This is a Questions and Answers document clarifying specifications and site conditions for a roofing replacement project on the Chief's Mess Building.
The project encompasses a 3,720 square foot roof replacement including removal of 10 existing 24"x24" skylights, two motorized electric exhaust vents, and solar hot-water roof-mounted components. The contractor must install a ridge vent, replace three existing pipe boots with new flashing, infill skylight openings with plywood, and replace approximately 300 square feet of damaged roof sheathing (anticipated to be ½" material). The roof deck will be covered with 15-pound felt or better underlayment and 30-year shingle type, with shingle color and type to be submitted for government acceptance after award. The performance period is 30 working days after award. Site conditions include sporadic building occupancy, available potable water and electrical power, restroom facilities, and permission for on-site dumpsters. The government will dispose of removed solar panels. Roof pitch information is unknown, and existing roof sheathing material confirmation is uncertain. Any damaged sheathing replacement exceeding the 300 square foot estimate will be treated as additional work per the revised Statement of Work included in amendment 0001.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. QUESTION: Please confirm the controlling performance period: 30 calendar days after award, per SF1442, or 30 working days after award, per the SOW?
ANSWER: 30 working days after award.
2. QUESTION: Please provide the approximate total roof area, roof pitch, and number of existing shingle layers.
ANSWER: Building is 3,720 square feet. The government is unsure of roof pitch. There are areas with single layers and areas with overlap layers.
3. QUESTION: Please provide the approximate dimensions of the 10 existing skylights.
ANSWER: Approximately 24”x24”.
4. QUESTION: Please confirm whether the skylight openings are within an attic space and no interior drywall or finish work is required after removal.
ANSWER: No interior drywall and plywood would need to be put back over the openings.
5. QUESTION: Please confirm whether a ridge vent is present and requires replacement.
ANSWER: No ridge vent, however, there are two motorized exhaust vents that will need to be removed and the ridge vent to be installed per the SOW included with this amendment.
6. QUESTION: Please confirm the existing roof deck/sheathing material and thickness.
ANSWER: This information is not known; however, it is anticipated to be ½”
7. QUESTION: Please provide an estimated quantity or allowance for damaged sheathing replacement beyond the skylight infill areas.
ANSWER: The estimated quantity is 300 sq ft for the purposes of quoting and anything over will be treated as additional work. A revised SOW is included in this amendment that captures this change.
8. QUESTION: Please confirm whether self-adhered ice-and-water membrane is required.
ANSWER: 15lb felt or better is required.
9. QUESTION: Please specify the required shingle type, class/rating and color.
ANSWER: 30-year shingle type and color type is to be submitted to the government for acceptance after award.
10. QUESTION: Please confirm whether all existing pipes that will remain in place require new pipe boots/flashing, and if so, provide the total quantity.
ANSWER: All existing pipes will need replacement boots. It is estimated that the total number is three.
11. QUESTION: Please clarify whether solar hot-water demolition is limited to roof-mounted components with connections capped, or if interior system removal is also required.
ANSWER Only roof mounted components.
12. QUESTION: Please identify which existing roof vents are to be replaced and clarify the type and size of the two 2-foot air vents referenced in the SOW.
ANSWER: The electric 2’ fan vents shall be removed and replaced with a ridge vent per the amendment 0001 SOW.
13. QUESTION: Please confirm whether the Chief’s Mess Building will remain occupied during construction.
ANSWER Building is not occupied all day just sporadically.
14. QUESTION: Will potable water and electrical power be available on site for contractor use?
ANSWER: Yes.
15. QUESTION: Are restroom facilities available to contractor personnel, or will portable toilets be required?
ANSWER: Yes.
16. QUESTION: Please confirm whether dumpsters/roll-off containers are permitted on site.
ANSWER: Yes.
17. QUESTION: Please confirm whether the removed solar panels are to be disposed of by the Contractor or retained by the Government.
ANSWER: The Government will dispose of the solar panels.