70FBR422Q00000006 - Questions 1-20-2022.pdf
PDF 203 KB Posted
- Attached to
- Amendment 0001-UPS System Replacement Federal contract opportunity
- Solicitation number
- 70FBR422Q00000020
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0001_70FBR422R00000006_signedVB.pdf | ||
| Solicitation 70FBR422R00000006 - SF1442.pdf | ||
| Project Experience Questionnaire_Fillable_rev1.pdf | ||
| Statement of Work 1-12-22 Thomasville FRC UPS Replacement.pdf | ||
| 70FBR422R00000006 - PHOTOS - Thomasville UPS.pdf | ||
| SAM.gov - Wage Determination.pdf | ||
| Access Request Form.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions received as of 1/20/2022:
# Page Section Section Description Vendor Question
1. General
How many volumes are required for proposal submission? Section L doesn’t mention volumes, but Section M suggests that there are 3 separate volumes?
RESPONSE: There is no such “volume” mentioned in this Solicitation; Section M refers to Evaluation factors of 1. Technical, 2.
Past Performance, and 3. Price.
2. 32 M 1.Technical -
Will the government please provide a detailed outline of the items required for the Technical volume of this proposal? –
RESPONSE: There is no such “volume” mentioned in this Solicitation; refer to the Submission of Proposals and prepare according to what is described.
3. 32 M 1.Technical - Is there a page count requirement for the Technical volume? –
RESPONSE: There is no such “volume” mentioned in this Solicitation; there is no required page count.
4. 32 M 2. Past Performance
Is the Project Experience Questionnaire required to be included as part of the Past Performance volume? –
RESPONSE: There is no such “volume” mentioned in this Solicitation. Past performance is required as stated.
5. 32 M 2. Past Performance
Will the government please provide a detailed outline of what is required to be included in the Past Performance Volume?
RESPONSE: There is no such “volume” mentioned in this Solicitation; follow what is detailed on the past performance Project Experience Questionnaire.
6. 32 M 2. Past Performance Is there a page count requirement for the Past Performance volume?
RESPONSE: There is no such “volume” mentioned in this Solicitation; no page count required.
7. 32 M 3. Price
Will the government please provide a detailed outline of what is required to be included in the Price Volume?
RESPONSE: There is no such “volume” mentioned in this Solicitation; Price must include a detailed breakout of costs as specified in Section L of the solicitation
8. 32 M 3. Price
Should the contractor include the contract documents (i.g. SF1442 or Section K) as part of the Price volume?
RESPONSE: There is no such “volume” mentioned in this Solicitation; you must submit your documentation in accordance with the instructions included in the Solicitation.
9. General How should the proposal response be submitted to the responsible party, via email or DOD safe link? –
RESPONSE: Via email to the POCs listed.
10. 1-4 A Solicitation/Contract Form
Does the government want the contractor to provide a lump sum amount on page 2 and page 4 of the contract form?
RESPONSE: Yes. NOTE: A complete breakout of costs should be submitted separately according to the terms and conditions.
11. Project Experience Questionnaire
How many extra pages can we include for the description of each project?
RESPONSE: There is no page limit.
12. Project Experience Questionnaire
Can the Prime contractor use Past performance examples of project performed by major subcontractors/team members?
RESPONSE: No. Must be work performed by the Prime contractor.
A. The spec calls out 480 and 208V in different sections. Please verify the voltage.
B. Information on the current battery system
1. buss voltage – Response: see attached photo
2. battery model number - Response: see attached photo
3. current battery over current in the cabinets - Response: will be answered during the site visit.
4. what type of trip on the battery breaker: UVR , shunt trip … Response: will be answered during the site visit.