70RFPW24QW9000003 - AM2.pdf
PDF 3 MB Posted
- Attached to
- Video Surveillance System Installation for Robert E. Coyle Federal Courthouse in Fresno, CA
- Solicitation number
- 70RFPW24QW9000003
About this file
This document is a revised Statement of Work (SOW) for a Request for Quotation (RFQ) to upgrade the Video Surveillance System (VSS) at the Robert E. Coyle Federal Courthouse in Fresno, CA. The SOW details the requirements for the purchase and installation of a new standalone Network Video Management System (NVMS), IP cameras, client workstations, control center monitors, and related equipment. Key details include the existing system description, new system requirements, installation and configuration specifications, system testing and acceptance, warranty and maintenance, and required deliverables. The acquisition is a small business set-aside, with a performance period of no more than 60 business days after notice to proceed. The solicitation was issued on April 2, 2024 by the Department of Homeland Security, Federal Protective Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REVISION 2 Instructions to Offerors via AM3.docx | DOCX document | |
| REVISION 2 Attachment E - Contractor Quotation Checklist via AM3.docx | DOCX document | |
| 70RFPW24QW9000003 - AM3.pdf | ||
| REVISED Instructions to Offerors via AM2.docx | DOCX document | |
| REVISED Attachment A - SOW via AM2 70RFPW24QW9000003.docx | DOCX document | |
| REVISED Attachment E - Contractor Quotation Checklist via AM2.docx | DOCX document | |
| 70RFPW24QW9000003 - AM1.pdf | ||
| REVISED Attachment A1 via AM1 on 240422.pdf | ||
| V2 - Synopsis.docx | DOCX document | |
| 70RFPW24QW9000003 - Solicitation.pdf | ||
| C - Past Performance Form.pdf | ||
| E - Contractor Quotation Checklist.docx | DOCX document | |
| D - Past Performance Questionnaire.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
70RFPW24QW9000003
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Auburn WA 98001 Attn: Rachel Kalac
OPO/FPS/WEST CCG/R9
1901 C Street SW, Suite 100 Ofc of Procurement Operations - FPS U.S. Dept. of Homeland Security DHS/FPS/West CCG/Region 9
Auburn WA 98001 1901 C Street SW, Suite 100
70RFPW
Federal Protective Service Acq. Division Office of Procurement Operations U.S. Dept. of Homeland Security
FPS WEST CCG (70RFPW)
04/22/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/02/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
COR: Phil Coughlin, Philip.J.Coughlin@fps.dhs.gov, 415-500-1995
CO: Kelly Minturn, Kelly.M.Minturn@fps.dhs.gov, 253-876-6844
CS: Rachel Kalac, Rachel.D.Kalac@fps.dhs.gov, 253-876-6838
Budget POC: Tonia Patterson, Tonia.A.Patterson@fps.dhs.gov, 415-816-4365
Video Surveillance System (VSS) Installation at the Robert E. Coyle Courthouse in Fresno, CA
1. The purpose of this amendment is to:
a. Provide responses to timely questions received. Responses are provided via Attachment
1 - Questions & Answers.
b. Remove the original Attachment A, Statement of Work (pages 32-86/138 of the RFQ
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Kelly Minturn
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 94
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
70RFPW24QW9000003/0002
package), in its entirety and replace it with the revised, attached Attachment A, Statement of Work.
c. Remove the revised Attachment A1, Drawings
(via AM0001), in its entirety and replace with the revised, attached Attachment A1, Drawings.
d. Remove the original Attachment E, Contractor Quotation Checklist (pages 107-108/138 of the RFQ package), in its entirety and replace it with the revised, attached Attachment E, Contractor Quotation Checklist.
e. Remove the original Instructions to Offerors (pages 109-138/138 of the RFQ package), in its entirety and replace it with the revised, attached Instructions to Offerors.
2. There are no others changes as a result of this amendment; all other dates, terms and conditions shall remain the same.
****OFFERORS ARE ENCOURAGED TO REVIEW THE RFQ
PACKAGE AND ASSOCIATED AMENDMENTS IN THEIR
ENTIRETY. ANY SUBMISSION WHICH DOES NOT MEET THE
REQUIREMENTS OF THIS RFQ WILL BE REMOVED FROM
AWARD CONSIDERATION. ATTACHMENT E (revised via
AM0002) IS PROVIDED FOR YOUR CONVENIENCE AND
OUTLINES THE REQUIREMENTS OF THIS RFQ PACKAGE.****
Period of Performance: 07/01/2024 to 04/30/2025
ATTACHMENTS:
1 - Questions & Answers
A - Statement of Work (REVISED)
A1 – Drawings/Floor Plans (REVISED)
E - Contractor Quotation Checklist (REVISED) Instructions to Offerors (REVISED)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ATTACHMENT 1
Questions and Answers for 70RFPW24QW9000003 – Robert E. Coyle Courthouse, Fresno, CA - VSS Installation via AM0002
Date Rec’d Question Answer RFQ Reference 1 04/03/2024 We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current/previous contract number?
This is a stand-alone contract with new requirements.
n/a
2 04/03/2024 We offer video surveillance that has the ability to capture facial recognition, weapon and gunshot detection as well as adaptive response with local 911 centers. Would this form of video surveillance be considered for this RFQ?
All interested vendors, who meet the minimum submission requirements by the closing date and time of this RFQ, are considered. Past Performance will be evaluated for Period of Performance, Scope, Magnitude, Complexity, and Overall Rehire-ability.
Instructions to Offerors Section 3, Paragraph 5, pages 111- 113/138 of the RFQ package.*
3 04/04/2024 When is the scheduled site assessment? Or do I need to make one?
As outlined in the original solicitation, a one-time only site visit was scheduled for 04/17/2024 at
0900 PST.
Instructions to Offerors, Section 2a, page 109/138 of the RFQ Package.*
4 04/06/2024 Can you please confirm if any type of documents are required to be submitted prior to site visit?
