This is a Performance Work Statement (PWS) for integrated pest management (IPM) services for the U.S. Coast Guard's Ninth District facilities. The contractor must provide all personnel, equipment, tools, materials, and supervision necessary to deliver comprehensive pest control services, including suppression of insects, arachnids, rodents and other pests within building interiors and exterior grounds of Air Station facilities, construction sites, and renovation areas.
The period of performance includes a base year from January 15, 2025 through December 31, 2025, with two one-year options through December 31, 2027. Key requirements include initial facility inspections, development of pest management plans, continuous monitoring and inspection programs, trapping devices maintenance, interior/exterior pest control, monthly reporting, and strict compliance with environmental and safety regulations. The contractor must obtain all necessary federal, state and local permits, possess current Commercial Pesticide Licenses, and ensure all personnel applying pesticides have Commercial Applicator's Licenses. Bio-based products are preferred, and the contractor must submit Material Safety Data Sheets for all chemical products 15 days prior to use. The PWS emphasizes an IPM approach that minimizes economic, health and environmental risks through scheduled monitoring rather than predetermined treatment schedules.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
Ninth Coast Guard District AOR
PERFORMANCE WORK STATEMENT FOR
INTEGRATED PEST MANAGEMENT SERVICES
Original 11/13/2024
Revised 1/8/2025
Table of Contents
1. INTRODUCTION
2. BACKGROUND
3. CONTINUITY OF FACILITIES OPERATION
4. APPLICABLE PUBLICATIONS
5. SPECIFIC TASKS REQUIRED
The Contractor shall meet the desired outcome listed in the table below and perform to the standards indicated ...3
5.1 INITIAL INSPECTION
5.2 REQUIRED PLANS
5.3 MONITORING AND INSPECTION
5.4 COORDINATION REQUIREMENTS
5.5 TRAPPING DEVICES
5.6 INTERIOR PEST POPULATIONS
5.7 EXTERIOR GROUNDS
5.8 RECORDS AND REPORTS
5.9 MONTHLY REPORTS
5.10 PESTICIDE PERMITS AND REGULATORY COMPLIANCE
5.11 DEBRIS DISPOSAL
5.12 CHEMICALS
5.13 ON-SITE ENCLOSED DUMPSTER
5.14 HAZARDOUS DEBRIS REMOVAL
5.15 SECURITY REQUIREMENTS
5.16 ENVIRONMENTAL CONTROLS
5.17 POLLUTION ABATEMENT
5.18. FIRE PREVENTION AND PROTECTION
6. DELIVERABLES
7. CONTRACT PERSONNEL
7.1 CONTRACTOR EMPLOYEES
7.2 APPEARANCE
7.3 DRIVERS
7.4 GOVERNMENT HIRES
7.5 TRAINING
7.6 ALCOHOLIC BEVERAGES/DRUGS
7.7 VISITORS
7.8 CONDUCT
8. QUALITY CONTROL REQUIREMENTS
8.1 GENERAL
8.2 PERFORMANCE EVALUATION MEETINGS
9. QUALITY ASSURANCE REQUIREMENTS
10. GOVERNMENT FURNISHED ITEMS AND SERVICES
10.1 WATER
10.2 UTILITIES
11. CONTRACTOR-FURNISHED ITEMS CONTRACTOR FURNISHED
11.1 CONTRACTOR FURNISHED EQUIPMENT NAD SUPPLIES
11.2 CONTRACTOR FURNISHED VEHICLES
12. TECHNICAL EXHIBITS
12.1 BASE MAP (SEE ATTACHMENT XX)
12.2 BUILDING DESCRIPTION AND SQUARE FOOTAGE
11/13/2024 Page 1 of 13
PERFORMANCE WORK STATEMENT (PWS)
1. INTRODUCTION
The purpose of this PWS is to obtain an efficient and effective Integrated Pest Management
(IPM) Program at as many units within U.S. Coast Guard (USCG) District Nine as possible.
