TAB reports, commissioning reports, and HVAC documentation are managed by the Civil Engineering Unit (CEU) and will be made available upon request during period of performance.
Whether the facility utilizes a hydronic heating system, forced-air system, or a combination of both.
The Pease Building utilizes a combination of both, featuring a hydronic system throughout the facility supplemented by forced-air ventilation.
Whether a site visit is available prior to quotation submission.
Yes, a site visit is highly recommended and can be coordinated prior to quotation submission.
Please refer to the solicitation instructions for details on scheduling a site visit.