There are no required documents to attend the site visit; however, as outlined in the original solicitation, offerors shall email the Contract Specialist should they plan to attend the site visit.
Instructions to Offerors, Section 2a, page 109/138 of the RFQ Package.*
5 04/15/2024 When is the site visit scheduled and how many people can attend?
As outlined in the original solicitation, a one-time only site visit was scheduled for 04/17/2024 at 0900 PST. Offerors are not limited on attendees.
Instructions to Offerors, Section 2a, page 109/138 of the RFQ package.*
6 04/25/2024 The SOW says cable that isn’t designated for reuse will be removed, will any cable be reused? Or are we to remove all existing cable and replace with new CAT6 cable? (Ref SOW C.1.2)
Yes, the vendor shall remove existing cable. All currently installed wire, cable, and fiber shall be completely removed and replaced with the appropriate new type of wire, cable or fiber by the Contractor and properly disposed of.
Revised SOW via AM0002:
SOW Section C.1 Subsection C.1.2 (revised)
7 04/25/2024 The plans show there are 5x existing 4MP cameras, 5x existing 360 cameras, 1x existing PTZ camera, and 1x existing PTZ camera to be relocated. But in the 70RFPW24QW9000003 section B .1 it lists 9x PTZ cameras, and 4x 4MP cameras. Can we please have clarification on the exact camera models that are
No existing cameras will be reused, all existing cameras shall be removed, and new cameras shall replace those.
In relation to the plans/drawing, the term ‘existing’ notifies vendors there is an existing camera that needs to be removed and replaced
Revised SOW and Drawings via
AM0002:
SOW Section B.1, Description of Existing System (original and revised)
70RFPW24QW9000003 - VSS for Robert Coyle CH AM0002 Page 3 of 94
Questions and Answers for 70RFPW24QW9000003 – Robert E. Coyle Courthouse, Fresno, CA - VSS Installation via AM0002 going to be reused? (Ref AM1 drawings and SOW B.1) with a new camera; icons indicating ‘new’ notifies vendors there is no camera in that location that needs to be removed prior to installing the new camera.
Attachment A1 – Drawings, page 87/138 of the RFQ package (revised)
8 04/25/2024 Will a console desk be expected to be included in this quote? If so, please clarify the location and confirm there is ample space. (Ref SOW D.4.2)
Yes, a console desk is a required item in accordance with the specifications set forth in the SOW. The location shall be the FPS Control Room, which is labeled on the drawings, and there is enough room for the console desk that is described in the SOW.
Revised SOW and Drawings via
AM0002:
SOW Section D.5, Sub-section D.5.2, items d-j (original and revised)
Attachment A1 – Drawings, page 87/138 of the RFQ package (revised)
9 04/25/2024 The specs for the equipment rack mention it being 72” high, but on the site walk it was mentioned that a small server rack would be preferred, please clarify the dimensions of the rack that are desired.
(Ref SOW D.4.4)
There will be a 72” high equipment rack in the FPS Control Room and a 24” high server rack in the USMS control room. The dimensions and specifications for the USMS server rack have been added to the revised SOW that is being incorporated as part of amendment 0002.
Revised SOW via AM0002:
SOW Section D.5, Sub-section D.5.4, Items dd-mm (original and revised) for FPS Control Room
SOW Section D.5, Sub-section D.5.4, Items ii-mm (revised only) for USMS Control Room
10 04/25/2024 Please identify if there are any cameras that need to be removed. On the site walk it was mentioned a camera was no longer working and was to be removed, so please clarify any camera locations that require removal. (Ref AM1 drawings)
This project is for the purchase and installation of a new standalone Video Surveillance System; all existing cameras shall be removed and replaced by new cameras.
For the purposes of the drawing, the term ‘existing’ notifies vendors there is an existing camera that needs to be removed and replaced with a new camera; icons indicating ‘new’ notifies vendors there is no camera in that location that
Revised Drawings via AM0002:
Attachment A1 – Drawings, page 87/138 of the RFQ package, reference revision provided via AM0002
AM0002 Page 4 of 94
Questions and Answers for 70RFPW24QW9000003 – Robert E. Coyle Courthouse, Fresno, CA - VSS Installation via AM0002 needs to be removed prior to installing the new camera.
11 04/25/2024 In section B.2.1 of the SOW it says to base storage calculations based off of the cameras full frame rate, but in section C.3.1 it says to calculate all cameras at 15 frames per seconds. Please clarify which section should be used for the storage calculations. (Ref SOW B.2.1 and SOW C.3.1)
A correction has been made to align the sections which now report the same information; both sections now state maximum frame rate at the device (Camera, not total system).
Revised SOW via AM0002:
SOW Sections B.2, Sub-Section B.2.1 and SOW Section C.3, Sub-Section C.3.1.
12 04/25/2024 Is the walk mandatory, thus precluding us from pursuing, or are we still able to bid?
The site visit is a one-time only, optional event.
Attending the site visit is not mandatory. Not attending does not disqualify vendors from submitting a quotation.
n/a
13 04/25/2024 Is the ISO 9001-2015 Certification due with the quotation or prior to any work being performed?
In accordance with the SOW, the ISO 9001-2015 is required as part of your quotation submission.
Please refer to documents within this amendment, AM2, which states the certificate shall be included in PART III of your submission.
Revised SOW, Attachment E – Contractor Quotation Checklist, and Instructions to Offerors via AM0002:
SOW Section C.1, Sub-section C.1.12 (original and revised)
Attachment E, Contractor Quotation Checklist (revised)
Instructions to Offerors, Section 3, Paragraph 3, Item 5 (revised)
*The responses to Questions 2 - 5 are not impacted by the revised Instructions to Offerors, as a result, the original reference has been noted.
However, Question 13 does require vendors to reference the revised Instructions to Offerors.
