70153 - Texarkana GSA Elevator Modernization - signed SOW - AR0057ZZ.pdf
PDF 375 KB Posted
- Solicitation number
- 47PH0522R0028
About this file
This document outlines a federal solicitation for elevator modernization services at the Texarkana Post Office and United States Courthouse in Texarkana, Texas. The General Services Administration is seeking proposals to modernize two elevators at the facility in accordance with the attached statement of work, which provides details on the project scope, schedule, and requirements. Interested contractors must attend an optional pre-proposal site visit on April 13, 2022 and submit proposals by May 2, 2022. Proposals will be evaluated based on technical approach, experience, schedule, past performance, and preventative maintenance approach. The contract is to be completed within 550 calendar days of the notice to proceed and liquidated damages of $250 per day will be assessed for delays beyond the substantial completion date. The magnitude of the project is estimated between $1,000,000 to $5,000,000. Davis Bacon wage rates apply and the selected contractor must provide a 120-day guarantee on all work performed. A single award will be made from this solicitation.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration Public Buildings Service
Greater Southwest Region
1 Last updated 8/13/2021
December 13, 2021
Construction Scope of Work
1. Project Title: GSA Elevator Modernization, Texarkana, TX (ePM 70153)
2. Project Location: TX0057ZZ Texarkana Post Office Courthouse 500 State Line Texarkana, TX, 71854
3. Building Location Hours: Every attempt must be made to ensure normal building operations are not interrupted. Operating hours for this facility are from 6:00 AM to 6:00 PM, Monday thru Friday.
Coordination and approval from GSA COR is required for work performed other than normal hours. Any disruptive work, (i.e. noise, demolition of existing equipment, etc. is to be performed during other than normal working hours. Notify Project Manager and Building Manager of any work that may cause disruption during the day. If work after hours needs to be accomplished the Project Manager must be notified a minimum of 72 hours in advance.
4. Pre-bid Site Visit: Site visits shall be conducted to allow prospective bidders the opportunity to see onsite conditions. COVID guidance from CDC and local building operation procedures must be adhered to during the Pre-Bid site visit. Site visits shall be conducted with a maximum of 10 people present to prevent exposure to and spread of the COVID-19 virus. If necessary, multiple site visits will be scheduled to accommodate prospective bidders.
5. Purpose: Modernize Two (2) existing Simplex (or equivalent) operation, traction Passenger elevators. Provide: AC motor, machine, solid state microprocessor controls, cab, doors, and all associated work to provide two complete new passenger elevators. All work performed under this contract shall meet or exceed the latest ASME-A17.1 Elevator Code and the Uniform Federal Accessibility Standards.
6. Points of Contact:
6.1 Contracting Officer: Paul Shirlee
819 Taylor Street, Room 12B Fort Worth, TX 76102 Phone: 817-564-8715
6.2 Project Manager: Lauren Young
200 N 4th Street, Suite 4050 Oklahoma City, OK, 73102 Phone: 405-443-5269
DocuSign Envelope ID: 43C9C108-BA36-4249-AD19-B9E5902DD47D
2 Last updated 8/13/2021
6.3 Property Manager: Richard Carlson
211 W Ferguson Street
TYLER, TX, 75702-7220
Phone: 903 245-5826
6.4 Other: R7 Security Clearance Coordinators
r7clearance@gsa.gov
7. Notice to Proceed:
7.1 The Contracting Officer is the ONLY individual from the Government that can give the contractor a notice to proceed.
7.2 Before any of the work within the scope of the contract is started, the Contractor shall confer with the COR (Contracting Officer’s Representative) and agree on a sequence of procedure; means of access to premises and building; delivery of material and use of approaches; use of corridors, stairways, elevators, and similar means of communications;
and the location partitions, eating spaces for Contractor’s employees and the like.
7.3 After a Notice to Proceed is given the Contractor has 7 days to provide a schedule.
8. Period of Performance: The total period of performance for this task order is 550 days, which includes 45 calendar days for required security clearances, pre-work submittals, and material ordering. Actual construction period of performance is 505 calendar days.
8.1 Contractor must initiate the fitness determination process (security clearance) within 10 days of Zone B HSPD-12 instructional email.
9. Description of Work: Contractor shall provide all materials, labor, tools, equipment and daily supervision to accomplish tasks as outlined in contract documents. Contractor is also responsible for all necessary safety measures.
9.1 Division 1 General Requirements
9.1.1 Work Sequence - Provide critical path method schedule
9.1.2 Daily clean up - All work space, staging areas, areas used for moving materials, trash, tools, etc. are to be kept clean at all times. All trash from the day’s work is to be removed and the work site clean and orderly.
