This document is a Statement of Work (SOW) for a federal contract opportunity to install a new standalone Network Video Management System (NVMS), IP cameras, client workstations, control room monitors, and related equipment for a video surveillance system (VSS) upgrade at the Robert E. Coyle Federal Courthouse in Fresno, CA.
The key details are: The contractor shall purchase and install a new NVMS, IP cameras, servers, storage, networking equipment, and related components to provide a fully functional IP-based VSS. The system shall monitor vehicle traffic, personnel entry, emergency exits, and the exterior perimeter. The contractor shall remove the existing analog system and ensure the new system is installed and operational within 60 business days after receiving the notice to proceed. The contract will be awarded as a firm-fixed price contract via a small business set-aside solicitation. The government will perform a performance verification test and final inspection prior to acceptance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REVISION 2 Instructions to Offerors via AM3.docx | DOCX document | |
| REVISION 2 Attachment E - Contractor Quotation Checklist via AM3.docx | DOCX document | |
| 70RFPW24QW9000003 - AM3.pdf | ||
| REVISED Instructions to Offerors via AM2.docx | DOCX document | |
| 70RFPW24QW9000003 - AM2.pdf | ||
| REVISED Attachment E - Contractor Quotation Checklist via AM2.docx | DOCX document | |
| 70RFPW24QW9000003 - AM1.pdf | ||
| REVISED Attachment A1 via AM1 on 240422.pdf | ||
| V2 - Synopsis.docx | DOCX document | |
| 70RFPW24QW9000003 - Solicitation.pdf | ||
| C - Past Performance Form.pdf | ||
| E - Contractor Quotation Checklist.docx | DOCX document | |
| D - Past Performance Questionnaire.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Protective Service U.S. Department of Homeland Security
STATEMENT OF WORK
REVISED VIA AMENDMENT 0002
for
Upgrade of Video Surveillance System (VSS)
VSS Upgrade Project
Robert E. Coyle Federal Courthouse 2500 Tulare Street Fresno, CA 93721 Building Number: CA0309
STATEMENT OF WORK
TABLE OF CONTENTS
| A. | BACKGROUND | 1 |
| B. | PURPOSE | 1 |
| C. | SCOPE | 6 |
| C.1 | General | 6 |
| C.2 | Installation Requirements | 8 |
| C.3 | Video Storage Requirements | 10 |
| C.4 | Control Room Monitors | 11 |
| C.5 | Networking Equipment | 11 |
| C.6 | Operating Systems Updates, Service Packs, and Firmware | 12 |
| C.7 | Wireless Point-to-Point: | 13 |
| D. | SYSTEM/EQUIPMENT SALIENT CHARACTERISTICS AND REQUIREMENTS | 14 |
| D.1 | Network Video Management System | 14 |
| D.2 | Minimum Server and Workstation Requirements | 17 |
| D.3 | IP Network Video Camera Minimum Requirements | 18 |
| D.4 | Network Managed Switch | 20 |
| D.5 | Additional System Component, software, location etc. specifications | 20 |
| D.5.1 | At a minimum, the Monitor Mount for Desk Console shall have the following characteristics: | 20 |
| E. | ADDITIONAL PROJECT REQUIREMENTS | 21 |
| E.1 | Design Standards | 21 |
| E.2 | Materials and Equipment | 22 |
| E.3 | Electrical and Cabling Requirements | 22 |
| E.4 | Final Inspection and Acceptance | 24 |
| E.5 | Cleanliness, Protection, and Patching | 25 |
| E.6 | Warranty and Maintenance | 26 |
| E.7 | Safety and Health | 27 |
| E.8 | Quality Control Plan | 27 |
| E.9 | Training | 28 |
| E.10 | Configuration Management | 29 |
| E.11 | Component/Device Configurations | 29 |
| E.12 | Network Settings | 29 |
| E.13 | Wireless Network Security | 30 |
| E.14 | Audit and Accountability | 31 |
| E.15 | Identification and Authentication / Access Control | 31 |
| E.16 | Data Protection | 32 |
| E.17 | User Accounts | 32 |
| E.18 | Incident Management and Disaster Recovery | 33 |
| E.19 | Software Maintenance | 33 |
| E.20 | Enterprise Architecture | 33 |
| F. | DELIVERABLES | 34 |
| F.1 | General | 34 |
| F.2 | Request for Quotation (RFQ) | 35 |
| F.3 | Pre-Installation Deliverables | 35 |
| F.4 | Post-Installation Deliverables | 36 |
| G. | PROJECT ADMINISTRATION | 37 |
| G.1 | Work Authorization | 37 |
| G.2 | Period of Performance | 37 |
| G.4 | Contacts | 38 |
| G.5 | Special Scheduling Requirements | 38 |
| G.6 | Contractor Access and Use of Premises | 38 |
| G.7 | Security Requirements | 39 |
| G.8 | Contractor Suitability Requirements | 40 |
| H. | APPLICABLE STANDARDS | 42 |
| H.1 | General | 42 |
| H.2 | Accessibility Requirements (Section 508) | 43 |
| I | Accountable Property: | 43 |
| I.1 | Definitions: | 43 |
| I.2 | Deliverables: | 44 |
| I.3 | Invoices: | 44 |
| I.4 | Property Accountability: | 45 |
| I.5 | Physical inventory: | 45 |
| I.6 | Property Disposal: | 45 |
| I.7 | Lost, Stolen, Damaged or Destroyed (LDD) property: | 46 |
| J. | INFORMATION TECHNOLOGY SECURITY | 46 |
| J.1 | Security Certification/Accreditation | 47 |
| J.2 | Security Review and Reporting | 47 |
| J.3 | Continuous Monitoring | 47 |
FOR OFFICIAL USE ONLY (FOUO)
For Official Use Only (FOUO)
For Official Use Only (FOUO)
1. BACKGROUND
A.1 The Federal Protective Service (FPS) is the federal law enforcement agency responsible for the protection and security of federal facilities, employees, and visitors. FPS actively works to reduce security vulnerabilities of federal facilities from criminal, terrorist, accidental, and natural disaster threats to ensure properties remain safe, secure, and available to the American public and employees of the federal Government.