AM0002 Page 5 of 94
FOR OFFICIAL USE ONLY (FOUO)
For Official Use Only (FOUO)
Federal Protective Service U.S. Department of Homeland Security
STATEMENT OF WORK
REVISED VIA AMENDMENT 0002
for
Upgrade of Video Surveillance System (VSS)
VSS Upgrade Project
Robert E. Coyle Federal Courthouse 2500 Tulare Street Fresno, CA 93721
Building Number: CA0309
Attachment A - Statement of Work REVISED via AM0002
AM0002 Page 6 of 94
STATEMENT OF WORK
TABLE OF CONTENTS
A. BACKGROUND
B. PURPOSE
C. SCOPE
C.1 GENERAL
C.2 INSTALLATION REQUIREMENTS
C.3 VIDEO STORAGE REQUIREMENTS
C.4 CONTROL ROOM MONITORS
C.5 NETWORKING EQUIPMENT
C.6 OPERATING SYSTEMS UPDATES, SERVICE PACKS, AND FIRMWARE
C.7 WIRELESS POINT-TO-POINT:
D. SYSTEM/EQUIPMENT SALIENT CHARACTERISTICS AND REQUIREMENTS
D.1 NETWORK VIDEO MANAGEMENT SYSTEM
D.2 MINIMUM SERVER AND WORKSTATION REQUIREMENTS
D.3 IP NETWORK VIDEO CAMERA MINIMUM REQUIREMENTS
D.4 NETWORK MANAGED SWITCH
D.5 ADDITIONAL SYSTEM COMPONENT, SOFTWARE, LOCATION ETC. SPECIFICATIONS
D.5.1 AT A MINIMUM, THE MONITOR MOUNT FOR DESK CONSOLE SHALL HAVE THE FOLLOWING CHARACTERISTICS:
E. ADDITIONAL PROJECT REQUIREMENTS
E.1 DESIGN STANDARDS
E.2 MATERIALS AND EQUIPMENT
E.3 ELECTRICAL AND CABLING REQUIREMENTS
E.4 FINAL INSPECTION AND ACCEPTANCE
E.5 CLEANLINESS, PROTECTION, AND PATCHING
E.6 WARRANTY AND MAINTENANCE
E.7 SAFETY AND HEALTH
E.8 QUALITY CONTROL PLAN
E.9 TRAINING
E.10 CONFIGURATION MANAGEMENT
E.11 COMPONENT/DEVICE CONFIGURATIONS
E.12 NETWORK SETTINGS
E.13 WIRELESS NETWORK SECURITY
E.14 AUDIT AND ACCOUNTABILITY
E.15 IDENTIFICATION AND AUTHENTICATION / ACCESS CONTROL
E.16 DATA PROTECTION
E.17 USER ACCOUNTS
AM0002 Page 7 of 94
E.18 INCIDENT MANAGEMENT AND DISASTER RECOVERY
E.19 SOFTWARE MAINTENANCE
E.20 ENTERPRISE ARCHITECTURE
F. DELIVERABLES
F.1 GENERAL
F.2 REQUEST FOR QUOTATION (RFQ)
F.3 PRE-INSTALLATION DELIVERABLES
F.4 POST-INSTALLATION DELIVERABLES
G. PROJECT ADMINISTRATION
G.1 WORK AUTHORIZATION
G.2 PERIOD OF PERFORMANCE
G.4 CONTACTS
G.5 SPECIAL SCHEDULING REQUIREMENTS
G.6 CONTRACTOR ACCESS AND USE OF PREMISES
G.7 SECURITY REQUIREMENTS
G.8 CONTRACTOR SUITABILITY REQUIREMENTS
H. APPLICABLE STANDARDS
H.1 GENERAL
H.2 ACCESSIBILITY REQUIREMENTS (SECTION 508)
I ACCOUNTABLE PROPERTY:
I.1 DEFINITIONS:
I.2 DELIVERABLES:
I.3 INVOICES:
I.4 PROPERTY ACCOUNTABILITY:
I.5 PHYSICAL INVENTORY:
I.6 PROPERTY DISPOSAL:
I.7 LOST, STOLEN, DAMAGED OR DESTROYED (LDD) PROPERTY:
J. INFORMATION TECHNOLOGY SECURITY
J.1 SECURITY CERTIFICATION/ACCREDITATION
J.2 SECURITY REVIEW AND REPORTING
J.3 CONTINUOUS MONITORING
AM0002 Page 8 of 94
FOR OFFICIAL USE ONLY (FOUO)
For Official Use Only (FOUO) 1
A. BACKGROUND
A.1 The Federal Protective Service (FPS) is the federal law enforcement agency responsible for the protection and security of federal facilities, employees, and visitors. FPS actively works to reduce security vulnerabilities of federal facilities from criminal, terrorist, accidental, and natural disaster threats to ensure properties remain safe, secure, and available to the American public and employees of the federal Government.
A.2 The following Statement of Work (SOW) and guidelines have been developed by the
Department of Homeland Security (DHS), Federal Protective Service (FPS) to mitigate threats and vulnerabilities pertaining to federal buildings and Government leased spaces. The SOW and regulations were developed with the notion that the security posture of each federally owned building or Government leased space is unique.
