This Statement of Work (SOW) details maintenance and repair requirements for four U.S. Coast Guard housing units located in Union City, Tennessee. The project involves comprehensive rehabilitation services for homes at 844 Gum Street, 854 Gum Street, 815 Olive Street, and 825 Olive Street, with specific focus on 854 Gum Street requiring extensive remediation. Scope of work includes pressure washing exterior surfaces, conducting foundation inspections, extensive kitchen and bathroom renovations, mold remediation, attic fan removal, ceiling repair, and subfloor and flooring replacement. The contractor must be state-licensed, provide all labor, materials, and equipment, and complete work within 15 calendar days after receiving contract approval, with work performed between 8:00 AM and 4:00 PM, Monday through Friday. The project is designated as a small business set-aside under NAICS code 236118 (Residential Remodelers), with a mandatory site visit scheduled for July 23, 2025, and quotes due by August 1, 2025, at 5:00 PM CST.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Wage Rate TN20250005.txt | TXT text file | |
| SOW.pdf | ||
| Construction Clauses (Mar) 2025.odt | ODT document | |
| SF1442 Union City.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
Maintenance and Repair CG Housing Union City
Located at U.S. Coast Guard Housing
Union City, TN Union City, TN 38261.
July 2025
Commanding Officer
United States Coast Guard Base New Orleans, LA
Facilities Engineering Department New Orleans, LA 70129
LT John Dunaway Facilities Engineer Base New Orleans, LA
PART 1: GENERAL
1. INTENT: The intent of this project is to perform exterior maintenance and repair to four (4) CG owned homes and interior mold remediation and repair to one (1) house in Union City, TN, Located at 844 Gum Street, 854 Gum Street, 815 Olive Street, and 825 Olive Street Union City, TN 38261. All work must be completed by state licensed contractor. All materials and installation shall meet or exceed applicable state code and follow industry standards. All work shall be completed as outlined in this Scope of Work. No work is authorized without the authorization of the Contracting Officer (KO) or the Contracting Officers Representative (COR).
2. BACKGROUND: Properties are approximately 1,600 -1,800 square feet, single-family homes located within Union City, TN. All four homes are brick construction with vinyl siding in each carport; all foundations are crawlspace foundations. The home at 854 Gum Street will be the one that requires demo and replacement of the bathrooms, mold remediation in the kitchen, sub-floor repair and flooring replacement, and attic floor repair. A hole in the attic was discovered that was behind the kitchen wall which created a condensation buildup and led to mold growth along kitchen cabinets.
3. SCOPE OF WORK: Contractor shall furnish all labor, tools, materials, transportation, equipment, supervision, and personnel to perform pressure wash exterior surfaces on all four (4) homes and conduct foundation inspections on all four (4) homes. In 854 Gum street, demolish all kitchen cabinets, bathroom fixtures and shower, flooring, and replace with new. Clean all surfaces and replace as necessary due to mold in kitchen area as well as treat the HVAC system to ensure eradication of any mold. Remove, insulate and cover attic ventilation fan in ceiling and match to existing finish and repair and insulate hole in attic to ensure sealed attic envelope. No repairs outside of the Statement of Work criteria are authorized without permission from the contracting officer or their representative.
4. QUALIFICATIONS: Contractor shall provide personnel who have the knowledge, qualifications, and working experience to perform the functions outlined in this Scope of Work. All personnel shall be properly licensed by the state.
5. CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facility’s normal operations. Perform all on-site work between the hours of 8:00 AM and 4:00 PM, Monday through Friday (federal holidays excluded), unless otherwise approved by the Contracting Officer or Contracting officer’s representative.
6. GOVERNMENT FURNISHED MATERIALS: None
7. GOVERNMENT FACILITIES AND UTILITIES: Electrical power and water are available within proximity.
The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded. Telephone services will not be available for use by the contractor. Building restroom facilities are available for use.
8. SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with and abiding by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued. In the event of Hot Work, the Contractor will notify the COR with dates and times Hot Work will be performed. Contractor is to give at least 48 hours notification. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.
9. ENVIRONMENTAL COMPLIANCE: Any waste generated because of the project shall either be recycled or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Base New Orleans listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW RCRA and all applicable federal, state (i.e. DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. All chemicals required for this project shall be pre-approved by the contract POC along with SDS’s.
All solid waste shall be removed from the residence after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To- Know Act requires Coast Guard maintains an inventory of all Hazardous Materials located at the site. A laydown area as required and an Erosion and Sediment Control Plan, shall be preapproved by the COR as needed. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence.
10. SITE VISIT: Site All site visits should be scheduled with the Contracting Officers Representative.
• Contracting Officers Representative (COR)
LT John Dunaway Cell: (504) 628-6294 Email: john.d.dunaway@uscg.mil
11. MATERIALS:
a) The Contractor will furnish all materials, equipment, instruments, tools, safety lines and harnesses, and other items necessary for accomplishment of these services.
b) Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight and kept away from excessive heat. The contractor shall not store any highly flammable materials in the work area and all chemicals used shall be preapproved by POC.