A.2 The following Statement of Work (SOW) and guidelines have been developed by the Department of Homeland Security (DHS), Federal Protective Service (FPS) to mitigate threats and vulnerabilities pertaining to federal buildings and Government leased spaces. The SOW and regulations were developed with the notion that the security posture of each federally owned building or Government leased space is unique.
PURPOSE
B.1 Description of Existing System
| Brand |
| Make |
| Model |
| Quantity |
| Location |
| Cable Specification |
| DVR |
| Bosch |
| Bosch |
| DVR-650-16A-1TB |
| 1 |
| FPS Security Room #1221 |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra IV |
| S5230-EG1 |
| 1 |
| North Tulare Street |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
P Street near Loading Dock
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
| Loading Dock West |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra IV |
| S5230-EG1 |
| 1 |
South Parking
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
| North Tulare Street |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
| Loading Dock |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
| South Side |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra III |
| S5230-EG1 |
| 1 |
| Main Entry SW Corner |
COAX
| Analog PTZ Camera |
| Pelco PTZ |
| Spectra IV |
| S5230-EG1 |
| 1 |
| Outside Main Entry |
COAX
| Analog Fixed Camera |
| Pelco |
| EH2515 |
| C20-DW6 |
| 1 |
| Loading Dock |
| COAX |
| Analog Fixed Camera |
| Pelco |
| EH2515 |
| C20-DW6 |
| 1 |
| Loading Dock |
| COAX |
| Analog Fixed Camera |
| Pelco |
| EH2515 |
| SSC-113A |
| 1 |
| Inside West Stairwell |
COAX
| Analog Fixed Camera |
| Pelco |
| EH2515 |
| C20-DW6 |
| 1 |
| Outside West Stairwell |
COAX
| Monitor |
| Pelco |
| Pelco |
| PMCL317BL |
| 1 |
| FPS Security Room #1221 |
COAX
| Monitor |
| Pelco |
| Pelco |
| PMCL417A |
| 1 |
| USMS Control Room |
| COAX |
| Keyboard |
| Pelco |
| Pelco |
| KBD300A |
| 1 |
| FPS Security Room #1221 |
| COAX |
| Switcher |
| Pelco |
| Pelco Switcher |
| CM6700 |
| 1 |
| FPS Security Room #1221 |
| COAX |
| Distribution Amp |
| Pelco Distribution Amp |
| Pelco |
| CM9760-MDA |
| 1 |
| FPS Security Room #1221 |
| COAX |
| Power Supply |
| Pelco |
| Pelco Power Supply |
| MCS16-20 |
| 1 |
| FPS Security Room #1221 |
| COAX |
B.2 Description of New System
B.2.1 This SOW is for the purchase and installation of a new standalone, Network Video Management System (NVMS), fixed/panoramic/PTZ IP cameras, client workstations, control center flat panel monitors, and all additional equipment and appurtenances necessary for a fully functional IP VSS located at the Robert E. Coyle Federal Courthouse 2500 Tulare Street Fresno, CA 93721. Also, this SOW shall include the purchase, installation, and programming of all contractors supplied equipment and or components.
B.2.2. The VSS shall monitor vehicle traffic, personnel entry, emergency exits, and the exterior perimeter of the facility. The VSS shall retain video for a minimum of 30 days plus 25% additional storage space for future expansion. Storage shall be calculated at full camera resolution, maximum frame rate at the device (Camera, not total system), and low compression.
C. SCOPE
C.1 General
C.1.1 As part of the pre-bid process, FPS may have a site visit and all interested Contractors are invited to attend. The purpose of the site visit is for Contractors to survey the site and review the requirements of this SOW. A site visit will be scheduled by the COR/FPS PM. All questions relevant to this SOW shall be submitted in writing to the FPS COR/TPOC. The Contractor shall not make or assume any changes to this SOW without written approval from the FPS COR/TPOC.
C.1.2 The Contractor shall be responsible for the removal, inventory, packaging for storage and return of all removed equipment to the FPS COR/TPOC. All currently installed wire, cable, and fiber shall be completely removed and replaced with the appropriate new type of wire, cable or fiber by the Contractor and properly disposed of.
C.1.3 The existing system shall remain fully functional and operational to the extent possible during the installation of the new surveillance system. The contractor shall cut over from the existing system to the new system in stages in order to minimize the number and duration of outages. The Contractor shall submit a system cutover plan in accordance with Section F Deliverables. The cutover plan shall be reviewed and approved in writing by the FPS COR/TPOC.
C.1.4 The Contractor shall provide and install and configure the system as described and/or shown herein. The system shall include all connectors, adapters, terminators, and appurtenances to interconnect all equipment. The Contractor shall also supply all cabling and miscellaneous materials necessary to interconnect all equipment installed in accordance with this SOW.
C.1.5 The Contractor shall be required to be familiar with all applicable codes while carrying out the work outlined in this SOW. The Contractor shall complete the work pursuant to this SOW following all applicable codes and standards including, but not limited to: Occupational Safety and Health Administration (OSHA), Underwriters Laboratories (UL), National Fire Protection Association (NFPA), National Electrical Code (NEC), and any additional federal, state and local codes and policies.
C.1.6 The Contractor shall furnish all tools and equipment necessary to complete all work outlined in this SOW. By no means shall the Contractor be authorized the use of Government owned property, tools or equipment, to complete work in accordance with this SOW, unless otherwise specified.
C.1.7 In the event any operational system or utility (e.g. fire, IDS, HVAC) is required to be disabled or turned off, forty-eight (48) hour notice shall be required and approved by the GSA Building Manager, FPS Inspector, and/or FPS COR/TPOC prior to deactivation.
a) The Contractor, prior to departing for the day, shall ensure all system(s) previously disabled or turned off are functioning properly. A basic functional test shall be required to determine proper functionality of the system(s) and should be reported to the FPS COR/TPOC.
b) In the event a system is non-functional once enabled or turned on, it shall be the responsibility of the Contractor, at no additional cost to the Government, to restore the system(s) prior to departure from the site.
c) If the Contractor fails to restore all system(s) before departing, they shall be liable for all costs incurred by the Government to restore system(s) functionality.