B. PURPOSE
B.1 Description of Existing System
Brand Make Model Quantit y
Location Cable Specification
DVR Bosch Bosch DVR-650-
16A-1TB
1 FPS Security Room #1221
COAX
Analog PTZ Camera
Pelco
PTZ
Spectra
IV
S5230-
EG1
1 North Tulare Street
Camera
Pelco
PTZ
Spectra
III
S5230-
EG1
P Street near Loading Dock
Camera
Pelco
PTZ
Spectra
III
S5230-
EG1
1 Loading Dock West
Camera
Pelco
PTZ
Spectra
IV
S5230-
EG1
South Parking
AM0002 Page 9 of 94
For Official Use Only (FOUO) 2
Camera
Pelco
PTZ
Spectra
III
S5230-
EG1
1 North Tulare Street
Camera
Pelco
PTZ
Spectra
III
S5230-
1 Loading Dock
Camera
Pelco
PTZ
Spectra
III
S5230-
1 South Side
Camera
Pelco
PTZ
Spectra
III
S5230-
EG1
1 Main Entry SW Corner
Camera
Pelco
PTZ
Spectra
IV
S5230-
EG1
1 Outside Main Entry
Analog Fixed Camera
Pelco EH2515 C20-DW6 1 Loading Dock COAX
Analog Fixed Camera
Pelco EH2515 C20-DW6 1 Loading Dock COAX
Analog Fixed Camera
Pelco EH2515 SSC-113A 1 Inside West Stairwell
Analog Fixed Camera
Pelco EH2515 C20-DW6 1 Outside West Stairwell
Monitor Pelco Pelco PMCL317
BL
Monitor Pelco Pelco PMCL417 A
1 USMS Control Room
Keyboard Pelco Pelco KBD300A
COAX
Switcher Pelco Pelco Switcher
CM6700
COAX
Distribution Amp
Pelco Distributi on Amp
Pelco CM9760-
MDA
COAX
Power Supply
Pelco Pelco Power Supply
MCS16-
AM0002 Page 10 of 94
For Official Use Only (FOUO) 3
B.2 Description of New System
B.2.1 This SOW is for the purchase and installation of a new standalone, Network Video
Management System (NVMS), fixed/panoramic/PTZ IP cameras, client workstations, control center flat panel monitors, and all additional equipment and appurtenances necessary for a fully functional IP VSS located at the Robert E. Coyle Federal Courthouse 2500 Tulare Street Fresno, CA 93721. Also, this SOW shall include the purchase, installation, and programming of all contractors supplied equipment and or components.
B.2.2. The VSS shall monitor vehicle traffic, personnel entry, emergency exits, and the exterior perimeter of the facility. The VSS shall retain video for a minimum of 30 days plus 25% additional storage space for future expansion. Storage shall be calculated at full camera resolution, maximum frame rate at the device (Camera, not total system), and low compression.
C. SCOPE
C.1 General
C.1.1 As part of the pre-bid process, FPS may have a site visit and all interested Contractors are invited to attend. The purpose of the site visit is for Contractors to survey the site and review the requirements of this SOW. A site visit will be scheduled by the COR/FPS PM. All questions relevant to this SOW shall be submitted in writing to the FPS COR/TPOC. The Contractor shall not make or assume any changes to this SOW without written approval from the FPS COR/TPOC.
C.1.2 The Contractor shall be responsible for the removal, inventory, packaging for storage and return of all removed equipment to the FPS COR/TPOC. All currently installed wire, cable, and fiber shall be completely removed and replaced with the appropriate new type of wire, cable or fiber by the Contractor and properly disposed of.
C.1.3 The existing system shall remain fully functional and operational to the extent possible during the installation of the new surveillance system. The contractor shall cut over from the existing system to the new system in stages in order to minimize the number and duration of outages. The Contractor shall submit a system cutover plan in accordance with Section F Deliverables. The cutover plan shall be reviewed and approved in writing by the FPS COR/TPOC.
C.1.4 The Contractor shall provide and install and configure the system as described and/or shown herein. The system shall include all connectors, adapters, terminators, and appurtenances to interconnect all equipment. The Contractor shall also supply all cabling and miscellaneous materials necessary to interconnect all equipment installed in accordance with this SOW.
AM0002 Page 11 of 94
For Official Use Only (FOUO) 4
C.1.5 The Contractor shall be required to be familiar with all applicable codes while carrying out the work outlined in this SOW. The Contractor shall complete the work pursuant to this SOW following all applicable codes and standards including, but not limited to:
Occupational Safety and Health Administration (OSHA), Underwriters Laboratories (UL), National Fire Protection Association (NFPA), National Electrical Code (NEC), and any additional federal, state and local codes and policies.
C.1.6 The Contractor shall furnish all tools and equipment necessary to complete all work outlined in this SOW. By no means shall the Contractor be authorized the use of Government owned property, tools or equipment, to complete work in accordance with this SOW, unless otherwise specified.
C.1.7 In the event any operational system or utility (e.g. fire, IDS, HVAC) is required to be disabled or turned off, forty-eight (48) hour notice shall be required and approved by the GSA Building Manager, FPS Inspector, and/or FPS COR/TPOC prior to deactivation.
a) The Contractor, prior to departing for the day, shall ensure all system(s) previously disabled or turned off are functioning properly. A basic functional test shall be required to determine proper functionality of the system(s) and should be reported to the FPS COR/TPOC.
b) In the event a system is non-functional once enabled or turned on, it shall be the responsibility of the Contractor, at no additional cost to the Government, to restore the system(s) prior to departure from the site.
c) If the Contractor fails to restore all system(s) before departing, they shall be liable for all costs incurred by the Government to restore system(s) functionality.
C.1.8 All personnel engaged in installation activities pursuant to this SOW shall be licensed by the state, local authority, and/or the city local authority in the required trades or professions which require licensing by such jurisdictions. The type and level of license shall be consistent with requirements of the jurisdictions and work to be performed by this SOW.
C.1.9 It shall be the sole responsibility of the contractor to employ personnel licensed and qualified to carry out all tasks outlined in this SOW. At no time during the installation shall the contractor require Government personnel to complete tasks required to be completed by the contractor as covered by this SOW.
C.1.10 The Contractor shall be solely responsible for ensuring their employees and subcontractors abide by all requirements of the contract. At all times while work is being performed in accordance with this contract, the Contractor shall have a supervisory representative available to answer questions, resolve issues, supervise company employee(s), and subcontractor(s).
AM0002 Page 12 of 94
For Official Use Only (FOUO) 5
C.1.11 The Contractor shall provide a daily access schedule to coordinate installation activities. The schedule shall be submitted as part of the project plan.
C.1.12 The Contractor shall maintain a separate set of drawings, schematics, and wiring diagrams of the VSS to be used for creating as-built drawings. This set shall be accurately kept up to date by the Contractor, noting all changes and additions to the VSS and shall be available for the final inspection walkthrough.
