Statement of Work 1-12-22 Thomasville FRC UPS Replacement.pdf

PDF 212 KB Posted

Attached to
Amendment 0001-UPS System Replacement Federal contract opportunity
Solicitation number
70FBR422Q00000020
Issued by
Federal Emergency Management Agency Region 4

View the file

Other files for this federal contract opportunity

Other files attached to Amendment 0001-UPS System Replacement, newest first.
File Type Posted
Amendment 0001_70FBR422R00000006_signedVB.pdf PDF
70FBR422Q00000006 - Questions 1-20-2022.pdf PDF
SAM.gov - Wage Determination.pdf PDF
Access Request Form.pdf PDF
Solicitation 70FBR422R00000006 - SF1442.pdf PDF
Project Experience Questionnaire_Fillable_rev1.pdf PDF
70FBR422R00000006 - PHOTOS - Thomasville UPS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

FEMA FRC UPS System Replacement, Thomasville, Ga.

1/12/2022

PURPOSE: Replace existing 80KVA 480V UPS system with a new 80KVA UPS System with a capacity of a minimum 15 minutes of backup power.

SCOPE:

• Replacement of the current failed GE Model SG 80KVA 208Y/120V UPS System with a new 80KVA UPS System

• Installation of (1) wrap around maintenance bypass panel to include (1) Tie Maintenance bypass breaker (MIS Breaker)

• Reuse existing UPS battery cabinet and batteries that were installed new on 10/29/2021 if compatible with new UPS system that is being proposed. Batteries must provide a minimum of 15 minutes of battery run time at current load plus 15%.

• Vendor shall complete all electrical connections between existing electrical distribution panels and the new UPS and Maintenance Bypass cabinet in accordance with all National Electrical Codes.

• Vendor shall commission all functions of the UPS System upon completion of the installation and provide a full commissioning report of the new UPS and maintenance bypass.

• Removal and disposal of existing UPS to include disposal of UPS batteries and cabinet if not compatible with UPS system that is being proposed for consideration.

• Provide detailed procedures for switching from “Normal” operation to a “Maintenance Bypass” mode of operation.

• Provide (1) year warranty to include labor and parts for the first year that shall begin upon the date of acceptance of the completed project.

• Provide a line item option for all manufacturer recommended maintenance of the UPS System to include any battery maintenance and testing of the existing batteries.

BACKGROUND: Existing UPS System has failed, and the critical frame room is on currently running on Utility power until the UPS can be replaced. The existing system has a new battery cabinet and batteries installed on 10/29/2021 that could possibly be reused to mitigate additional cost if they are compatible with a new UPS system. Current UPS configuration does not currently have a maintenance bypass cabinet to allow for the system to switch to normal utility power for maintenance/repairs.

Note: It is highly recommended that all vendors visit the site to view the current UPS System, existing batteries and cabinet, existing electrical distribution and what will be needed to install a new UPS System to the existing electrical distribution gear.

• CONSTRAINTS: Workers must submit Facilities Access Forma and be able to pass a federal background check to obtain access to federal facilities to perform any work on the premises. Scheduling to be coordinated and completed during normal business hours (8:00 AM – 4:30 PM) Monday

– Friday.

• DELIVERABLE SCHEDULE:

The government expects that a following deliverable schedule (or better) will be followed in delivering this SOW. The cumulative days mentioned below are business days, not calendar days.

Task Deliverables Expected Completion Timeframe

1 Provide quote for UPS replacement to include a maintenance bypass cabinet with MIS breaker per requirements listed in the SOW.

30 Days following initial posting

2 Complete removal of existing UPS and installation of the replacement

UPS.

90 Days following acceptance of contract award

3 Provide a minimum of 1 year warranty (parts and labor) from date of completion and commissioning.

Upon Completion of Installation and commissioning

• PERIOD OF PERFORMANCE:

The period of performance for this task order will begin on award and terminate 90 days from acceptance of the contract award.

• CONTRACTOR STAFFING PLAN AND KEY PERSONNEL:

[Each offeror should submit a staffing plan for achieving the

SOW…]

Note: All personnel must submit a Facility Access Request (see attached) and pass a federal background check prior to being allowed on site to perform any work.

Region-IV Facility Access Request Form

SCOPE:
Replacement of the current failed GE Model SG 80KVA 208Y/120V UPS System with a new 80KVA UPS System
Installation of (1) wrap around maintenance bypass panel to include (1) Tie Maintenance bypass breaker (MIS Breaker)
Reuse existing UPS battery cabinet and batteries that were installed new on 10/29/2021 if compatible with new UPS system that is being proposed. Batteries must provide a minimum of 15 minutes of battery run time at current load plus 15%.
Vendor shall complete all electrical connections between existing electrical distribution panels and the new UPS and Maintenance Bypass cabinet in accordance with all National Electrical Codes.
Vendor shall commission all functions of the UPS System upon completion of the installation and provide a full commissioning report of the new UPS and maintenance bypass.
Removal and disposal of existing UPS to include disposal of UPS batteries and cabinet if not compatible with UPS system that is being proposed for consideration.
Provide detailed procedures for switching from “Normal” operation to a “Maintenance Bypass” mode of operation.
Provide (1) year warranty to include labor and parts for the first year that shall begin upon the date of acceptance of the completed project.
Provide a line item option for all manufacturer recommended maintenance of the UPS System to include any battery maintenance and testing of the existing batteries.
BACKGROUND: Existing UPS System has failed, and the critical frame room is on currently running on Utility power until the UPS can be replaced. The existing system has a new battery cabinet and batteries installed on 10/29/2021 that could possibly be ...
CONSTRAINTS: Workers must submit Facilities Access Forma and be able to pass a federal background check to obtain access to federal facilities to perform any work on the premises. Scheduling to be coordinated and completed during normal business hou...
DELIVERABLE SCHEDULE:
PERIOD OF PERFORMANCE:
CONTRACTOR STAFFING PLAN AND KEY PERSONNEL: [Each offeror should submit a staffing plan for achieving the SOW…]