9.1.3 Protection - Contractor is responsible for protection of existing finishes, utilities, etc.
in the facility, and must maintain a separation of work area from adjacent spaces.
Site is to be secured at the end of day. The Contractor shall be responsible for the security of the work site.
9.1.4 All work performed for the passenger elevator shall conform to specification number 14210 (See Attachment 2: SPEC 14210)
9.1.5 Progress Meetings/Calls - Contactor shall be responsible for providing an updated agenda, RFI and Submittal Log no later than 24 hours before the Progress Call or Meeting, and shall provide Minutes no later than 48 hours after the Progress Call or Meeting. Agenda content and Log format shall be reviewed and approved by the PM. A monthly call including relevant stakeholders until the project begins work.
mailto:r7clearance@gsa.gov
3 Last updated 8/13/2021
Once work begins calls will be twice per month including relevant stakeholders.
9.2 Division 2 -13 not used
9.3 Division 14: Conveying Equipment
9.3.1 Reference conveying equipment requirements in SPEC 14210 (See Attachment 2).
9.4 Division 15-33 not used
10. Liquidated Damages: $250.00 per day may be assessed by the Contracting Officer each day past the substantial completion date and will be deducted from the contractor’s final payment application.
11. Sustainability:
11.1 Green Purchasing: See Appendix 1: Green Purchasing Requirements
11.2 Waste Diversion: Fourteen days from Notice to Proceed, the Contractor shall submit to the
Project Manager an updated Non-Hazardous Solid Waste Management Plan (Attachment 1: Waste Diversion Plan), to include (not limited to):
a) List of materials Contractor will reuse
b) List of materials the Contractor will donate and name and address of donation recipient.
c) List of materials the Contractor will recycle and the name and address of the recycler. If Contractor receives recycling revenue, Contractor shall keep revenue and provide receipt for GSA for reference.
d) Name and location of solid waste landfill for non-diverted material.
12. Other Requirements:
12.1 Purchase of Equipment
12.2 Building Specific Requirements
12.2.1 Parking: Space for one contactor vehicle, on the west side of the buildings, allowing access to the basement.
12.2.2 Building Specific Access Requirements: HSPD12 cleared, and have a photo badge for each contractor.
12.2.3 After-Hours Coordination: Property Manager and Project Manager will assist with after-hours coordination (access requirements are subject to change)
12.2.4 Loading Dock Use (During Duty & After-Hours): Property Manager will assist with loading dock access.
12.2.5 Common Area Cleaning: Contractor will clean up their work areas at the end of each day.
12.2.6 Utility Outages: Contractor will need to provide the Property Manager and Project Manager 2 weeks notice in advance of a utility outage request.
12.2.7 Hot Work Permits: The Contractor will need to give 2 days notice to the Property Manager and Project Manager when a Hot Work Permit is required.
12.2.8 Key Control: One key for the elevator mechanical room will be provided by the Property Manager to the contractor and must be returned once the work is completed.
4 Last updated 8/13/2021
13. Submittals:
13.1 Submittal Log - List of Submittals
13.2 Critical Path Method Gantt Schedule that accounts for potential impacts.
13.3 Waste Diversion Submittal: Preconstruction (See Attachment 1)
13.4 Waste Diversion Submittal: Post Construction (See Attachment 1)
13.5 Green Purchasing items
13.6 Reference submittal requirements in (See Attachment 2: SPEC 14210)
13.7 Safety Plan
14. Attachments:
14.1 Attachment 1: Waste Diversion Plan
14.2 Attachment 2: SPEC 14210
15. Closeout Plan:
15.1 Final Punch list complete
15.2 Customer Acceptance
15.3 Close Out Documents (O&M Manuals, Warranty, Certified payrolls, Release of Claims, Waste Diversion documentation (See Attachment 1), and any requirements in SPEC 14210 (See Attachment 2))
15.4 All Government Furnished Equipment and Property returned including, but not limited to:
GSA PIV cards, Building keys, Government IT equipment, etc.
15.5 SBU/CUI Documentation - Reference Paragraph III.N in base contract
15.5.1 Provide list of all entities to which SBU/CUI is disseminated
15.5.2 Provide notification SBU/CUI has been returned or destroyed
15.6 Final Payment - CO may withhold payment until all Closeout items are received.
END OF SOW
5 Last updated 8/13/2021
GSA Project Manager Date
GSA Supervisory Project Manager Date
GSA Building Manager Date
GSA Subject Matter Expert Date
1/13/2022
1/13/2022
1/18/2022
1/14/2022
6 Last updated 8/13/2021
Appendix 1: Green Purchasing Requirements
Sustainability:
● Green Purchasing:
o The contractor shall refer to the “Green Procurement Compilation” for all products being installed in federal facilities. The Green Procurement Compilation can be found at https://sftool.gov/greenprocurement. The standards found in this compilation shall guide all product purchasing decisions as they relate to federal facilities.
o The use of the following standards (“Key Sustainable Product” or “KSP” standards) is mandatory for all contracts and task orders. See https://sftool.gov/green-products/1037/key-sustainable-products for more details.