C.1.13 The Contractor may be required to attend installation construction meetings.
C.1.14 For buildings 45 years of age or older: All repairs, installations and removals are required to follow the Secretary of the Interior’s Standards for Rehabilitation (SOI):
https://www.nps.gov/crps/tps/rehab-guidelines/stand.htm.
C.1.15 The Contractor must be ISO 9001-2015 Certified and provide their ISO certification with their proposal documentation.
C.1.16 The Contractor shall install all new
C.2 Installation Requirements
C.2.1 The Contractor shall install all system components and appurtenances in accordance with manufacturer’s instructions following all applicable local, state and federal codes and policies. All appurtenances, such as, but not limited to connectors, terminators, and mounting hardware shall be supplied by the Contractor, as well as, all adjustments, alignments, programming, and configuration required for a complete and optimal VSS operating system.
C.2.2 The Contractor shall provide and install a complete statically assigned IP based VSS to include, but not limited to, Network Video Management System (NVMS) capable of viewing, recording, playback, and exporting of video, cameras, servers, RAID 6 video storage, workstations, and network routers/switches. Provide and install camera mounts and other appurtenances, premise wiring, and system hardware as required for a complete and fully operational system as specified in this SOW. The installed system shall easily be expandable for future growth.
C.2.3 The Contractor, for all equipment/device(s) requiring licensing, shall purchase/install license(s) as required by the manufacturer. All licensing fees shall be nonrecurring.
Documentation of all software and hardware licenses shall be provided to FPS as part of the final system documentation.
C.2.4 All equipment required to be wall-mounted shall be mounted.
C.2.5 The Contractor shall be responsible to provide the necessary equipment and tools to access all equipment which is not accessible by ladder. The contractor is accountable
70RFPW24QW9000003 - VSS for Robert Coyle CH AM0002 Page 13 of 94 https://www.nps.gov/crps/tps/rehab-guidelines/stand.htm
For Official Use Only (FOUO) 6 for all tool and equipment used during the course of installation; potentially dangerous items must remain under the physical control of the installer at all times. All tools and equipment to include electronic equipment and computers are subject to inspection by
FPS.
C.2.6 All measurements and equipment locations are approximate and shall be verified by the
Contractor for accuracy and installation feasibility. The Government shall not be held responsible for any error or variation in any measurements or other data listed, nor shall the Contractor, because of an error or variation in any measurement listed, be relieved of the responsibility to carry out the requirements in accordance with the true intent and meaning of the specifications without additional cost to the Government.
C.2.7 All ceiling tiles removed to accommodate installation shall be returned at the end of the workday.
C.2.8 The Contractor shall remove and haul debris from the project site daily and dispose of in a proper, acceptable manner in accordance with all federal, state and local laws and regulations, off of the job site property. The debris created from this project shall not be disposed of at the job site, in Government dumpsters, or on Government property.
C.2.9 The Contractor shall install and configure cameras in accordance with manufactures recommendations and industry best practices for optimal live view and recording.
C.2.10 The Contractor shall verify all camera views with the FPS COR/TPOC prior to installation.
C.2.11 The Contractor, when removing the existing cameras, cabling, and appurtenances in accordance with this SOW, shall ensure all openings or penetrations are sealed and/or patched accordingly to protect against weather exposure, unless otherwise designated for reuse. All openings or penetrations that are designated for reuse shall be sealed and/or patched accordingly to protect against weather exposure at the completion of installation. All penetrations that become exposed to weather during installation shall be protected from exposure throughout the installation period.
C.2.12 Installers shall be trained, certified, and authorized by the Manufacturer to install, integrate, test, and commission the system. The contractor shall provide and submit with their proposal documentation from the manufacture that they are trained, certified, and authorized to install, integrate, test, and commission the system. If documentation is not available, the contractor can substitute by providing with their proposal confirmation on manufacturer letterhead, they are trained, certified, and authorized to install, integrate, test, and commission the system within two years of the submittal date.
C.2.13 At least one factory certified trained technician on the VMS being installed by the contractor must be onsite at all times during the installation. Factory certification must be within the last two years (date of proposal).
AM0002 Page 14 of 94
For Official Use Only (FOUO) 7
C.3 Video Storage Requirements
C.3.1 The Contractor shall calculate appropriate storage for all cameras recording at the maximum frame rate at the device (Camera, not total system), maximum resolution, and minimum compression. Storage capacity shall be capable of storing video for a minimum of thirty (30) days. The Contractor shall calculate and provide video storage requirements with the Quotation. The Contractor shall include enough storage for an additional 25% storage for future expansion maintaining the thirty (30) day minimum requirement. In addition to 6 additional camera licenses. The contractor will not have access to video data and will not be responsible for the collection, use, maintenance or storage of video data.
C.3.2 The Contractor shall configure the installed VSS to function in a Network Domain environment, not as a workgroup.
C.3.3 Microsoft Windows and the NVMS software shall be configured to use MS Active
Directory for authentication. If the NVMS software is not capable of authenticating to the Active Directory, then separate NVMS accounts will be configured in accordance with account management plan.
C.3.4 The Contractor shall not apply power to the NVMS until, at a minimum; the following checks have been completed.
a) All equipment has been installed and connected in accordance with manufacturer’s instructions.
b) All installed and/or reused wiring has been tested accordingly (e.g. shorts, opens, continuity).
c) Power supplies have been verified to operate at the correct voltage, phase, and frequency. Satisfaction of the above requirements shall not relieve the Contractor of responsibility for incorrect installation, defective equipment, or collateral damage as a result of Contractor work/equipment.
C.3.5 The Contractor shall ensure all system devices are configured appropriately for time synchronization. The local time zone where the system physically resides will be utilized. All devices shall be configured for time synchronization with a GPS enabled network time source. The GPS time source will not have any connectivity capability beyond receive functionality.