The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to provide IPM Services as defined within this PWS. The
Contractor shall be responsible for the management of the total facilities identified in this
PWS. This is to include the suppression of all insects, arachnids, rodent populations and any other pest not specifically excluded from this solicitation and subsequent contract. Pest populations located within building interiors and the exterior grounds within the property boundaries of the identified Air Station Facilities, Construction Sites and Renovation areas are included under this effort.
This effort also includes the sealing of minor cracks, crevices and holes that serve as known pest harborage, or permit pest ingress and egress. The Government will be responsible for any work related to the building components such as structural members, furnishings, etc.
affected including the removal of damaged material and any associated repairs.
The services to be performed will rely heavily on knowledgeable, experienced, individuals capable of servicing the facilities in an orderly, clean, and environmentally healthy manner.
The Contractor shall ensure that all services protect the integrity of the units, while protecting human health and the environment.
2. BACKGROUND
IPM is the preferred method for USCG pest management and disease vector control. IPM is a sustainable approach to managing pests and controlling disease vectors by combining applicable pest management tools in a way that minimizes economic, health, and environmental risks. IPM uses regular or scheduled monitoring to determine if and when treatments are needed and employs physical, mechanical, cultural, biological, genetic, regulatory chemical and educational tactics to keep pest numbers/populations low enough to prevent unacceptable damage or impacts. Treatments are not made to a predetermined schedule; they are made only when and where monitoring has indicated that the pest will cause unacceptable economic, medical, or aesthetic damage. Treatments are chosen and timed to be most effective and least disruptive to natural controls of pests. Least hazardous, but effective pesticides are used as a last resort. The costs for all treatments are included in the contract amount.
IPM in the USCG is based on seven (7) steps that are routine procedures for addressing each pest problem. These steps are:
a. Identification and assessment of pest or disease vector problems.
b. Development of a written management plan or strategy that emphasizes natural controls and non-chemical tactics to deal with pest and disease vector problems.
c. Establishment of an action threshold for each pest and disease vector problem to
11/13/2024 Page 2 of 13 define when corrective action must be implemented.
d. Use of a monitoring procedure, such as inspection, trapping, or surveillance, for each pest and disease vector.
e. Application of corrective action when a threshold is reached for any pest or disease vector.
f. Use of a documentation system to catalogue monitoring information and to document management problems.
g. Verification and evaluation procedures to ensure that the IPM program is meeting stated risk reduction measures and that information exists to redesign the IPM plan where required.
The IPM services are generally accomplished through a proactive service performed as regular inspections and reactive services performed as a response to service requests.
3. CONTINUITY OF FACILITIES OPERATION
The Contractor is to perform all on-site work between the hours of 8:00 AM and 4:00 PM, Mon- day through Friday (Federal Holidays excluded), unless otherwise approved by the
Contracting Officer or COR.
4. APPLICABLE PUBLICATIONS
The Government will provide all publications listed that are not readily available to the contractor upon request of the Contractor. Supplements or amendments to listed publications may be issued during the life of the contract. The Contractor shall immediately implement those changes, which result in a decrease, or no change in the contract price. The
Government will also pro- vide the forms listed which are needed for daily operations. Upon completion of the contract, the Contractor shall return to the Government all issued publications and unused forms.
Document Publication Title
USCG PUBLICATIONS
COMDTINST M5100.47 Safety and Environmental Manual
FEDERAL PUBLICATIONS
29 CFR (OSHA) Labor
29 CFR 1910.120 Occupational Safety and Health Standards
40 CFR Protection of the Environment
PL 94-580 Resource Conservation and Recovery Act
11/13/2024 Page 3 of 13
5. SPECIFIC TASKS REQUIRED
The Contractor shall meet the desired outcome listed in the table below and perform to the standards indicated:
Performance Based Matrix
Desired Outcome Standard for Successful Performance
The Contractor shall provide, establish and maintain safe, effective and environmentally sound IPM pro- gram to prevent or control pest and disease vectors that may adversely impact readiness or military operations by affecting the health of personnel or damaging structures, materiel or property.
• 98 Percent of specific sites of actual or potential pest infestation identified.
• 100 percent of existing populations sup-pressed with corrective solutions.