Laydown areas and parking should be on non-vegetated areas when possible.
c) The Contractor is required to comply with local VOC laws and regulations. All applicable Safety Data Sheets shall be available upon request.
12. LIABILITY OF CONTRACTOR: Any damage to government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the government. The contractor shall not disconnect any service without approval from the Technical Representative.
PART 2 PERFORMANCE STANDARDS
1. PERFORMANCE REQUIREMENTS: Contractor shall provide all materials and labor to complete all work at
854 Gum St, 844 Gum st, 815 Olive st, and 825 Olive st Union City, TN. All supplied materials shall match current configurations and colors of existing conditions unless local code dictates otherwise. All repairs shall comply with state building codes and follow industry standards. All replacement materials shall be approved by the COR prior to purchase. Refer to part 2-6 for instructions on submittals.
Exterior Repair and Maintenance of all four Homes:
a) Pressure wash/clean all four unit’s exterior surfaces to include: walls, walkways, driveways and sheds. Do not clean roofs.
b) Complete an inspection of all exterior surfaces make report to COR of any necessary repairs.
c) Remove all jobsite debris and dispose off-site.
mailto:john.d.dunaway@uscg.mil
Conduct Foundation inspection of all four homes:
a) Conduct foundation inspections of all four homes crawl space foundations for signs of deterioration or sinking and make report to the COR speaking to their condition and any necessary repairs with pricing.
854 Gum Street Kitchen Mold Remediation and Repair:
a) Remove and dispose all existing cabinetry, counter tops, backsplash, fixtures.
b) Provide plan for COR approval with new finishes and floor plan to include cabinets, counter tops, backsplash, fixtures including microwave with exhaust hood. Existing Fridge, dishwasher, and range must be reused in new layout
c) Clean and assess all mold areas and paint/replace drywall where necessary. Perform HEPA vacuum and air scrubbing to ensure all mold is eradicated.
d) Furnish and install all components of approved kitchen plan.
e) Connect all water, electrical and gas lines.
f) Operational test of all installed equipment.
g) Remove all job site debris
854 Gum Street Bathroom Repair:
a) Remove and dispose of existing tub/shower combo, vanity, mirror, light and water fixtures in full bath and vanity, mirror, light and water fixtures in half bath.
b) Ensure area is clean and absent from mold/mildew.
c) Provide plan for COR approval to replace vanity, lights, sink, sink top, water fixtures. Shower replacement should include an insert option and an insert tub with tile backsplash option.
d) Connect all water and electrical lines.
e) Remove all job site debris
854 Gum Street Attic Fan removal and ceiling repair:
a) Remove and dispose of existing attic exhaust fan.
b) Repair hole in ceiling to match attic access with foam board insulation backing on ¾” plywood; paint to match existing ceiling color, trim to match attic access.
c) Properly cap all electrical connections.
d) Repair hole in attic and ensure attic is properly insulated and sealed to prevent future mold issues.
e) Remove all job site debris
854 Gum Street replace subfloor and flooring:
a) Remove all existing carpet and pad flooring to expose subfloor. Assess subfloor and repair up to ~25% of subfloor as needed.
b) Furnish and install LVP flooring system throughout ~1000 sqft. to match existing LVP, Bathroom floors will remain.
c) Remove all job site debris
2. LABOR LAWS: The Service Contract Act applies to the procurement.
3. SITE RESTORATION & CLEAN UP: The work site shall be cleaned up at the completion of each workday.
Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of any trash, extra materials, dirt, debris, or other litter that remains, off-site. There will be no final acceptance of the contract until the Contracting Officers Representative approves the appearance of the job site.
4. GOVERNMENT FACILITIES AND REGULATIONS: The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Base/Unit regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties. There shall be No Smoking on the property.
5. CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting Officer.
a) Provide all required submittals to the Contracting Officer within 7 calendar days after contract award.
b) The U.S. Coast Guard will have 4 calendar days to review the submittals and respond to Contractor.
c) Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 14 calendar days after the contract has been awarded.
d) The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 Calendar days to begin work on the project & 15 Calendar days to complete. The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.
6. SUBMITTALS: All potential vendors shall provide a quote for repair with one (1) line item as an option:
flooring replacement at 844 Gum St. Once awarded, the following list of submittals required for approval defines the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance of the material with these specifications and referenced specifications.
i. Work schedule
ii. Foundation inspection report with recommended repairs with pricing
iii. Kitchen and Bathroom layout plans with list of components
iv. Quote for additional repair as needed outside this scope of work.
v. Manufactures and Workmanship Warranty Information
7. EXECUTION: Installation, workmanship, fabrication, assembly, erection, examination, inspection, and testing shall be in accordance with appropriate sections of 29 CFR 1910, 1926.
a) The Contractor shall schedule all work with the Technical Representative. The Contractor shall understand the importance to schedule and complete all work in a timely fashion. The Contractor shall minimize the impact for the command and/or mission of the personnel located at each location.
b) The Contractor shall perform all work IAW all Federal, EPA, OSHA, and State of Tennessee laws and regulations.