C.3.6 The Contractor shall demonstrate to the FPS COR/TPOC that the completed NVMS installation complies with the contract requirements. Using an approved test procedure, all physical and functional requirements of the project shall be demonstrated and shown. The test procedure shall include techniques and requirements for validating all
AM0002 Page 15 of 94
For Official Use Only (FOUO) 8 significant system functions. The Contractor shall provide all test equipment and personnel required for final testing.
C.4 Control Room Monitors
C.4.1 The new monitors to be provided and installed are one (1) fifty-inch (50”) monitor and two (2) twenty-four-inch (24”) monitors shall be installed in the FPS Security Room #1221. One (1) forty-three-inch (43”) monitor in the US Marshal Service (USMS) Court Security Officer (CSO) control room. The one (1) 50” monitor shall be wall mounted. The two (2) 24” monitors shall be a vesa desk mounted and shall be located in the FPS Security room # 1221. The one (1) 43” monitor located in the USMS CSO control room shall be wall mounted.
C.4.2 At a minimum, the 50” Monitor shall possess the following salient characteristics.
a) Color
b) 3840 x 2160 resolution, 16- or 32-bit pixel color resolution
c) Flat Panel
d) Wall and desk top Mountable.
e) Must meet applicable and appropriate Electronic Product Environmental
Assessment Tool (EPEAT) and ENERGY Star standards.
C.4.3 At a minimum, the 43” Monitors shall possess the following salient characteristics.
c) Flat Panel
d) Wall mountable.
e) Must meet applicable and appropriate Electronic Product Environmental
Assessment Tool (EPEAT) and ENERGY Star standards.
C.4.4 At a minimum, the 24” Monitors shall possess the following salient characteristics.
c) Flat Panel
d) Mountable to articulating desk mount to hold two (2) 24” monitors.
e) Must meet applicable and appropriate Electronic Product Environmental
Assessment Tool (EPEAT) and ENERGY Star standards.
C.5 Networking Equipment
C.5.1 As required per this SOW, the contractor shall purchase, install, and configure all equipment, components, and necessary appurtenances for a complete and appropriately configured Ethernet network connecting all devices of the NVMS.
AM0002 Page 16 of 94
For Official Use Only (FOUO) 9
C.5.2 The Contractor shall configure installed switches for Trunk line communication between the switches. Line encryption shall be enabled between all network devices to the maximum extent possible. If copper network cabling is utilized between network devices, it must be metallically shielded twisted pair.
C.5.3 The Contractor shall configure installed switches with Virtual Local Area Network
(VLAN) and appropriate VLAN Routing. VLAN’s to be configured are:
COYLE VLAN
Identify naming scheme of the network/VLAN when appropriate. Should be something unique for the facility, not called “security camera network” or something security related.
C.5.4 All equipment shall be rack mountable, if possible. All equipment that is not rack mountable shall be installed on the wall. An appropriately sized piece of ¾” plywood shall be mounted on the wall, painted with fire retardant paint, and all equipment mounted on the plywood. Final mounting location shall be approved by the FPS PM.
C.5.5 The Contractor shall provide and install a rack mounted 19” combination display, keyboard, and mouse (KVM) at a usable height, in FPS Security Room #1221 connected to the new NVMS Server for system configuration and administration.
C.5.6 The Contractor shall install new VSS client workstations in FPS Security Room #1221 and USMS Control Room. Location of workstation shall be coordinated with the FPS COR/TPOC before installation.
C.5.7 The Contractor shall enable software based, packet filtering firewalls on the VSS network. Firewalls will be enabled to permit only authorized network devices and protocols. A list of ports and protocols shall be provided as part of the system documentation for each unique device model and software suite. The VSS shall be functionality tested to ensure enabled firewall rules and port restrictions do not interfere with the overall functionality of the systems.
C.5.8 The Contractor shall ensure that all installed network devices that are Wi-Fi-capable have that capability disabled.
C.6 Operating Systems Updates, Service Packs, and Firmware
C.6.1 Operating systems and software applications shall be capable of being updated/patched after delivery. The Contractor shall ensure that all installed server(s) and client workstation(s) Operating System Software (OS), at the time of installation, are current with all security updates/patches, service packs, revisions, and shall provide through the warranty period. The NVMS and all other installed software shall be the current version with all applicable updates and installed in accordance with manufacturers recommendations.
AM0002 Page 17 of 94
For Official Use Only (FOUO) 10
C.6.2 The Contractor shall remove and/or disable all software components (bloatware) that are not required for the operation and maintenance of the camera system; and shall provide documentation on what is removed and/or disabled. The software to be removed and/or disabled shall include, but is not limited to: games, device drivers for network devices not delivered, messaging services (e.g., MSN, AOL IM), Servers or clients for unused Internet services, unused networking and communications protocols, unused document processing utilities (Microsoft Word, Excel, PowerPoint, Adobe Acrobat, OpenOffice, etc.).
C.6.3 The Contractor shall provide notification of patches affecting security within a pre-negotiated period (usually the warranty period) as identified in the patch management process.
a) Pre-Contract Award – The Contractor shall provide details on their patch management and update process. Responsibility for installation and update of patches shall be identified.
b) Post-Contract Award - The Contractor shall provide notification of known vulnerabilities affecting Contractor-supplied or required OS, application, and third-party software within 30 days after public disclosure.
C.6.4 The Contractor shall ensure that all VSS components have the latest manufacture approved firmware version installed. Firmware version is to be documented on the device inventory.
C.7 Wireless Point-to-Point:
C.7.1 Not Required
C.8 Attachments
C.8.1 VSS Locations: See floor plans (Attachment C. The contractor and FPS shall verify all camera installation locations to provide the optimal view prior to any installation.
AM0002 Page 18 of 94
For Official Use Only (FOUO) 11
D. SYSTEM/EQUIPMENT SALIENT CHARACTERISTICS AND
REQUIREMENTS
D.1 Network Video Management System
D.1.1 The NVMS shall support these essential software capabilities:
a) Live video monitoring
b) Recording of video
c) Playback of video from local or remote location(s)
d) Integral alarm/event management
e) Video export
D.1.2 The NVMS shall store/archive video using one of the following techniques:
a) Internal Disk Storage
b) Direct Attached Storage
c) Storage Area Network
D.1.3 The NVMS shall include image storage with configurable resolutions and frame rates.