• 100 percent of areas vulnerable to infestation managed.
• 100 percent of required records accurately maintained and reports submitted timely per the Contracting Officer and COR.
• Effectiveness of the IPM actions systematically evaluated.
• Requests for service responded to in re-quired timeframes 95 percent of the time.
• Appropriate level of toxicity applied per the Contactors approved plan.
• The Contractor is cooperative, committed to customer satisfaction and has a business-like concern for the interest of the customer.
5.1 INITIAL INSPECTION
The Contractor shall make a thorough initial inspection of the all premises covered to evaluate and inventory its pest management needs within sixty (60) calendar days after Contract award.
The Contractor shall brief the Contracting Officers Representative (COR) on all findings in writing within ten (10) days after the initial inspection.
The Contractor shall continue to respond to routine service requests while performing this inspection.
5.2 REQUIRED PLANS
IPM (Integrated Pest Management) Plan: The Contractor shall submit the following detailed plans:
5.3 A plan detailing proactive and reactive strategies for interior, exterior, and
11/13/2024 Page 4 of 13 miscellaneous IPM requirements on Coast Guard property. IPM required with quote, submitted to Contracting Officer (KO) and COR and your approval
5.4 MONITORING AND INSPECTION
A critical aspect of the pest management plan shall be implementation of a continuous monitoring and inspection program to identify problem zones and allow an objective assessment of pest population levels and to identify procedural and structural deficiencies that contribute to pest infestations.
The Contractor shall report findings and make detailed, site specific recommendations in writing for corrective action to the COR.
The Contractor shall give special attention to the Government sanitation, waste management, and repair/alteration activities.
Recommendations to the Government that can aid in the overall pest suppression effort may involve improvement in cleaning or storage practices, installation or repair of screens and barriers, application of caulk and other sealants, patching of structural gaps, repairing leaks and draining or filling exterior sites.
5.5 COORDINATION REQUIREMENTS
The Contractor shall provide services in accordance with a Government approved detailed pest management plan and inspection and service schedule developed for each building.
Contractor shall perform services that do not adversely affect tenant health or productivity during the hours of operation in the various buildings. Contractor shall coordinate access to building space, including restricted areas, and the scheduling of service with the COR.
When it is necessary to perform work on weekends or outside the regularly scheduled hours set in the Contractor’s plan and schedule, the contractor shall notify the COR at least two (2) workdays in advance. If a particular treatment requires an area to be vacated, the
Contractor’s shall notify the COR at least two (2) workdays in advance of the treatment;
provide and post all necessary signage; ensure the security of the area being treated; and remove signage when the area is safe for entry.
5.6 TRAPPING DEVICES
The Contractor shall:
a. Check all trapping devices use anticoagulant or similar products used in rodent
(Norway Rats, mice and other rodents) management on a routine basis.
b. Dispose of rodents killed (including dead carcasses on the exterior grounds) or trapped.
c. Place traps out of general view and where routine cleaning procedures are not affected.
d. Map the location of all trapping devices or bait boxes and submit copies to the COR.
e. Service and maintain all bait boxes on a scheduled basis and in accordance with
Environmental Protection Agency (EPA) regulations, assuring the safety of non-target species.
11/13/2024 Page 5 of 13
f. Assure 100 percent compliance with all Federal, State, and Local laws, regulations, and/or special ordinances regarding nuisance wildlife management.
g. Check all live traps for nuisance wildlife on a routine basis.
5.7 INTERIOR PEST POPULATIONS
The Contractor shall manage interior pest populations. The contractor shall ensure that:
a. All products are applied according to the manufacturer’s label.
b. All trapping devices are labeled and dated at installation and each service.
c. No airborne pesticides are applied.
d. No rodent poisons are applied.
5.8 EXTERIOR GROUNDS
The Contractor shall manage the exterior grounds pest issues. The Contractor shall ensure that:
a. Urban insect pests are managed.
b. All mammalian populations and/or individuals are managed.
c. All products are applied/used according to the manufacturer’s label.
d. All trapping devices and bait boxes are labeled and dated at installation and each servicing.
e. All trapping devices and bait boxes are accounted for at all times.
f. All trapping devices and bait boxes are removed from the premises when not in use.
g. All live trapping is conducted humanely and professionally.
h. All Federal, State, and Local laws, regulations, or special ordinances regarding nuisance wildlife management are obeyed.
i. All live traps are routinely checked.