C.1.8 All personnel engaged in installation activities pursuant to this SOW shall be licensed by the state, local authority, and/or the city local authority in the required trades or professions which require licensing by such jurisdictions. The type and level of license shall be consistent with requirements of the jurisdictions and work to be performed by this SOW.
C.1.9 It shall be the sole responsibility of the contractor to employ personnel licensed and qualified to carry out all tasks outlined in this SOW. At no time during the installation shall the contractor require Government personnel to complete tasks required to be completed by the contractor as covered by this SOW.
C.1.10 The Contractor shall be solely responsible for ensuring their employees and subcontractors abide by all requirements of the contract. At all times while work is being performed in accordance with this contract, the Contractor shall have a supervisory representative available to answer questions, resolve issues, supervise company employee(s), and subcontractor(s).
C.1.11 The Contractor shall provide a daily access schedule to coordinate installation activities. The schedule shall be submitted as part of the project plan.
C.1.12 The Contractor shall maintain a separate set of drawings, schematics, and wiring diagrams of the VSS to be used for creating as-built drawings. This set shall be accurately kept up to date by the Contractor, noting all changes and additions to the VSS and shall be available for the final inspection walkthrough.
C.1.13 The Contractor may be required to attend installation construction meetings.
C.1.14 For buildings 45 years of age or older: All repairs, installations and removals are required to follow the Secretary of the Interior’s Standards for Rehabilitation (SOI): https://www.nps.gov/crps/tps/rehab-guidelines/stand.htm.
C.1.15 The Contractor must be ISO 9001-2015 Certified and provide their ISO certification with their proposal documentation.
C.1.16 The Contractor shall install all new
C.2 Installation Requirements
C.2.1 The Contractor shall install all system components and appurtenances in accordance with manufacturer’s instructions following all applicable local, state and federal codes and policies. All appurtenances, such as, but not limited to connectors, terminators, and mounting hardware shall be supplied by the Contractor, as well as, all adjustments, alignments, programming, and configuration required for a complete and optimal VSS operating system.
C.2.2 The Contractor shall provide and install a complete statically assigned IP based VSS to include, but not limited to, Network Video Management System (NVMS) capable of viewing, recording, playback, and exporting of video, cameras, servers, RAID 6 video storage, workstations, and network routers/switches. Provide and install camera mounts and other appurtenances, premise wiring, and system hardware as required for a complete and fully operational system as specified in this SOW. The installed system shall easily be expandable for future growth.
C.2.3 The Contractor, for all equipment/device(s) requiring licensing, shall purchase/install license(s) as required by the manufacturer. All licensing fees shall be nonrecurring. Documentation of all software and hardware licenses shall be provided to FPS as part of the final system documentation.
C.2.4 All equipment required to be wall-mounted shall be mounted.
C.2.5 The Contractor shall be responsible to provide the necessary equipment and tools to access all equipment which is not accessible by ladder. The contractor is accountable for all tool and equipment used during the course of installation; potentially dangerous items must remain under the physical control of the installer at all times. All tools and equipment to include electronic equipment and computers are subject to inspection by FPS.
C.2.6 All measurements and equipment locations are approximate and shall be verified by the Contractor for accuracy and installation feasibility. The Government shall not be held responsible for any error or variation in any measurements or other data listed, nor shall the Contractor, because of an error or variation in any measurement listed, be relieved of the responsibility to carry out the requirements in accordance with the true intent and meaning of the specifications without additional cost to the Government.
C.2.7 All ceiling tiles removed to accommodate installation shall be returned at the end of the workday.
C.2.8 The Contractor shall remove and haul debris from the project site daily and dispose of in a proper, acceptable manner in accordance with all federal, state and local laws and regulations, off of the job site property. The debris created from this project shall not be disposed of at the job site, in Government dumpsters, or on Government property.
C.2.9 The Contractor shall install and configure cameras in accordance with manufactures recommendations and industry best practices for optimal live view and recording.
C.2.10 The Contractor shall verify all camera views with the FPS COR/TPOC prior to installation.
C.2.11 The Contractor, when removing the existing cameras, cabling, and appurtenances in accordance with this SOW, shall ensure all openings or penetrations are sealed and/or patched accordingly to protect against weather exposure, unless otherwise designated for reuse. All openings or penetrations that are designated for reuse shall be sealed and/or patched accordingly to protect against weather exposure at the completion of installation. All penetrations that become exposed to weather during installation shall be protected from exposure throughout the installation period.
C.2.12 Installers shall be trained, certified, and authorized by the Manufacturer to install, integrate, test, and commission the system. The contractor shall provide and submit with their proposal documentation from the manufacture that they are trained, certified, and authorized to install, integrate, test, and commission the system. If documentation is not available, the contractor can substitute by providing with their proposal confirmation on manufacturer letterhead, they are trained, certified, and authorized to install, integrate, test, and commission the system within two years of the submittal date.
C.2.13 At least one factory certified trained technician on the VMS being installed by the contractor must be onsite at all times during the installation. Factory certification must be within the last two years (date of proposal).
C.3 Video Storage Requirements
C.3.1 The Contractor shall calculate appropriate storage for all cameras recording at the maximum frame rate at the device (Camera, not total system), maximum resolution, and minimum compression. Storage capacity shall be capable of storing video for a minimum of thirty (30) days. The Contractor shall calculate and provide video storage requirements with the Quotation. The Contractor shall include enough storage for an additional 25% storage for future expansion maintaining the thirty (30) day minimum requirement. In addition to 6 additional camera licenses. The contractor will not have access to video data and will not be responsible for the collection, use, maintenance or storage of video data.
C.3.2 The Contractor shall configure the installed VSS to function in a Network Domain environment, not as a workgroup.
C.3.3 Microsoft Windows and the NVMS software shall be configured to use MS Active Directory for authentication. If the NVMS software is not capable of authenticating to the Active Directory, then separate NVMS accounts will be configured in accordance with account management plan.
