Request for Information Amendment (SF-30)-CCTV Bodega Bay Ammendment 2.doc
DOC document 71 KB Posted
- Attached to
- CCTV Security System Services Federal contract opportunity
- Solicitation number
- 70Z03120PLBB078
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Station BB site map.pptx | PPTX presentation | |
| CCTV-Tech-HBK_0713-508.pdf | ||
| Request for Information Amendment (SF-30)-CCTV Bodega Bay.doc | DOC document | |
| WD 99-0316.txt | TXT text file | |
| FAR Class Deviation 20-05 Rev_1 52.204_25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment signed .pdf | ||
| Bodega Bay Solicitation_dtd_21_August_2020.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE
| PAGE |
| OF PAGES |
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
| 1 |
| 3 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NO. (If applicable) |
| Amendment 0002 |
| August 25, 2020 |
| 6. ISSUED BY |
| CODE |
| 84 |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
| 84 |
Department of Homeland Security
United States Coast Guard
Coast Guard Island Bldg 21 Alameda, CA 94501-5100
Same as Item 6 POC: Mack Kelley (510) 437-3194 E-mail: mack.kelley@uscg.mil
| 8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) |
| (X) |
| 9A. AMENDMENT OF SOLICITATION NO. |
70Z03120PLBB078
| X |
| 9B. DATED (SEE ITEM 11) |
August 25, 2020
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
| CODE |
| FACILITY CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FORMCHECKBOX
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for Receipt of Offers FORMCHECKBOX is extended / XX is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning one copy(s) of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
| CHECK ONE |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A. |
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc)
SET FORTH IN ITEM 14, PURSUANT TO AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority).
E. IMPORTANT: Contractor FORMCHECKBOX is not / FORMCHECKBOX is required to sign this document and return ___ copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The subject solicitation is hereby amended as follows:
A. The purpose of this amendment is to answer bidder’s questions.
B. Per 52.212-1, Instructions to Offerors, (3) Solicitation Amendments. Offerors shall acknowledge all Solicitation Amendments. Offerors shall complete Blocks 8 and 15(a-c) on all Solicitation Amendments (SF-30) issued by the Government and submit with their offer.
C. The closing date is 4 September 2020, 2:00 PM, Eastern.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
Mack Kelley
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
BY:
(Signature of person authorized to sign)
(Signature of Contracting Officer)
NSN 7540-01-152-8070
STANDARD FORM 30 (REV. 10-83) PREVIOUS EDITION UNUSABLE
Prescribed by GSA, FAR (48 CFR) 53.24
Q.1 With the COVID19 and civil unrest issues would the Government authorize an extension to submit the final proposal in order to allow for the vendor to finalize the best quote possible?
A.1 Yes, Deadline has been extended to 4 September, 2020.
Q.2 Could the Government clarify this statement? Is it the desire of the Government for the vendor to remove the (4) existing cameras and offer a new “cover plan” that may require a different quantity of final camera count or is the Government specifing a one for one replacement? If the vendor reads further into Para (4), it has five actual surveillance specified areas identified with a statement of “The CCTV must have the capability to adequately cover the following areas.” Please clarify.
A.2 The legacy system in inoperable & unrecoverable - must be removed. A new camera coverage plan is desired and the camera count was not specified by design. CCTV must be able to capture unit critical areas - this CCTV will not be actively monitored some of the time, so in system design, the notion that this CCTV system will be used for forensic (after the fact) study in these critical areas should be considered.
Q.3 If the Government does desire the vendor to submit a new coverage plan, could the Government provide a current map of the desired coverage areas (coverage area highlighted) and updated buildings so that the vendor can do a map assessment and build the proper coverage plan?
A.3 Yes. Please see Station BB Site Map attachment in the solicitation.
Q.4 Could the Government provide pictures of the current cameras installed? A close up image will allow for the vendor to plan accordingly for tools, materials required for patch work if needed. In addition, it will allow the vendor to assess if the current camera mounting site requires additional preparation work before installing new cameras.
A.4 No, due to COVID-19 and reduced unit visits, SME will not be available to go and take photos of existing cameras.
Q.5 Does the Government require Fixed of PTZ capabilities in the new camera being installed or does the Government required a mix (for example: Fixed on the interiors sites and PTZ on the exterior sites)?
A.5 There is no hard set "requirement" for number / type of cams- per se. The architecture of this system was left vague and open to interpretation by design. See also answer to Q3.
Q.6 The Government specified “Removal of all existing wiring...” Does this mean from the point where the cameras are mounted all the way back to the network switch (please clarify this question if you know what I am asking) or is the Government specifying ONLY at the camera mounted point to disconnect the camera and its immediate wires to the mounting point on the wall /ceiling/overhang?
A.6 All legacy system wiring needs to be removed.
Q.7 If removing wire all the way back to the network switch, will the Government specify the estimated wire run distance from each one of the areas that the Government specified for CCTV coverage back to the central network collection point (i.e. distance from the Armory Gate to Network Switch, distance from the Boat Docks to the network switch…etc.)?
A.7 Unable to provide, due to operations tempo and SME techs inability to travel to site.
Q.8 If removing the wires and installing new wires from the new camera point back to the network switch, can the Government state if there is adequate existing conduit to be used from those locations back to the network switch point or is the vendor required to run new conduit?
A.8 The condition of the existing conduit is unknown. Unable to provide, due to operations tempo and SME techs inability to travel to site.
Q.9 Is there adequate table / desk space for the (2) monitors and base computer or will the vendor be required to provide additional tables?
A.9 Space is or will be made available.