5.9 RECORDS AND REPORTS
The Contractor shall maintain complete and accurate records for each building and area that include, but are not limited to:
a. Monitoring data indicating pest population levels (graphs and/or charts utilized to reflect monthly and seasonal variation)
b. Locations of pest infestations, numbers of pests trapped or killed, new rodent burrows observed, etc.
c. Inspection data indicating findings and recommendations concerning other program areas involved in the IPM process;
d. Pesticide application data including the name of the product used or applied, amount ap- plied, method of application, location(s) of treated area(s), Material Safety Data
Sheets (MSDS), etc.
e. Location and service of all bait stations and trapping devices on the premises.
11/13/2024 Page 6 of 13
5.10 MONTHLY REPORTS
The Contractor shall submit a monthly report to the Contracting Officer’s Representative by the fifteenth (15th) calendar day of the following month detailing the performance of the
Contractor. The Contractor shall include, but is not limited to, the following information:
a. A general performance overview of the month;
b. Updates/progress reports of any pertinent schedules;
c. An accurate amount of each product used/applied;
d. An accurate number of rodent kills;
e. A calendar of events, plans, meetings, and/or special situations for the next 60 days;
f. Any special activities accomplished;
g. Frequency of office complaints per month (categorized by pest species, such as cock- roaches, ants, mice, rats, Norway rats, etc.).
h. Customer “callbacks” due to large, recurring pest populations. The instance of relatively large, recurring pest populations is quantifiable based on an atypical number of calls to one or more locations within the building, or during specific times of the year.
5.11 PESTICIDE PERMITS AND REGULATORY COMPLIANCE
The Contractor shall obtain any Federal, State, and Local permits required for the use of any pesticide and/or herbicide used under this contract at no additional expense to the
Government. All pesticides/herbicides shall be procured, possessed, and labeled as registered with the EPA and the State of Alaska pursuant to the Federal Insecticide, Fungicide and Rodenticide Act as applicable. Each product shall be so registered for use under the particular environmental conditions under which it is applied as directed by
Federal, State or Local agencies. The Contractor shall possess for the state in which they are operating, all State Licenses required by law. The Contractor shall possess a current
Commercial Pesticide License. All Contractor personnel that apply pesticides shall have a current Commercial Applicator’s License and required training.
Bio-based products are preferred.
5.12 DEBRIS DISPOSAL
Debris shall be removed; sidewalks and paved areas cleaned, and all trash from the
Contractor’s operations shall be removed from the site. The Contractor shall dispose of all debris resulting from clearing work in accordance with Federal, State, and Local regulations.
5.13 CHEMICALS
The Contractor shall furnish to the COR, prior to the initial application of pesticides, the
MSDS on all chemical products to include trade names, chemical names and a label showing the con- tents and the use strength of the chemical as applied and antidote thereto.
The Contractor shall furnish this information each time there are changes in chemicals or
11/13/2024 Page 7 of 13 products used in the performance of this contract.
MSDS or EPA Certification Labels will be submitted to the COR for all chemical products to be used for approval at least 15 days prior to use. Chemical products refer to, but are not limited to, such items as herbicides, pesticides, fungicides, fertilizers, etc. The contractor shall also submit a copy of the manufacturer’s recommendations for all chemical, seed, and plant products used under this contract 15 days prior to any application.
5.14 ON-SITE ENCLOSED DUMPSTER
If the Contractor provides a dumpster for the collection of rodent debris generated by the
Con- tractor’s employees, the contractor shall be responsible for the servicing of the dumpster.
5.15 HAZARDOUS DEBRIS REMOVAL
All hazardous debris and policed items shall be transported off site on a daily basis and dis-posed in accordance with applicable federal, state, and local regulations. Debris and policed items shall be transported in tarp covered or closed vehicles. Any materials dripped or blown off the vehicles shall be immediately picked-up by the contractor. All scrap materials and debris shall be disposed of daily in accordance with all applicable federal, state and local regulations.