D.1.4 The NVMS shall be compatible with, but not limited to: H.264, H265, MPEG4, and
MJPEG video compression formats.
D.1.5 The NVMS shall be capable of system fail-over and redundancy options.
D.1.6 NVMS System Architecture
a) HDMS SmartCodec Technology Support Automatically adjusts compression levels for regions in a scene, to optimize bandwidth while still maintaining image quality.
b) Appearance Search Technology Quickly search recorded video to find instances of a person or vehicle across all sites using cameras with Avigilon self-learning analytics. Search for a person by physical description, including clothing color, hair color, gender, and age group.
Search for a vehicle by physical description, including color and category
- car, truck, bus, bicycle, and motorcycle.
c) Facial Recognition Technology AI-powered facial recognition algorithms notify operators when a person of interest returns to a facility.
Add a person to a face watch list by uploading a photo or from recorded video. Create watch list alarms or monitor the Focus of Attention interface to detect matches.
d) Intelligent Search Powerful search tools enable you to quickly search recorded video for motion, the presence of classified objects (people or vehicles), background changes in the scene (thumbnail search), and for events.
AM0002 Page 19 of 94
For Official Use Only (FOUO) 12
e) Video Archive Retain and manage large amounts of video for on-demand retrieval and review. Extend your storage beyond NVRs using the Avigilon Video Archive for reliable and scalable storage.
f) Detailed Management, Monitoring, and Reporting of System Status and Security Detailed logs of storage, network, and overall system status to help ensure the highest possible system uptime for critical applications.
g) Unusual Activity Detection (UAD) technology enables object-level detection of atypical activity. This edge-based intelligence uses advanced AI technology and is designed to be object-aware, enabling operators to know when a person or vehicle is in an unusual location in the scene or moving at an unusual speed.
h) Unusual Motion Detection (UMD) technology enables fast video search and is designed to reduce hours of work to minutes by narrowing potentially thousands of motion events to a handful. This allows operators to focus their attention on recorded video needing further investigation.
i) Federal Government Compliance with FIPS 140-2 Certified Encryption To comply with policies, Federal Government and other customers can enable FIPS 140-2 certified cryptography on VSM software and on supported cameras. Required camera cryptography licenses are centrally managed in VMS. Within VMS, optionally turn on licensed FIPS cryptography on cameras. VMS inventories the number of FIPS camera licenses being used and determines whether customers have the required number of licenses within a facility.
j) The NVMS shall operate on a TCP/IP managed digital network.
k) The system software shall operate in a Client/Server configuration across a Local Area Network (LAN) or Wide Area Network (WAN).
l) Streams live and recorded video up to 60 frames per second.
m) Support prioritizing streaming at 30 frames per second on 4K (8MP) cameras.
n) Streams live and recorded video from cameras up to a resolution of 7K
(30 MP) — 6720 x 4488.
o) Decompresses H.264 and/or H.265 video through the client graphics card to help leverage the client’s total processing power.
p) Scalable to support up to 100 servers and/or 10,000 cameras per site.
q) All recorded video and audio are digitally signed using 256-bit encryption so video can be authenticated for evidentiary purposes.
r) Secure video and audio data by securely transmitting all command-and-control data via TCP/IP using cryptographic keys based on SSL to prevent eavesdropping or tampering.
s) External system alarms can be pre-selected and configured to be monitored and trigger event driven video operations.
t) Video and audio recording can be defined by a recording schedule assigned to each video source.
u) Recording schedules are based on event types that trigger video recording over a time period each day per week.
AM0002 Page 20 of 94
For Official Use Only (FOUO) 13
v) Video recording can also occur manually by user triggered recording.
w) Alarms and rules can be triggered by self-learning video analytics-based events.
x) Each recorded event includes a pre-event and post-event recording option to provide context for a given situation.
y) Reference frame recording is an option when no events are detected.
z) Motion detection is provided for each individual video source with adjustable sensitivity, threshold, and detection zones.
aa) Primary and secondary video streams from each H.264 and/or H.265 video source is recorded and maintained for a set amount of time before the primary stream is discarded as a means of increasing record time.
bb) The maximum recorded video retention time can be set for each video source.
cc) The Video Analytics Activity overlay displays a color-coded bounding box around moving objects categorized as humans or vehicles.
dd) Configure the ability to display analytics activity for individual cameras or for the system.
ee) The ability to stream video and audio is limited only by the system hardware capabilities.
ff) The application window display can be shared with other users for collaborative investigations while viewing both live and recorded video.
gg) Live and recorded video and audio can be streamed simultaneously on the same monitor.
hh) Use High-Definition Stream Management (HDSM) software technology to efficiently compress and preserve image quality while intelligently managing HD image transmission throughout the system.
ii) Operating System shall be certified to work by the Video Management Software’s manufacturer and be one of the following: Windows Server 2010 or newer.
jj) Windows 10 or newer.
kk) Support recording and management of video and audio sources using industry standard drivers. These drivers shall include: ONVIF Profile S, T and G Publicly Published API.
ll) Support the following video analytic event types when captured by supported cameras: Objects in area, object loitering’ objects crossing defined line, object appears or enters area, object not present in area, objects enter area, objects leave area, object stops in area, anticipated direction of travel is violated, scene dramatically changes in an unexpected fashion.
mm) Support the ability to export media and provide the following options.
nn) Export recorded video in the following formats: Native (AVE), JPEG, PNG, TIFF, AVI, Print. Export recorded audio in the following formats:
WAV, Native (AVE), AVI. Export a still frame of video as displayed in the video preview area: Native (AVE), JPEG, PNG, TIFF.
oo) Native (AVE) format exports shall:
pp) Digitally sign recorded video and audio using 256-bit encryption so video can be authenticated for evidentiary purposes.
