Statement of Work 1-12-22 Thomasville FRC UPS Replacement.pdf
PDF 212 KB Posted
- Attached to
- Amendment 0001-UPS System Replacement Federal contract opportunity
- Solicitation number
- 70FBR422Q00000020
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001_70FBR422R00000006_signedVB.pdf | ||
| 70FBR422Q00000006 - Questions 1-20-2022.pdf | ||
| SAM.gov - Wage Determination.pdf | ||
| Access Request Form.pdf | ||
| Solicitation 70FBR422R00000006 - SF1442.pdf | ||
| Project Experience Questionnaire_Fillable_rev1.pdf | ||
| 70FBR422R00000006 - PHOTOS - Thomasville UPS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
FEMA FRC UPS System Replacement, Thomasville, Ga.
1/12/2022
PURPOSE: Replace existing 80KVA 480V UPS system with a new 80KVA UPS System with a capacity of a minimum 15 minutes of backup power.
SCOPE:
• Replacement of the current failed GE Model SG 80KVA 208Y/120V UPS System with a new 80KVA UPS System
• Installation of (1) wrap around maintenance bypass panel to include (1) Tie Maintenance bypass breaker (MIS Breaker)
• Reuse existing UPS battery cabinet and batteries that were installed new on 10/29/2021 if compatible with new UPS system that is being proposed. Batteries must provide a minimum of 15 minutes of battery run time at current load plus 15%.
• Vendor shall complete all electrical connections between existing electrical distribution panels and the new UPS and Maintenance Bypass cabinet in accordance with all National Electrical Codes.
• Vendor shall commission all functions of the UPS System upon completion of the installation and provide a full commissioning report of the new UPS and maintenance bypass.
• Removal and disposal of existing UPS to include disposal of UPS batteries and cabinet if not compatible with UPS system that is being proposed for consideration.
• Provide detailed procedures for switching from “Normal” operation to a “Maintenance Bypass” mode of operation.
• Provide (1) year warranty to include labor and parts for the first year that shall begin upon the date of acceptance of the completed project.
• Provide a line item option for all manufacturer recommended maintenance of the UPS System to include any battery maintenance and testing of the existing batteries.
BACKGROUND: Existing UPS System has failed, and the critical frame room is on currently running on Utility power until the UPS can be replaced. The existing system has a new battery cabinet and batteries installed on 10/29/2021 that could possibly be reused to mitigate additional cost if they are compatible with a new UPS system. Current UPS configuration does not currently have a maintenance bypass cabinet to allow for the system to switch to normal utility power for maintenance/repairs.
Note: It is highly recommended that all vendors visit the site to view the current UPS System, existing batteries and cabinet, existing electrical distribution and what will be needed to install a new UPS System to the existing electrical distribution gear.
• CONSTRAINTS: Workers must submit Facilities Access Forma and be able to pass a federal background check to obtain access to federal facilities to perform any work on the premises. Scheduling to be coordinated and completed during normal business hours (8:00 AM – 4:30 PM) Monday
– Friday.
• DELIVERABLE SCHEDULE:
The government expects that a following deliverable schedule (or better) will be followed in delivering this SOW. The cumulative days mentioned below are business days, not calendar days.
Task Deliverables Expected Completion Timeframe
1 Provide quote for UPS replacement to include a maintenance bypass cabinet with MIS breaker per requirements listed in the SOW.
30 Days following initial posting
2 Complete removal of existing UPS and installation of the replacement
UPS.
90 Days following acceptance of contract award
3 Provide a minimum of 1 year warranty (parts and labor) from date of completion and commissioning.
Upon Completion of Installation and commissioning
• PERIOD OF PERFORMANCE:
The period of performance for this task order will begin on award and terminate 90 days from acceptance of the contract award.
• CONTRACTOR STAFFING PLAN AND KEY PERSONNEL:
[Each offeror should submit a staffing plan for achieving the
SOW…]
Note: All personnel must submit a Facility Access Request (see attached) and pass a federal background check prior to being allowed on site to perform any work.
Region-IV Facility Access Request Form
| SCOPE: |
| Replacement of the current failed GE Model SG 80KVA 208Y/120V UPS System with a new 80KVA UPS System |
| Installation of (1) wrap around maintenance bypass panel to include (1) Tie Maintenance bypass breaker (MIS Breaker) |
| Reuse existing UPS battery cabinet and batteries that were installed new on 10/29/2021 if compatible with new UPS system that is being proposed. Batteries must provide a minimum of 15 minutes of battery run time at current load plus 15%. |
| Vendor shall complete all electrical connections between existing electrical distribution panels and the new UPS and Maintenance Bypass cabinet in accordance with all National Electrical Codes. |
| Vendor shall commission all functions of the UPS System upon completion of the installation and provide a full commissioning report of the new UPS and maintenance bypass. |
| Removal and disposal of existing UPS to include disposal of UPS batteries and cabinet if not compatible with UPS system that is being proposed for consideration. |
| Provide detailed procedures for switching from “Normal” operation to a “Maintenance Bypass” mode of operation. |
| Provide (1) year warranty to include labor and parts for the first year that shall begin upon the date of acceptance of the completed project. |
| Provide a line item option for all manufacturer recommended maintenance of the UPS System to include any battery maintenance and testing of the existing batteries. |
| BACKGROUND: Existing UPS System has failed, and the critical frame room is on currently running on Utility power until the UPS can be replaced. The existing system has a new battery cabinet and batteries installed on 10/29/2021 that could possibly be ... |
| CONSTRAINTS: Workers must submit Facilities Access Forma and be able to pass a federal background check to obtain access to federal facilities to perform any work on the premises. Scheduling to be coordinated and completed during normal business hou... |
| DELIVERABLE SCHEDULE: |
| PERIOD OF PERFORMANCE: |
| CONTRACTOR STAFFING PLAN AND KEY PERSONNEL: [Each offeror should submit a staffing plan for achieving the SOW…] |