5.16 SECURITY REQUIREMENTS
5.15.1 PERSONNEL. The Contractor shall maintain a current listing of all employees, including sub-contractors. The list shall include employee’s names and social security numbers. This list shall be validated by the contractor’s manager and provided to the KO and each Units Security Officer prior to the Contract start date. The listing shall be updated and provided upon change of employee(s). Contractor personnel not listed may be denied access to the Coast Guard facility.
5.15.2 KEY CONTROL. The Contractor shall establish and implement methods for the safe- guarding of all keys issued by the government to the contractor for use by contractor employees. The Contractor shall ensure that keys are not lost or misplaced and are not used by unauthorized persons. The Contractor shall immediately report to each Unit's
Engineering Office, COR, or KO any occurrences of loss, unauthorized use, or unauthorized duplication of keys. In the event keys, other than master keys are lost or duplicated, the contractor may be required, up-on written direction of the Contracting
Officer, to re-key or replace the affected lock of locks without cost to the government. The government may, however, at its discretion, replace the affected lock
(s) or perform the re-keying and deduct the cost of such from the monthly payment due to the Contractor. The Contractor shall control access to all government provided lock combinations to preclude unauthorized entry.
11/13/2024 Page 8 of 13
5.16 ENVIRONMENTAL CONTROLS
The Contractor shall ensure policies and procedures are established that protect the health and safety of employees and the community to minimize or eliminate the risk of environmental pollution.
5.16.1 PESTICIDES. Selective pesticides shall be applied in strict compliance with the products EPA and/or each respective state's registered labeling. All manufacturers’ instructions and recommendations for the preparation and application of herbicides and pesticides shall be strictly followed. In addition, the Contractor shall comply with all other applicable federal, state, and local laws and regulations concerning the application, storage and disposal of such hazardous material.
Pesticides used at U.S. Coast Guard installations shall be approved in advance and in writing by the CO and the Coast Guard Hazardous Material Specialist. The Contractor shall not illegally dump or dispose of any pesticides. The Contractor shall follow pesticide label directions and shall not spray pesticides if the wind is exceeding 10 MPH. Bio-based products are preferred.
5.16.2 NOTIFICATION OF ENVIRONMENTAL SPILLS. If the contractor spills or releases any substance listed in 40 CFR 302 into the environment, the Contractor shall immediately re- port the incident to the COR. The contractor shall be liable for the containment and environmental clean-up of the spill or release of such substance.
5.16.3 HAZARDOUS MATERIALS HANDLING PROCEDURES The Contractor is responsible for advising his employees of all Environmental and Hazardous Materials
Handling Procedures. The Contractor is required to have and maintain MSDSs for all materials used in the day to day operations. All materials shall be handled in accordance with federal and state laws and/or regulations and the Occupational Safety and Health
Administration (OSHA) requirements. In the event of a spill of hazardous substances/materials, the Contractor shall immediately contain, clean-up and remove all hazardous substances/materials in accordance with all applicable federal, state, and local regulations. The contractor shall ensure that his operations do not expose any personnel
(government or contractor) to any hazardous conditions (i.e. chemicals, etc.) as covered by all applicable federal, state and local regulations.
5.16.4 PESTICIDE/EQUIPMENT STORAGE. The USCG will not provide storage areas for pesticides/equipment.
5.17 POLLUTION ABATEMENT
5.17.1 RODENT DEBRIS. The Contractor shall ensure that transportation of any rodent debris or policed materials from the site shall be accomplished in a manner preventing pest debris from becoming exposed or uncovered: such as covered vehicles or enclosed dumpster boxes. The Contractor shall ensure that vehicles used for pesticide applications will carry an approved spill containment kit capable of containing any spill until first responders arrive. Any and all rodent/pest debris shall be removed off site at the
Contractor’s expense.
11/13/2024 Page 9 of 13
5.17.2 DRAINAGE. The contractor will ensure that drainage ways, sanitary sewers, storm sewers, etc., shall not be polluted by pesticides or other harmful materials. If any of these materials are inadvertently spilled into these areas, the Contractor shall immediately notify the COR or the Unit's Hazardous Material Specialist.
5.18. FIRE PREVENTION AND PROTECTION
The Contractor and his employees shall comply with USCG’s Fire Protection Plan. A copy of this plan may be obtained from the COR. Unit fire prevention personnel may make periodic routine inspections for regulation compliance. Burning of any material on USCG property by the contractor is prohibited.
6. DELIVERABLES
The Contractor shall comply with all federal, state and local environmental protection statutes and regulations, as well as applicable USCG instructions, directives, attachments and exhibits listed in the table below pertaining to the services required herein and to the conduct and qualifications of personnel in performance of this contract. The Contractor shall utilize safe products and equipment and qualified personnel to ensure the health and safety of all are in compliance with EPA and OSHA regulations.
Report Ref Due Date Distribute To:
Initial Inspection Report PWS 5.1 10 days after inspection COR
Pesticide/Herbicide Permits PWS 5.10 / 5.16
15 days prior to start of contract
COR
State Pesticide License
PWS 5.10 /
5.16
15 days prior to start of contract
COR
List of Contractor Personnel
PWS 7 15 days prior to start of contract and as needed
COR / KO
Monthly Report PWS 5.9 15 calendar days after the preceding month.
COR / KO
Quality Control Plan PWS 8 15 days prior to start of contract
COR / KO
Material Safety Data Sheets or EPA Certification Labels
PWS 5.12 15 days prior to start of contract and as needed thereafter
COR
A plan detailing proactive and reactive strategies for interior, exterior, and miscellaneous IPM requirements on USCG property.
PLWS 5.2 Prior to contract award KO
11/13/2024 Page 10 of 13
A detailed exterior rodent control plan for the
PWS 5.5 /
5.7
Prior to contract award KO
Certificate of Liability
Insurance
Solicitation 15 days prior to start of contract, and when annually renewed
KO
7. CONTRACT PERSONNEL
7.1 CONTRACTOR EMPLOYEES
The Contractor shall not employ persons for work on this contract if such employee is identified to the contractor as a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population. The Contractor personnel must be able to read, write, and understand English sufficiently well in order to carry out all duties assigned to them.
7.2 APPEARANCE
Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. The contractor shall provide each employee with an identification badge that shall include the employee’s name, employee’s photograph, and contractor’s name.
Identification shall be available prior to employment and shall be worn or attached to the outer garment at all times.
7.3 DRIVERS
To drive on a Government installation, the Contractor’s employees must have a vehicle registration, a valid state driver’s license, automobile insurance as required, and operate the vehicle in accordance with base traffic regulations. All vehicles must be insured in accordance with State laws.
7.4 GOVERNMENT HIRES
The Contractor shall not employ any person who is an employee of the United States
Government if employing that person would create a conflict of interest or the appearance of a conflict of interest. Additionally, the contractor shall not employ any person who is an employee of the USCG, either military or civilian, unless such person seeks and receives approval according to USCG procedures.
7.5 TRAINING
The Contractor shall provide environmental, health, and safety training to ensure compliance with all federal, state, and local laws or regulations.
11/13/2024 Page 11 of 13
7.6 ALCOHOLIC BEVERAGES/DRUGS
The use, possession, or sale of alcoholic beverages or illegal drugs by the Contractor or its personnel while on duty is strictly prohibited. The Contractor shall immediately remove any employee who uses, possesses, or sell alcohol or drugs while on Coast Guard property.
Removal of the employee for such causes does not relieve the Contractor of the requirement to provide sufficient personnel to adequately perform services.
7.7 VISITORS
Contractor employees shall not bring visitors without the expressed permission of the COR.
7.8 CONDUCT
Contractor employees shall not loiter Coast Guard property. Upon completion of their performance, shall promptly depart the Air Station.
