This document is a Minimum Standards for Responsiveness form from Salt Lake County for a small project involving the Taylorsville Library Entrance Remodel construction services. The form is designed to pre-qualify potential bidders by requiring them to answer a series of contract and project-specific performance questions. The questions assess the proposing firm's past performance, including their ability to complete construction projects without owner interventions, defaults, or liquidated damages, and their experience with similar project sizes, scopes, and types (specifically commercial and government projects).

The form requires proposers to demonstrate their qualifications by responding affirmatively to all ten questions, which cover aspects such as project completion history, references, and willingness to support third-party building systems commissioning. If a proposer cannot answer "YES" to all questions, their bid will be considered non-responsive and non-responsible. The document must be included in the bid package, and the County reserves the right to investigate the responses further. The form provides space for the company name, signer, and title, indicating it is part of the bid submission process for this specific library entrance remodeling project.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposer must answer, in the affirmative, to all questions below or the Proposer's bid will be deemed non-responsive and non-responsible.

Blank Page

EXHIBIT: [EXHIBIT A]
STANDARD: MINIMUM STANDARDS FOR RESPONSIVENESS
CONST: CONSTRUCTION SERVICES FOR:
ID: LIBTAYENTRANC
OWNER: SALT LAKE COUNTY - SMALL PROJECT
NO: NO
01: 01
02: 02
03: 03
04: 04
05: 05
Check Box 04b: Off
06: 06
07: 07
CONTRACTOR:
TITLE:
COMPANY:
COMPANY TEXT: COMPANY NAME
SIGNOR TEXT: SIGNER
TITLE TEXT: TITLE
PROJ TEXT: PROJ. ID.
QUESTION 02: Completed all construction projects without being removed from the project upon a claim by the Owner for default or breach of contract?
QUESTION 03: Completed all construction projects without assessment or payment of Liquidated Damages?
QUESTION 04: In the last five years, has your firm, acting as the General Contractor, worked on a project of similar size and scope?
QUESTION 05: In the last 3 years, has your firm, acting as the General Contractor, worked on a commercial project(s) and/or Government projects(s) outside of new single-family homes and single-family renovations?
QUESTION 06: From the last five years, is your firm able to provide a minimum of 3 references who will speak to your performance?
QUESTION 07: Will your firm and your sub-contractors support third-party building systems commissioning if required on this project?
08: 08
CHECK 08A: Off
CHECK 08B: Off
CHECK 07A: Off
CHECK 07B: Off
CHECK 06A: Off
CHECK 06B: Off
CHECK 05A: Off
CHECK 05B: Off
CHECK 04A: Off
CHECK 03A: Off
CHECK 03B: Off
CHECK 02A: Off
CHECK 02B: Off
CHECK 01A: Off
CHECK 01B: Off
YES: YES
QUESTIONS: QUESTIONS
CONTRACT 01: In the last five years, has your firm, acting as the General Contractor:
QUESTION 01: Completed all construction projects without the owner(s) calling in or involving sureties to assist in completing or assuming responsibility for completing a project?
CONTRACT: CONTRACT SPECIFIC PERFORMANCE:
PROJECT: Taylorsville Library Entrance Remodel
PROJ PERF: PROJECT SPECIFIC PERFORMANCE:
Text2: This form must be included in your bid package as part of the required forms for submittal.

The County reserves the right to investigate further, any of the responses to the above questions.

QUESTION 08:
QUESTION 09:
09: 09
CHECK 09A: Off
CHECK 09B: Off
10: 10
CHECK 10A: Off
CHECK 10B: Off
QUESTION 10:

File details come from the government source that posted it. Updated .