▪ Nylon Carpet: NSF-140 Platinum or Cradle to Cradle Bronze.
▪ Resilient Flooring (e.g. vinyl and linoleum): NSF-332 (any level) or Cradle to
Cradle (any level)
▪ Interior Latex Paint: Master Painters Institute (MPI) Extreme Green or Green
Seal 11.
▪ Acoustical Ceiling Tiles: > 15% post-consumer recycled content.
▪ Water-Consuming Equipment: WaterSense Certified.
A. For each KSP listed, the Contractor shall submit proof of compliance to the CO or his designee prior to the installation of the product or material. The CO’s designee shall verify compliance.
B. If the KSP materials listed above are 1) not reasonably available within a reasonable period of time; 2) fail to meet the performance standards set forth in the specification or fail to meet reasonable performance standards of GSA; or 3) are available only at an unreasonable price, only then can the Contractor use other types of products. In these cases the Contractor shall select products and materials, to the extent possible, which are the safest and most environmentally friendly. Exemptions must be submitted in writing and can only be approved by the CO.
Certificate Of Completion Envelope Id: 43C9C108BA364249AD19B9E5902DD47D Status: Completed
Subject: Please DocuSign: 70153 - Texarkana GSA Elevator Modernization - Construction SOW- AR0057ZZ.pdf
Source Envelope:
Document Pages: 6 Signatures: 4 Envelope Originator:
Certificate Pages: 2 Initials: 0 Lauren Young
AutoNav: Enabled
EnvelopeId Stamping: Enabled
Time Zone: (UTC) Dublin, Edinburgh, Lisbon, London
1800F F St NW
Washington DC, DC 20405 lauren.j.young@gsa.gov
IP Address: 159.142.0.111
Record Tracking Status: Original
1/13/2022 9:43:43 PM
Holder: Lauren Young lauren.j.young@gsa.gov
Location: DocuSign
Security Appliance Status: Connected Pool: FedRamp
Storage Appliance Status: Connected Pool: US General Services Administration Location: DocuSign
Signer Events Signature Timestamp Jeff Chiavetta jeff.chiavetta@gsa.gov
Supervisory Project Architect
US General Services Administration
Security Level: Email, Account Authentication (None)
Signature Adoption: Pre-selected Style
Using IP Address: 159.142.0.111
Sent: 1/13/2022 9:52:35 PM
Viewed: 1/13/2022 10:09:25 PM
Signed: 1/13/2022 10:09:31 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Lauren Young lauren.j.young@gsa.gov
Security Level: Email, Account Authentication (None)
Signature Adoption: Pre-selected Style
Using IP Address: 159.142.0.111
Sent: 1/13/2022 9:52:35 PM
Viewed: 1/13/2022 9:52:44 PM
Signed: 1/13/2022 9:52:49 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
RICHARD D CARLSON
richardd.carlson@gsa.gov
US General Services Administration
Security Level: Email, Account Authentication (None) Signature Adoption: Pre-selected Style
Using IP Address: 159.142.71.4
Sent: 1/13/2022 9:52:36 PM
Resent: 1/18/2022 4:39:30 PM
Viewed: 1/18/2022 5:04:18 PM
Signed: 1/18/2022 5:04:48 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
Scott Cumby scott.cumby@gsa.gov
US General Services Administration
Security Level: Email, Account Authentication (None) Signature Adoption: Pre-selected Style
Using IP Address: 159.142.0.105
Sent: 1/13/2022 9:52:36 PM
Viewed: 1/14/2022 9:36:14 PM
Signed: 1/14/2022 9:37:07 PM
Electronic Record and Signature Disclosure:
Not Offered via DocuSign
In Person Signer Events Signature Timestamp
Editor Delivery Events Status Timestamp
Agent Delivery Events Status Timestamp
Intermediary Delivery Events Status Timestamp
Certified Delivery Events Status Timestamp
Carbon Copy Events Status Timestamp
Witness Events Signature Timestamp
Notary Events Signature Timestamp
Envelope Summary Events Status Timestamps Envelope Sent Hashed/Encrypted 1/13/2022 9:52:36 PM
Certified Delivered Security Checked 1/14/2022 9:36:14 PM
Signing Complete Security Checked 1/14/2022 9:37:07 PM
Completed Security Checked 1/18/2022 5:04:48 PM
Payment Events Status Timestamps
| 2022-01-18T09:09:37-0800 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .