SOW Appendix A - OEM Maintenance Requirements_Rev_22OCT2024.pdf
PDF 104 KB Posted
- Attached to
- PSC GENSET Storage & Maintenance
- Solicitation number
- 70Z02325RSALC0001
About this file
This document is an appendix to a Request for Proposal (RFP) for generator and engine maintenance services. The RFP is numbered 70Z02325RSALC0001 and is being issued by the Department of Homeland Security US Coast Guard.
The appendix outlines the maintenance requirements for an ABB generator and Caterpillar engines. For the generator, the requirements include tasks to be performed upon arrival, annually, and every 12 months. For the engines, the requirements include annual cleaning, inspection, and corrosion mitigation tasks, as well as more comprehensive preservation and inspection tasks to be performed every 24 months. The RFP indicates that Caterpillar will complete the required engine maintenance tasks under an existing contract with the agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 70Z02325RSALC0001 SOW Appendix A
PSC GENSET OEM Maintenance Requirements
Revised – 22 October 2024
ABB GENERATOR MAINTENANCE
UPON ARRIVAL
1. Turn the assembly 10 revolutions.
2. Check and record all (Stator and rotor) insulation resistance.
3. Test, Check, and Record anti-condensation electrical measurements.
4. Measure and check air gap.
5. Verify the operation of the space heaters.
12 MONTHS (YEARLY, due in NOV)
1. Conduct visual inspection of generator overall condition, mounting, foundations, and any external connections.
2. Visually check, test, and record electrical measurements of the anti-condensation heaters.
3. Visually check and record condition of rotor and stator.
4. Test, check, and record insulation resistance and polarization index measurement of the stator and rotor windings.
5. Visually inspect all interior windings.
6. Measure and record air gaps.
7. Turn the assembly 10 revolutions.
8. Verify the operation of the space heaters.
RFP 70Z02325RSALC0001 SOW Appendix A
CATERPILLAR (FATHER AND SON) ENGINE MAINTENANCE
UPON ARRIVAL (Caterpillar will complete required tasks under existing contract with BMS)
12 MONTHS (YEARLY, due in November)
1. Clean interior of surfaces in visual observation of engine.
2. Inspect condition of VCI Packaging Coating (Touch-up as required).
3. Conduct full engine corrosion inspect. Correct as required.
24 MONTHS (due every other November)
1. Conduct full engine VCI Packaging Preservation.
2. Clean and inspect all interior engine components. Renew AVI Lubrication on interior of engine.
3. Conduct full engine corrosion inspect. Correct as required.
4. Conduct borescope inspection of Cooling Water Systems (Fresh and Salt Water) and the
Exhaust Systems.