7--7- Exhibit A- Contractor Responsibility Questionnaire- FAC134232.pdf

PDF 316 KB Posted

Attached to
SLCo FAC134232 Adult Detention Center Roof Top Unit Replacement - CONST
Solicitation number
SLCo FAC134232 Adult Detention Center Roof Top Unit Replacement - CONST
Issued by
Utah

About this file

This is a Contractor Responsibility Questionnaire prepared by Salt Lake County, Utah, for a construction project designated as FAC134232 involving roof-top unit replacement at the Adult Detention Center. The questionnaire serves as a mandatory evaluation tool for assessing contractor qualifications and must be completed in its entirety and included in bid packages; failure to answer all questions may result in a proposal being deemed non-responsive or non-responsible. The project requires contractors to replace all Roof-Top Units (RTUs) in accordance with specified plans and specifications.

The questionnaire contains twelve performance-based criteria that contractors must address, including: demonstrating an OSHA recordable incident rate at or below the Utah industry average; completion of all construction projects without liquidated damages assessments; five years of experience as a general contractor on projects of similar size and scope; three years of experience on commercial and/or government projects outside single-family residential work; submission of three comparable project references from the past five years; commitment to support third-party building systems commissioning; successful management of large-scale rooftop equipment replacements with engineered crane lifts and complex rigging; experience with phased construction and temporary HVAC systems to minimize operational disruptions; compliance with correctional facility security requirements including background checks and escort procedures; experience integrating new HVAC equipment with existing building automation systems; and demonstrated experience managing long-lead mechanical equipment procurement on projects exceeding $20 million. The County reserves the right to conduct further investigation into any responses provided.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposer must answer all questions below or the Proposer may be deemed non-responsive and/or non-responsible.

Blank Page

EXHIBIT: [EXHIBIT A]
STANDARD: CONTRACTOR RESPONSIBILITY QUESTIONNAIRE.
CONST: CONSTRUCTION SERVICES FOR:
ID: FAC134232
OWNER: SALT LAKE COUNTY - SMALL PROJECT
NO: NO
01: 01
02: 02
03: 03
04: 04
05: 05
Check Box 04b: Off
06: 06
07: 07
CONTRACTOR:
TITLE:
COMPANY:
COMPANY TEXT: COMPANY NAME
SIGNOR TEXT: SIGNER
TITLE TEXT: TITLE
PROJ TEXT: PROJ. ID.
QUESTION 02: Is your OSHA recordable incident rate at or below the Utah industry average?
QUESTION 03: Completed all construction projects without assessment or payment of Liquidated Damages?
QUESTION 04: In the last five years, has your firm, acting as the General Contractor, worked on a project of similar size and scope?
QUESTION 05: In the last 3 years, has your firm, acting as the General Contractor, worked on a commercial project(s) and/or Government projects(s) outside of new single-family homes and single-family renovations?
QUESTION 06: From the last 5 years, bidder shall provide 3 References for comparable projects in size and scope on the Reference Form found in the Bid Requested Information area.
QUESTION 07: Will your firm and your sub-contractors support third-party building systems commissioning if required on this project?
08: 08
CHECK 08A: Off
CHECK 08B: Off
CHECK 07A: Off
CHECK 07B: Off
CHECK 06A: Off
CHECK 06B: Off
CHECK 05A: Off
CHECK 05B: Off
CHECK 04A: Off
CHECK 03A: Off
CHECK 03B: Off
CHECK 02A: Off
CHECK 02B: Off
CHECK 01A: Off
CHECK 01B: Off
YES: YES
QUESTIONS: QUESTIONS
CONTRACT 01: In the last five years, has your firm, acting as the General Contractor:
QUESTION 01: Completed all construction projects without the owner(s) calling in or involving sureties to assist in completing or assuming responsibility for completing a project?
CONTRACT: CONTRACT SPECIFIC PERFORMANCE:
PROJECT: Adult Detention Center Roof Top Unit Replacement
PROJ PERF: PROJECT SPECIFIC PERFORMANCE:
Text2: This form must be included in your bid package as part of the required forms for submittal.

The County reserves the right to investigate further, any of the responses to the above questions.

QUESTION 08: Has your firm successfully managed large-scale rooftop equipment replacements requiring engineered crane lifts, structural coordination, and complex equipment rigging?
09: 09
CHECK 09A: Off
CHECK 09B: Off
QUESTION 09: Does your firm have experience implementing phased construction, temporary HVAC systems, and contingency plans to minimize operational disruptions?
10: 10
CHECK 10A: Off
CHECK 10B: Off
QUESTION 10: Will your firm and its subcontractors comply with correctional facility security requirements, including background checks, controlled access, tool accountability, and escort procedures?
QUESTION 11: Does your firm have experience integrating new HVAC equipment with existing building automation systems, including controls, testing, commissioning, and functional performance verification?
QUESTION 12: Can your firm demonstrate experience managing long-lead mechanical equipment procurement, scheduling, and coordination on projects exceeding $20 million?
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
11: 11
12: 12