8. QUALITY CONTROL REQUIREMENTS
8.1 GENERAL
The Contractor, not the Government, is responsible for quality control and management actions to meet the terms of the Contract. The Government performs quality assurance to monitor whether Contract standards are achieved. The Contractor shall provide a Quality
Control Plan (QCP) that contains, as a minimum, the following items, prior to contract start date:
1. A description of the inspection system to cover all tasks and services listed in this performance work statement. The description shall include specifics as to the areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, submission of quality control inspection schedule(s), and the title and organizational placement of inspectors.
2. A description of records to be kept for document inspections and corrective or preventative actions taken. The records of inspections shall be kept and made available to the government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract.
3. The Contractor shall provide a customer complaint form for correction of complaints.
8.2 PERFORMANCE EVALUATION MEETINGS
The KO may require the Contractor to meet with the KO, Contract Specialist, COR and/or other government personnel as deemed necessary. The Contractor may request a meeting with the KO when the Contractor believes such a meeting is necessary. Written minutes of any such meetings shall be recorded and signed by the Contractor and the KO or Contract
11/13/2024 Page 12 of 13
Specialist. If the Con- tractor does not concur with any portion of the minutes, such non-concurrence shall be provided in writing to the KO within five (5) calendar days following receipts of the minutes from the Government.
9. QUALITY ASSURANCE REQUIREMENTS
The Government reserves the right to inspect the Contractor’s job performance at any time during the duration of this contract as outlined in the QASP. The Government
Representatives may inspect each facility or other location as completed or vary the number of quality assurance inspections at their discretion. The Government will also investigate any complaints from various customers located on the installation. The Contractor shall be responsible for initially validating customer complaints. However, the Government representative shall make the final determination of the validity of customer complaint(s) in cases of disagreement with customer(s). The Government reserves the right to inspect the
Contractor’s performance in its entirety to ensure services are received. If the Government discovers unsatisfactory performance, the Government's preferred course of action will be discussions with the Contractor. However, the Government may also take further actions as outlined in the Performance Requirement Summary (PRS).
10. GOVERNMENT FURNISHED ITEMS AND SERVICES
10.1 WATER
The Government will provide access to sink rooms (with utility sinks), where available, at various points throughout the building. The Government will provide hot and cold water as necessary for the Contractor to perform the requirements herein and limited to the normal water sup- ply provided in the building. The Contractor shall not use these rooms for storing equipment. The Contractor shall keep sink room doors closed, locked and the light(s) and water turned off when not in use.
10.2 UTILITIES
The Contractor shall make sure contractor employees practice utilities conservation. The
Contractor shall operate under conditions that prevent the waste of utilities to include turning off lights when not in use and turning off water faucets or valves when not in use.
11. CONTRACTOR-FURNISHED ITEMS CONTRACTOR FURNISHED
11.1 CONTRACTOR FURNISHED EQUIPMENT NAD SUPPLIES
Unless otherwise specified, the Contractor shall furnish all personnel, equipment, tools, materials, supervision, and other items and services necessary to provide for the performance of work under this Contract. The Contractor shall only use supplies and materials that conform to the principles of IPM. All supplies, materials, and equipment used in the work described herein are subject to approval by the COR.
11/13/2024 Page 13 of 13
11.2 CONTRACTOR FURNISHED VEHICLES
Contractor provided vehicles shall meet all local, state, and federal safety requirements.
Each Contractor vehicle shall have the name of the contractor neatly exhibited on each side of the cab. The contractor shall operate vehicles to comply with base traffic regulations. Vehicle mounted communication equipment shall conform to all applicable base and federal frequency regulations. Vehicles shall be maintained clean to present a professional appearance.
11.3 PERIOD OF PERFORMANCE
Base Year: January 15, 2025 – December 31, 2025
Option Year 1: January 1, 2026 – December 31, 2026
Option Year 2: January 1, 2027 – December 31, 2027
Contracting Regulations: FAR 17.1 and DFARS 217.1
12. TECHNICAL EXHIBITS
12.1 BUILDING DESCRIPTIONS, ADDRESSES, SQUARE FOOTAGE AND
CURRENT SERVICING VENDOR