C.3.4 The Contractor shall not apply power to the NVMS until, at a minimum; the following checks have been completed.
a) All equipment has been installed and connected in accordance with manufacturer’s instructions.
b) All installed and/or reused wiring has been tested accordingly (e.g. shorts, opens, continuity).
c) Power supplies have been verified to operate at the correct voltage, phase, and frequency. Satisfaction of the above requirements shall not relieve the Contractor of responsibility for incorrect installation, defective equipment, or collateral damage as a result of Contractor work/equipment.
C.3.5 The Contractor shall ensure all system devices are configured appropriately for time synchronization. The local time zone where the system physically resides will be utilized. All devices shall be configured for time synchronization with a GPS enabled network time source. The GPS time source will not have any connectivity capability beyond receive functionality.
C.3.6 The Contractor shall demonstrate to the FPS COR/TPOC that the completed NVMS installation complies with the contract requirements. Using an approved test procedure, all physical and functional requirements of the project shall be demonstrated and shown. The test procedure shall include techniques and requirements for validating all significant system functions. The Contractor shall provide all test equipment and personnel required for final testing.
C.4 Control Room Monitors
| C.4.1 | The new monitors to be provided and installed are one (1) fifty-inch (50”) monitor and two (2) twenty-four-inch (24”) monitors shall be installed in the FPS Security Room #1221. One (1) forty-three-inch (43”) monitor in the US Marshal Service (USMS) Court Security Officer (CSO) control room. The one (1) 50” monitor shall be wall mounted. The two (2) 24” monitors shall be a vesa desk mounted and shall be located in the FPS Security room # 1221. The one (1) 43” monitor located in the USMS CSO control room shall be wall mounted. |
| C.4.2 | At a minimum, the 50” Monitor shall possess the following salient characteristics. |
a) Color
b) 3840 x 2160 resolution, 16- or 32-bit pixel color resolution
c) Flat Panel
d) Wall and desk top Mountable.
e) Must meet applicable and appropriate Electronic Product Environmental Assessment Tool (EPEAT) and ENERGY Star standards.
C.4.3 At a minimum, the 43” Monitors shall possess the following salient characteristics.
a) Color
b) 3840 x 2160 resolution, 16- or 32-bit pixel color resolution
c) Flat Panel
d) Wall mountable.
e) Must meet applicable and appropriate Electronic Product Environmental Assessment Tool (EPEAT) and ENERGY Star standards.
C.4.4 At a minimum, the 24” Monitors shall possess the following salient characteristics.
a) Color
b) 3840 x 2160 resolution, 16- or 32-bit pixel color resolution
c) Flat Panel
d) Mountable to articulating desk mount to hold two (2) 24” monitors.
e) Must meet applicable and appropriate Electronic Product Environmental Assessment Tool (EPEAT) and ENERGY Star standards.
C.5 Networking Equipment
C.5.1 As required per this SOW, the contractor shall purchase, install, and configure all equipment, components, and necessary appurtenances for a complete and appropriately configured Ethernet network connecting all devices of the NVMS.
C.5.2 The Contractor shall configure installed switches for Trunk line communication between the switches. Line encryption shall be enabled between all network devices to the maximum extent possible. If copper network cabling is utilized between network devices, it must be metallically shielded twisted pair.
C.5.3 The Contractor shall configure installed switches with Virtual Local Area Network (VLAN) and appropriate VLAN Routing. VLAN’s to be configured are:
COYLE VLAN
Identify naming scheme of the network/VLAN when appropriate. Should be something unique for the facility, not called “security camera network” or something security related.
C.5.4 All equipment shall be rack mountable, if possible. All equipment that is not rack mountable shall be installed on the wall. An appropriately sized piece of ¾” plywood shall be mounted on the wall, painted with fire retardant paint, and all equipment mounted on the plywood. Final mounting location shall be approved by the FPS PM.
C.5.5 The Contractor shall provide and install a rack mounted 19” combination display, keyboard, and mouse (KVM) at a usable height, in FPS Security Room #1221 connected to the new NVMS Server for system configuration and administration.
C.5.6 The Contractor shall install new VSS client workstations in FPS Security Room #1221 and USMS Control Room. Location of workstation shall be coordinated with the FPS COR/TPOC before installation.
C.5.7 The Contractor shall enable software based, packet filtering firewalls on the VSS network. Firewalls will be enabled to permit only authorized network devices and protocols. A list of ports and protocols shall be provided as part of the system documentation for each unique device model and software suite. The VSS shall be functionality tested to ensure enabled firewall rules and port restrictions do not interfere with the overall functionality of the systems.
C.5.8 The Contractor shall ensure that all installed network devices that are Wi-Fi-capable have that capability disabled.
C.6 Operating Systems Updates, Service Packs, and Firmware
C.6.1 Operating systems and software applications shall be capable of being updated/patched after delivery. The Contractor shall ensure that all installed server(s) and client workstation(s) Operating System Software (OS), at the time of installation, are current with all security updates/patches, service packs, revisions, and shall provide through the warranty period. The NVMS and all other installed software shall be the current version with all applicable updates and installed in accordance with manufacturers recommendations.
C.6.2 The Contractor shall remove and/or disable all software components (bloatware) that are not required for the operation and maintenance of the camera system; and shall provide documentation on what is removed and/or disabled. The software to be removed and/or disabled shall include, but is not limited to: games, device drivers for network devices not delivered, messaging services (e.g., MSN, AOL IM), Servers or clients for unused Internet services, unused networking and communications protocols, unused document processing utilities (Microsoft Word, Excel, PowerPoint, Adobe Acrobat, OpenOffice, etc.).
C.6.3 The Contractor shall provide notification of patches affecting security within a pre-negotiated period (usually the warranty period) as identified in the patch management process.
a) Pre-Contract Award – The Contractor shall provide details on their patch management and update process. Responsibility for installation and update of patches shall be identified.
b) Post-Contract Award - The Contractor shall provide notification of known vulnerabilities affecting Contractor-supplied or required OS, application, and third-party software within 30 days after public disclosure.
C.6.4 The Contractor shall ensure that all VSS components have the latest manufacture approved firmware version installed. Firmware version is to be documented on the device inventory.
