This is an Amendment 0001 Attachment Page containing clarifications to a federal roofing contract solicitation in the form of Questions and Answers.

The amendment addresses five key clarifications regarding roofing specifications and project requirements. Contractors are permitted to price standard contractor and manufacturer warranties rather than specific 10, 15, or 20-year no dollar limit warranties. The roofing membrane thickness is specified as 60 mil TPO. Regarding existing coping caps associated with the metal panel system, contractors must refer to the Statement of Work for removal and replacement requirements. For compliance with UFC 3-110-03 Roofing standards, the roof shall be replaced per Statement of Work requirements as a same-in-kind replacement matching the existing roof, clarifying that additional components such as vapor barriers, gypsum substrate board, and gypsum coverboard are not mandated beyond those requirements. The period of performance for the project is established at 10 working days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 0001 ATTACHMENT PAGE

1. QUESTION: Please advise if contractors need to price a 10, 15 or 20 year no dollar limit roofing warranty for this project?

ANSWER: Whatever is the standard contractor and manufacture warranty is sufficient.

2. QUESTION: What is the thickness of the roofing membrane required 80 or 60 mil TPO?

ANSWER: 60 mil TPO.

3. QUESTION: Will the existing coping caps associated with the metal panel system need to be removed and replaced?

ANSWER: Please refer to the Statement of Work requirements.

4. QUESTION: Please confirm if contracts need to follow UFC 3-110-03, Roofing. Requiring a vapor barrier, gypsum substrate board and a gypsum coverboard to be included in the roofing assembly.

ANSWER: The roof shall be replace per the Statement of Work requirements with a same in kind as the existing roof.

5. QUESTION: What is the period of performance for this project?

ANSWER: 10 working days.