7. Schedule of Values.pdf

PDF 138 KB Posted

Attached to
129JGP20R0050 - LTBMU Bike Trail Construction
Solicitation number
129JGP20R0050
Issued by

About this file

This document contains a schedule of values and bid items for a federal construction contract. The schedule lists estimated quantities, unit prices, and total costs for various construction items across two sites. Work at Site 1 includes mobilization, surveying, excavation and embankment, minor crushed aggregate installation, culvert installation, and rock slope protection. Work at Site 2 involves similar items - mobilization, excavation and embankment, aggregate base installation, and asphalt paving. The total proposed cost is to be provided.

The related federal opportunity is a solicitation from the USDA Forest Service Pacific Southwest Region for bike trail construction within the Lake Tahoe Basin Management Unit with an estimated value between $100,000 and $250,000. Requests for information are due by August 14, 2020. Bidders are expected to visit the site independently.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION B – SCHEDULE OF ITEMS

ITEM DESCRIPTION UNIT EST. UNIT TOTAL

NO. QTY. PRICE COST

BASE BID ITEMS (Site 1)

1 15101 ‐ Mobilization LS 1 $ $

15201 ‐ Construction Survey, Method II, Tolerance Class B

LS 1 $ $

20401 ‐ Excavation and Embankment, Placement Method 2 (2)

CY 1645 $ $

302 ‐ Minor Crushed Aggregate, Grading E, Compaction Method 1

LF 2525 $ $

5 60205 ‐ 36” DIA X 50’ Culvert LS 1 $ $

6 70502 ‐ Rock Slope Protection, Class 1 TN 75 $ $

Base Bid Items (Site) 1: Sub‐Total $

BASE BID ITEMS (Site 2)

7 15101 ‐ Mobilization LS 1 $ $

20401 ‐ Excavation and Embankment, Placement Method 2 (2)

LF 600 $ $

30102 ‐ Aggregate base, CalTrans ¾” Class

2, Compaction D

TN 191 $ $

40301 ‐ Asphalt Concrete, CalTrans ½” Max

Medium ‘B’ Type

TN 66 $ $

Base Bid Items (Site) 2: Sub‐Total $

Total Proposal $

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

Company Name: POC & Title:

Email: Phone Number:

DUNS Number: Tax ID:

NOTE: Payment for bond premiums in accordance with Clause 52.232‐5, Payments under Fixed‐Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under Pay Item “Mobilization”.