C.7 Wireless Point-to-Point:
C.7.1 Not Required
C.8 Attachments
C.8.1 VSS Locations: See floor plans (Attachment C. The contractor and FPS shall verify all camera installation locations to provide the optimal view prior to any installation.
D. SYSTEM/EQUIPMENT SALIENT CHARACTERISTICS AND REQUIREMENTS
D.1 Network Video Management System
D.1.1 The NVMS shall support these essential software capabilities:
a) Live video monitoring
b) Recording of video
c) Playback of video from local or remote location(s)
d) Integral alarm/event management
e) Video export
D.1.2 The NVMS shall store/archive video using one of the following techniques:
a) Internal Disk Storage
b) Direct Attached Storage
c) Storage Area Network
D.1.3 The NVMS shall include image storage with configurable resolutions and frame rates.
D.1.4 The NVMS shall be compatible with, but not limited to: H.264, H265, MPEG4, and MJPEG video compression formats.
D.1.5 The NVMS shall be capable of system fail-over and redundancy options.
D.1.6 NVMS System Architecture
a) HDMS SmartCodec Technology Support Automatically adjusts compression levels for regions in a scene, to optimize bandwidth while still maintaining image quality.
b) Appearance Search Technology Quickly search recorded video to find instances of a person or vehicle across all sites using cameras with Avigilon self-learning analytics. Search for a person by physical description, including clothing color, hair color, gender, and age group. Search for a vehicle by physical description, including color and category - car, truck, bus, bicycle, and motorcycle.
c) Facial Recognition Technology AI-powered facial recognition algorithms notify operators when a person of interest returns to a facility. Add a person to a face watch list by uploading a photo or from recorded video. Create watch list alarms or monitor the Focus of Attention interface to detect matches.
d) Intelligent Search Powerful search tools enable you to quickly search recorded video for motion, the presence of classified objects (people or vehicles), background changes in the scene (thumbnail search), and for events.
e) Video Archive Retain and manage large amounts of video for on-demand retrieval and review. Extend your storage beyond NVRs using the Avigilon Video Archive for reliable and scalable storage.
f) Detailed Management, Monitoring, and Reporting of System Status and Security Detailed logs of storage, network, and overall system status to help ensure the highest possible system uptime for critical applications.
g) Unusual Activity Detection (UAD) technology enables object-level detection of atypical activity. This edge-based intelligence uses advanced AI technology and is designed to be object-aware, enabling operators to know when a person or vehicle is in an unusual location in the scene or moving at an unusual speed.
h) Unusual Motion Detection (UMD) technology enables fast video search and is designed to reduce hours of work to minutes by narrowing potentially thousands of motion events to a handful. This allows operators to focus their attention on recorded video needing further investigation.
i) Federal Government Compliance with FIPS 140-2 Certified Encryption To comply with policies, Federal Government and other customers can enable FIPS 140-2 certified cryptography on VSM software and on supported cameras. Required camera cryptography licenses are centrally managed in VMS. Within VMS, optionally turn on licensed FIPS cryptography on cameras. VMS inventories the number of FIPS camera licenses being used and determines whether customers have the required number of licenses within a facility.
j) The NVMS shall operate on a TCP/IP managed digital network.
k) The system software shall operate in a Client/Server configuration across a Local Area Network (LAN) or Wide Area Network (WAN).
l) Streams live and recorded video up to 60 frames per second.
m) Support prioritizing streaming at 30 frames per second on 4K (8MP) cameras.
n) Streams live and recorded video from cameras up to a resolution of 7K (30 MP) — 6720 x 4488.
o) Decompresses H.264 and/or H.265 video through the client graphics card to help leverage the client’s total processing power.
p) Scalable to support up to 100 servers and/or 10,000 cameras per site.
q) All recorded video and audio are digitally signed using 256-bit encryption so video can be authenticated for evidentiary purposes.
r) Secure video and audio data by securely transmitting all command-and-control data via TCP/IP using cryptographic keys based on SSL to prevent eavesdropping or tampering.
s) External system alarms can be pre-selected and configured to be monitored and trigger event driven video operations.
t) Video and audio recording can be defined by a recording schedule assigned to each video source.
u) Recording schedules are based on event types that trigger video recording over a time period each day per week.
v) Video recording can also occur manually by user triggered recording.
w) Alarms and rules can be triggered by self-learning video analytics-based events.
x) Each recorded event includes a pre-event and post-event recording option to provide context for a given situation.
y) Reference frame recording is an option when no events are detected.
z) Motion detection is provided for each individual video source with adjustable sensitivity, threshold, and detection zones.
aa) Primary and secondary video streams from each H.264 and/or H.265 video source is recorded and maintained for a set amount of time before the primary stream is discarded as a means of increasing record time.
ab) The maximum recorded video retention time can be set for each video source.
ac) The Video Analytics Activity overlay displays a color-coded bounding box around moving objects categorized as humans or vehicles.
ad) Configure the ability to display analytics activity for individual cameras or for the system.
ae) The ability to stream video and audio is limited only by the system hardware capabilities.
af) The application window display can be shared with other users for collaborative investigations while viewing both live and recorded video.
ag) Live and recorded video and audio can be streamed simultaneously on the same monitor.
ah) Use High-Definition Stream Management (HDSM) software technology to efficiently compress and preserve image quality while intelligently managing HD image transmission throughout the system.
ai) Operating System shall be certified to work by the Video Management Software’s manufacturer and be one of the following: Windows Server 2010 or newer.
aj) Windows 10 or newer.
ak) Support recording and management of video and audio sources using industry standard drivers. These drivers shall include: ONVIF Profile S, T and G Publicly Published API.
al) Support the following video analytic event types when captured by supported cameras: Objects in area, object loitering’ objects crossing defined line, object appears or enters area, object not present in area, objects enter area, objects leave area, object stops in area, anticipated direction of travel is violated, scene dramatically changes in an unexpected fashion.
am) Support the ability to export media and provide the following options.
an) Export recorded video in the following formats: Native (AVE), JPEG, PNG, TIFF, AVI, Print. Export recorded audio in the following formats: WAV, Native (AVE), AVI. Export a still frame of video as displayed in the video preview area: Native (AVE), JPEG, PNG, TIFF.
ao) Native (AVE) format exports shall:
ap) Digitally sign recorded video and audio using 256-bit encryption so video can be authenticated for evidentiary purposes.
aq) Be able to export video from one or multiple camera streams simultaneously.
ar) Support exporting multiple video segments from different spans of time.
as) Support reviewing of exported or backed-up video and audio in a dedicated player.
at) Support playback of exported clips in synchronized sequential time.
au) Support playback of multiple clips in continuous, sequential order.
av) Support exporting of video in lower frame-rates than originally recorded.
aw) Support exporting of a designated area from the camera’s recorded field of view.
ax) Support re-export into Native or other supported formats.
ay) Provide a record of the video source properties, including but not limited to: Camera model, Firmware version, Location, MAC address, Serial number, Resolution.
D.1.7 All components/equipment licensing fees for the newly installed NVMS shall be nonrecurring.
D.2 Minimum Server and Workstation Requirements
Network Video Management Server Minimum Requirements
| CPU |
| Intel Core i7 or newer |
| OS |
| Windows Server or newer 64bit |
| RAM |
| 16 GB |
| OS Hard Drive |
| SSD RAID Mirrored |
| Network Interface |
| 1GB |
| Display Adaptor |
| DVI, HMDI |
| Storage Configuration |
| RAID 6 |
| Power Supply |
| Dual redundant hot swappable |
| Drives |
| Hot Swappable |
| Warranty |
| 5-year Warranty |
Multimedia Storage Requirements
| General |
| · Multimedia storage shall be dedicated for archiving |
· Archiving shall be physically separated from OS/DB drives
· OS/DB and Archive drive may be housed in the same chassis
· Archive drives RAID 6 configuration
| Total Storage Capacity |
| Shall be calculated by the Contractor based on the requirements of the SOW. All calculations shall be provided with quotation. |
Workstation Minimum Requirements
| CPU |
| Intel Core i7 or newer |
| OS |
| Windows 10 Pro or newer 64 bit |
| RAM |
| 16 GB DDR3 |
| OS Hard Drive |
| SSD RAID Mirrored |
| Network Interface |
| 1GB |
| Display Adaptor |
| VGA, DVI, HDMI dual monitor support |
D.3 IP Network Video Camera Minimum Requirements
D.3.1 At a minimum, equal or better than Avigilon Exterior PTZ 8MP IP Camera: The FPS Local POC shall determine the field-of-view (FoV) for each camera with the Contractor, at the time of installation.
a) ONVIF Compliant Profile S, Profile T and Profile G
b) Operate in a temperature range of -40 deg C to +60 deg C (-40 deg F to +140 deg F)
c) Operate in a humidity range of 0-95% RH (non-condensing)
d) High Definition Stream Management
e) Multi-stream H.264, Multi-stream H.265, Motion JPEG.
f) Video Resolution: 8 MP
g) IPv4/IPv6, HTTP, HTTPS, SOAP,DNS,NTP, RTSP, RTCP, RTP, TCP,UDP, IGMP, ICMP, DHCP, Zeroconf, ARP,HSTS
h) Environmental rating IP66 and IP67
i) Impact rating IK10
j) Video Pattern Detection and Teach by Example Technology
k) Password protection, HTTPS encryption, digest authentication, WS authentication, user access log, 802.1x port based authentication, FIPS 140-2 L1 (with optional camera license), FIPS 140-2 L3 (with optional accessory)
l) 5-year warranty
D.3.2 At a minimum, equal or better than Avigilon 180/270/360-degree Exterior/Interior IP Panoramic Camera: verify the panoramic camera is compatible with the video management system software to ensure full functionality of the camera.
a) 180/270/360 degree panoramic
b) Wide Dynamic Range Panoramic
c) 3 or 4 sensors (cameras) within the housing
d) Lens: 2.8mm f1.2-103° , 4mm f1.6-72°, Remote Focus; 4mm f1.8-101°, 5.2mm f1.8-70° Remote Focus
e) Image Compression: H.264 HDSM Smartcodec or H.265 HDSM SmartCodec or Motion JPEG
f) Outdoor Rated IP66 and IK-10 Impact-Resistant Housing
g) Self learning video analytics on all sensors
h) Content adaptive IR technology up to 30m (100ft)
i) 3D Noise Reduction Filter
j) 8 MP per sensor resolution
D.3.3 At a minimum, equal or better than Avigilon Interior/Exterior Fixed 4 MP IP Camera: The FPS Local POC shall determine the field-of-view (FoV) for each camera with the Contractor, at the time of installation.
a. ONVIF Compliant Profile S and Profile G
b. Operate in a temperature range of -25 deg C to +60 deg C (-13 deg F to +140 deg F)
c. Operate in a humidity range of 0-95% RH (non-condensing)
d. High Definition Stream Management
e. Multi-stream H.264, Multi-stream H.265, Motion JPEG;
f. Video Resolution: 61 MP
g. IPv4/IPv6, HTTP,HTTPS, SOAP,DNS,NTP, RTSP, RTCP, RTP, TCP,UDP, IGMP, ICMP,DHCP, Zeroconf, ARP,HSTS
h. Environmental rating IP66,
i. PoE: IEEE802.3at Class 4 compliant
j. Teach by Example Technology
k. Password protection, HTTPS encryption, digest authentication, WS authentication, user access log, 802.1x port based authentication, FIPS 140-2 L1 (with optional camera license), FIPS 140-2 L3 (with optional accessory)
l. 5 year warranty
D.3.3.1
D.4 Network Managed Switch
a) Physical Aspects <Apply appropriate specifications>
(1) 24 auto-sensing RJ45 10/100/1000 ports; Layer 3 managed
(2) 4 SFP ports 100/1000
(3) Serial DB9 RS-232 console port
(4) Rack Mountable
b) Power over Ethernet (PoE)
(1) 24 PoE+ ports
(2) IEEE 802.3at (up to 30 Watts/port)
D.5 Additional System Component, software, location etc. specifications
D.5.1 At a minimum, the Monitor Mount for Desk Console shall have the following characteristics:
a) Holds most monitors up to 20 lbs. with VESA 75/100 pattern.
b) Capable of holding two (2) 24” monitors
c) Compatible with LD Series Desk systems
d) Vertical Range: 26.8"
e) Horizontal Range: 19.3" to 36.2"
D.5.1 At a minimum, the UPS shall possess the following salient characteristics.
a) Heavy duty surge protector
b) Rack Mountable
c) Sized to provide at least four (4) hours of back up battery power.
D.5.2 At a minimum, the Console Desk shall be equal or better than Windstead and have the following.
d) Height: 30"
e) Width: 48"
f) Monitor Mountable
g) Material: Wood Top
h) Desktop finish: constructed of 1” thick 45 lb. density industrial MDF board with thermolaminate.
i) Power distribution/cable management cabinet/constructed of fully welded, 16- gauge steel and feature integral front and rear doors for convenient access.
j) Stainless steel footrest shall be constructed of 18-gauge steel.
D.5.3 At a minimum, the GPS Time Server shall have the following.
k) Protocol NTP Stratum 1 Time Server
l) Accuracy Ethernet NTP ± 1ms overall
m) GPS source ±0.1μS
n) ANTENNA
o) Connector SMA Male
p) Cable 5-meter cable, (optional 10-meter extension)
q) Antenna head GPS sensor, in externally rated magnetic housing (+ adhesive pad/window fixing)
r) Unit power 1.5W
s) POE type Class 1
t) Alternative power input 10-40V DC (max current 150mA at 12V)
u) ETHERNET
v) Connector type RJ45
w) Rate 10Base-T/100Base-TX full-duplex with auto-negotiation
x) Data security Shared Keys system (server authentication)
y) Dimensions L 87mm W 75mm H 22mm. L 3.42 inches W 2.95 in H 0.86 in.
z) Weight 123g [ 4.3oz] (with mounting brackets) 121g [4.2oz].
aa) Operating temperature -15oC to 75oC [5oF to 167oF].
ab) Relative humidity 95% non-condensing.
ac) Compliance CE, FCC, RoHS
| D.5.4 | At a minimum, the VSS Equipment Rack shall have the following | |
| characteristics. | ||
| FPS Control room |
ad) Metal lockable rack
ae) Glass doors with handle
af) On rolling casters
ag) Equipment cooling fans
ah) 72” high
USMS Control room.
ai) Metal lockable rack
aj) Glass doors with handle
ak) On rolling casters
al) Equipment cooling fans.
am) 24” high.
1. ADDITIONAL PROJECT REQUIREMENTS
E.1 Design Standards
E.1.1 Design Limitations – During design and planning activities, the Contractor shall advise the FPS COR/TPOC of all functional incompatibility issues and/or system interoperability limitations of any equipment to be installed. This shall include, but is not limited to, limitations as a result of insufficient heating, ventilation and HVAC, power, rack, console, and space requirements.
E.1.2 Infrastructure Design – The system design shall include all conduit, junction boxes, cabling, fiber, network topology, and HVAC and power requirements for the proposed Network Video Management System (NVMS).
E.1.3 Equipment Selection – The Contractor shall use commercial off the shelf (COTS) components in system design.
E.1.4 Backup Power Requirements –All VSS electrical and electronic equipment installed shall be powered from an Uninterruptable Power Supply (UPS). It is expected that all equipment necessary for continuous live viewing, recording, and archiving VSS video will be uninterrupted during a power outage. The UPS shall be sized to provide at least four (4) hours[footnoteRef:1] battery back-up in the event the primary power source is interrupted. The Contractor shall include load calculations with their bid proposal. [1: ISC RMP Criteria 70 - Provide uninterruptible emergency power to essential electronic security systems for a minimum of four hours.]
E.1.5 Wiring Schematics – The Contractor shall provide complete system design wiring schematic diagrams representing planned device terminations to and between system equipment and components.
E.1.6 Riser Diagrams – The Contractor shall supply a system riser diagram. The diagram shall indicate the location of all associated system components.
E.2 Materials and Equipment
E.2.1 Items of the same type shall be products of a single manufacturer. All material, software and hardware, shall be new, the most current version, and presently being produced.
E.2.2 The Contractor shall provide enclosures as necessary for equipment not mounted in racks or supplied with an appropriate housing.
a) Interior: Enclosures to house equipment in an interior environment shall meet the requirements of NEMA 250 Type 12.
b) Exterior (Exposed-to-Weather): Enclosures to house equipment in an outdoor environment shall meet the requirements of NEMA 250 Type 4X.
E.2.3 All external camera housings shall be minimum IP66/NEMA4X rated for protection against rain, dust, and snow.
E.2.4 All camera housings shall be a minimum IK-10 Impact-Resistant for vandalism.
E.2.5 Camera housings shall match the color and architecture of the building, equal to or greater than the existing camera housings. Coloring camera housings shall not void the camera and housing manufacturer’s warranty. Before camera housings are painted the color shall be approved in writing by the Facility Security Committee.
E.3 Electrical and Cabling Requirements
E.3.1 Wires, cables, and fiber shall meet applicable requirements of NFPA 70 and UL listings for type and method of installation.
E.3.2 Materials, equipment, and devices shall, at a minimum, meet requirements of UL, where UL standards are established, and requirements of NFPA 70.
E.3.3 All wire, cable, and fiber runs shall be installed in accordance with all federal, state, and local codes and/or regulations. In the instance there is a conflict between applicable codes and regulations, the most stringent shall apply.
E.3.4 All wire, cable, and fiber runs shall be installed inside conduit and sized according to NFPA 70 for fill requirements. As an alternative, if allowed by applicable codes and/or regulations, wire, cable, and fiber may be installed utilizing wire molding, cable trays, and inner duct. Industry approved hangers/hooks may be substituted for conduit, if allowed by applicable codes and/or regulations, in the advent wire, cable, and fiber runs are installed above a suspended ceiling. No wire, cable, or fiber shall be left unsupported or hanging across ceiling tiles, HVAC ductwork, sprinkler pipes, water pipes, or other appurtenances previously installed.
E.3.5 All wire, cable, and fiber shall not contain splices between equipment termination points.
E.3.6 All wire, cable, and fiber shall be clearly labeled at both ends utilizing a permanent type of label using a common labeling convention.
E.3.7 There shall be no crimp type fittings utilized during cable/wire termination unless specified by the equipment manufacturer.
E.3.8 All equipment connected to AC power shall be protected from surges as described in IEEE C62.41 and IEEE C62.43. Fuses shall not be used for surge protection.
E.3.9 All cable and fiber installed in conduit shall include a pull string for future use. If an existing pull string is used in any location it shall be replaced with a new one.
E.3.10 All cable and fiber installed in support of this SOW shall be tested and test reports included in the O&M manual.
E.3.11 All wire, cable, or fiber that is existing and to be reused in support of this SOW shall be tested prior to use. Test report(s) shall be provided with final installation documentation and denoted that wire, cable, or fiber was previously installed.
E.3.12 All Ethernet network cabling shall be CAT 6/7 metallically shielded cable or multimode fiber optic cable, UL listed for its intended use (e.g., indoor, outdoor, plenum).
E.3.13 All CAT 6/7 cabling shall be installed in accordance with ANSI/TIA/EIA-568-B Commercial Building Telecommunications Cabling Standard. All cable terminations shall conform to ANSI/TIA/EIA-568-B standards. A few key areas of concern, but not all inclusive are:
a) Pair twists shall be maintained as close as possible to the point of termination.
b) Strip back only as much jacket as is required to terminate individual pairs.
c) All four pairs shall be terminated.
d) Pin/Pair assignments shall follow the T568B configuration.
E.3.14 All CAT 6/7 cabling shall be tested to certify that the cable conforms to ANSI/TIA/EIA-568-B standards. The test device shall provide an electronic copy of the test results. Test results shall be printed and included in the O&M manual.
E.4 Final Inspection and Acceptance
E.4.1 Upon completion of the installation the Contractor shall perform a Contractor Verification Test (CVT) in accordance with approved Perform Performance Verification Test (PVT) procedures to ensure installed system is fully operational. A copy of the test results shall be available for review by the FPS PM prior to commencing PVT testing and final inspection.
E.4.2 The Contractor shall submit, at a minimum five business days in advance of PVT testing, a proposed testing plan to the FPS COR/TPOC. The plan shall include test procedures, actions, and expected results demonstrating system functionality and compliance with this SOW. The test plan shall also include means for documenting test results. The test plan shall be approved by the FPS COR/TPOC prior to the Contractor requesting Final Inspection and PVT testing.
E.4.3 The Contractor shall notify the FPS COR/TPOC in writing when requesting a date and time for Final Inspection and PVT testing. Request must be received, at a minimum, five business days in advance.
E.4.4 The Contractor shall provide all equipment and manpower necessary to perform Final Inspection and PVT testing.
E.4.5 Final Inspection Minimum Requirements
a) Review of Redline drawings.
b) Walk-through and inspection of all installed components and workmanship.
c) Perform Performance Verification Test (PVT) in accordance with approved test plan.
d) All equipment default or contractor entered user IDs and passwords shall be relinquished by the Contractor to the Government.
e) In the event a deficiency is found, or a test fails the Contractor shall have personnel available onsite to resolve the issue so inspection and testing may continue. Once the Contractor deems the issue has been resolved, a re-inspection or re-test shall occur.
f) The Final Inspection and PVT testing shall be performed during a single site visit.
g) Installation Acceptance by the Government shall be given only after the satisfactory completion of the Final Inspection, PVT testing, training, and receipt of all required deliverables outlined in this SOW.
E.5 Cleanliness, Protection, and Patching
E.5.1 The Contractor shall take necessary precautions to avoid damage to existing items that will remain in place, be reused, or remain the property of the Government. It shall be the sole responsibility of the Contractor to repair or replace damaged items, at no cost to the Government. Contractor shall notify the FPS COR/TPOC of any damage immediately.
E.5.2 The Contractor shall not disturb existing construction beyond the extent indicated or necessary to fulfill installation requirements. In the event excessive damage is caused it shall be the sole responsibility of the Contractor to repair damage, at no cost to the Government. Contractor shall notify the FPS COR/TPOC of any damage immediately.
E.5.3 The Contractor shall provide protective methods to control accumulation and migration of dirt and dust in and around all work areas. Removal of dirt, dust, and debris shall be completed daily and in accordance with all applicable federal, state, and local laws and regulation.
E.5.4 It shall be the sole responsibility of the Contractor to protect all existing building systems and utilities, to include, but not limited to, equipment, cabling, and appurtenances (e.g. fire, VSS, IDS, HVAC) during demolition, installation and construction. If any system, service, utilities, equipment, or cabling are damaged due to installation construction the Contractor shall repair damage at no cost to the Government.
E.5.5 If necessary, the Contractor shall be responsible for moving furniture and/or equipment to protect it from damage during installation. All items relocated during installation shall be returned to their original location at the completion of work in the area. Any items that are unable to be relocated shall be protected from damage. In the event damage is incurred during this time it shall be the sole responsibility of the Contractor to replace damaged items without cost to the Government.
E.5.6 The Contractor shall prepare and lay out work in advance. Exercise care when cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings, or other surfaces as necessary for installation, support, or anchoring of conduit, raceways, and equipment.
E.5.7 The Contractor shall provide a qualified installer to install fire-stopping material to all penetrations and openings created during the installation. All existing penetrations or openings utilized by the contractor during the installation shall have fire-stopping material installed, regardless if it was previously installed. Fire-stopping shall consist of furnishing and installing tested and listed fire-stop systems, combination of materials, or devices to form an effective barrier against the spread of flame, smoke and gases, and maintain the integrity of walls, fire resistance rated walls, partitions, floors, and ceiling-floor assemblies, including through-penetrations. Firestop systems shall be UL Fire Resistance listed or FM P7825a approved with ''F" and/or “T” rated to at least be equal to fire-rating of the wall, fire wall, or floor in which penetrated openings are to be protected.
E.5…