AM0002 Page 21 of 94
For Official Use Only (FOUO) 14
qq) Be able to export video from one or multiple camera streams simultaneously.
rr) Support exporting multiple video segments from different spans of time.
ss) Support reviewing of exported or backed-up video and audio in a dedicated player.
tt) Support playback of exported clips in synchronized sequential time.
uu) Support playback of multiple clips in continuous, sequential order.
vv) Support exporting of video in lower frame-rates than originally recorded.
ww) Support exporting of a designated area from the camera’s recorded field of view.
xx) Support re-export into Native or other supported formats.
yy) Provide a record of the video source properties, including but not limited to:
Camera model, Firmware version, Location, MAC address, Serial number, Resolution.
D.1.7 All components/equipment licensing fees for the newly installed NVMS shall be nonrecurring.
D.2 Minimum Server and Workstation Requirements
Network Video Management Server Minimum Requirements
CPU Intel Core i7 or newer OS Windows Server or newer 64bit
RAM 16 GB
OS Hard Drive SSD RAID Mirrored Network Interface 1GB Display Adaptor DVI, HMDI Storage Configuration RAID 6 Power Supply Dual redundant hot swappable Drives Hot Swappable Warranty 5-year Warranty
AM0002 Page 22 of 94
For Official Use Only (FOUO) 15
Multimedia Storage Requirements
General • Multimedia storage shall be dedicated for archiving
• Archiving shall be physically separated from
OS/DB drives
• OS/DB and Archive drive may be housed in the same chassis
• Archive drives RAID 6 configuration
Total Storage Capacity Shall be calculated by the Contractor based on the requirements of the SOW. All calculations shall be provided with quotation.
Workstation Minimum Requirements
CPU Intel Core i7 or newer OS Windows 10 Pro or newer 64 bit
RAM 16 GB DDR3
OS Hard Drive SSD RAID Mirrored Network Interface 1GB Display Adaptor VGA, DVI, HDMI dual monitor support
D.3 IP Network Video Camera Minimum Requirements
D.3.1 At a minimum, equal or better than Avigilon Exterior PTZ 8MP IP Camera: The
FPS Local POC shall determine the field-of-view (FoV) for each camera with the Contractor, at the time of installation.
a) ONVIF Compliant Profile S, Profile T and Profile G
b) Operate in a temperature range of -40 deg C to +60 deg C (-40 deg F to +140 deg F)
c) Operate in a humidity range of 0-95% RH (non-condensing)
d) High Definition Stream Management
e) Multi-stream H.264, Multi-stream H.265, Motion JPEG.
f) Video Resolution: 8 MP
g) IPv4/IPv6, HTTP, HTTPS, SOAP,DNS,NTP, RTSP, RTCP, RTP, TCP,UDP, IGMP, ICMP, DHCP, Zeroconf, ARP,HSTS
h) Environmental rating IP66 and IP67
i) Impact rating IK10
j) Video Pattern Detection and Teach by Example Technology
k) Password protection, HTTPS encryption, digest authentication, WS
AM0002 Page 23 of 94
For Official Use Only (FOUO) 16 authentication, user access log, 802.1x port based authentication, FIPS 140-2 L1 (with optional camera license), FIPS 140-2 L3 (with optional accessory)
l) 5-year warranty
D.3.2 At a minimum, equal or better than Avigilon 180/270/360-degree Exterior/Interior IP Panoramic Camera: verify the panoramic camera is compatible with the video management system software to ensure full functionality of the camera.
a) 180/270/360 degree panoramic
b) Wide Dynamic Range Panoramic
c) 3 or 4 sensors (cameras) within the housing
d) Lens: 2.8mm f1.2-103° , 4mm f1.6-72°, Remote Focus; 4mm f1.8-
101°, 5.2mm f1.8-70° Remote Focus
e) Image Compression: H.264 HDSM Smartcodec or H.265 HDSM
SmartCodec or Motion JPEG
f) Outdoor Rated IP66 and IK-10 Impact-Resistant Housing
g) Self learning video analytics on all sensors
h) Content adaptive IR technology up to 30m (100ft)
i) 3D Noise Reduction Filter
j) 8 MP per sensor resolution
D.3.3 At a minimum, equal or better than Avigilon Interior/Exterior Fixed 4 MP
IP Camera: The FPS Local POC shall determine the field-of-view (FoV) for each camera with the Contractor, at the time of installation.
a. ONVIF Compliant Profile S and Profile G
b. Operate in a temperature range of -25 deg C to +60 deg C (-13 deg F to
+140 deg F)
c. Operate in a humidity range of 0-95% RH (non-condensing)
d. High Definition Stream Management
e. Multi-stream H.264, Multi-stream H.265, Motion JPEG;
f. Video Resolution: 61 MP
g. IPv4/IPv6, HTTP,HTTPS, SOAP,DNS,NTP, RTSP, RTCP, RTP, TCP,UDP, IGMP, ICMP,DHCP, Zeroconf, ARP,HSTS
h. Environmental rating IP66,
i. PoE: IEEE802.3at Class 4 compliant
j. Teach by Example Technology
k. Password protection, HTTPS encryption, digest authentication, WS authentication, user access log, 802.1x port based authentication, FIPS 140-2 L1 (with optional camera license), FIPS 140-2 L3 (with optional accessory)
l. 5 year warranty
AM0002 Page 24 of 94
For Official Use Only (FOUO) 17
D.3.3.1
D.4 Network Managed Switch
a) Physical Aspects <Apply appropriate specifications>
(1) 24 auto-sensing RJ45 10/100/1000 ports; Layer 3 managed
(2) 4 SFP ports 100/1000
(3) Serial DB9 RS-232 console port
(4) Rack Mountable
b) Power over Ethernet (PoE)
(1) 24 PoE+ ports
(2) IEEE 802.3at (up to 30 Watts/port)
D.5 Additional System Component, software,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .