SOW Appendix A - OEM Maintenance Requirements.pdf

PDF 103 KB Posted

Attached to
PSC GENSET Storage & Maintenance
Solicitation number
70Z02325RSALC0001
Issued by

About this file

This document is a Statement of Work (SOW) Appendix A that outlines the Original Equipment Manufacturer (OEM) maintenance requirements for a Solicitation (RFP 70Z02325RSALC0001) for PSC GENSET storage and maintenance services.

The SOW Appendix A details the OEM maintenance requirements for an ABB generator and Caterpillar engines. For the ABB generator, the requirements include turning the assembly, checking insulation resistance, testing anti-condensation electrical measurements, and measuring/checking the air gap - both upon arrival and annually. For the Caterpillar engines, the requirements include cleaning, inspecting, and conducting monthly, yearly, and 24-month maintenance activities.

The associated federal contract opportunity is a combined synopsis/solicitation (Solicitation Number: 70Z02325RSALC0001) issued by the Department of Homeland Security US Coast Guard for PSC GENSET storage and maintenance services. The Government intends to award a sole source contract to Crow Point Energy using the authority at FAR 6.302-1.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 70Z02325RSALC0001 SOW Appendix A

PSC GENSET OEM Maintenance Requirements

ABB GENERATOR MAINTENANCE

UPON ARRIVAL

1. Turn the assembly 10 revolutions.

2. Check and record all (Stator and rotor) insulation resistance.

3. Test, Check, and Record anti-condensation electrical measurements.

4. Measure and check air gap.

12 MONTHS (YEARLY, due in NOV)

1. Conduct visual inspection of generator overall condition, mounting, foundations, and any external connections.

2. Visually check, test, and record electrical measurements of the anti-condensation heaters.

3. Visually check and record condition of rotor and stator.

4. Test, check, and record insulation resistance and polarization index measurement of the stator and rotor windings.

5. Visually inspect all interior windings.

6. Measure and record air gaps.

7. Turn the assembly 10 revolutions.

RFP 70Z02325RSALC0001 SOW Appendix A

CATERPILLAR (FATHER AND SON) ENGINE MAINTENANCE

UPON ARRIVAL

1. Clean interior of surfaces in visual observation of engine.

2. Inspect condition of VCI Packaging Coating (Touch-up as required).

3. Conduct Monthly Inspections.

12 MONTHS (YEARLY, due in November)

1. Clean interior of surfaces in visual observation of engine.

2. Inspect condition of VCI Packaging Coating (Touch-up as required).

3. Conduct Monthly Inspections.

24 MONTHS (due every other November)

1. Conduct full engine VCI Packaging Preservation.

2. Clean and inspect all interior engine components. Renew AVI Lubrication on interior of engine.

3. Conduct full engine corrosion inspect. Correct as required.

4. Conduct borescope inspection of Cooling Water Systems (Fresh and Salt Water) and the

Exhaust Systems.