7-03 - Specifications.pdf

PDF 5 MB Posted

Attached to
34th Street Upland to Milwaukee -22B Project
Solicitation number
RFP 25-19137-TF
Issued by
Hunt County, Texas

About this file

The document is a comprehensive project manual for the 34th Street Paving Improvements project, prepared by the City of Lubbock, Texas, with engineering services by Kimley-Horn and Associates. The project involves reconstructing 34th Street from Upland Avenue to Milwaukee Avenue, transforming it from a 2-lane to a 5-lane roadway. The project manual includes detailed specifications for construction, covering aspects such as site preparation, excavation, concrete and asphalt paving, utility adjustments, traffic control, and erosion control. The document outlines specific construction milestones, including completing curb, gutter, and roadway paving, installing permanent pavement markings, and achieving final project completion within 30 consecutive calendar days after the punch list walk-through.

The project manual provides extensive technical specifications for materials and construction methods, including requirements for concrete and asphalt pavement, flexible base courses, and site preparation. The geotechnical report accompanying the manual indicates a detailed subsurface investigation involving seven soil borings, with recommendations for pavement construction using either asphalt cement concrete (ACC) or Portland cement concrete (PCC) sections. The recommended pavement thickness varies based on traffic areas, with specific material specifications for base courses, surface layers, and compaction requirements. The project appears to be funded through the City of Lubbock's 2022 Street Bond Project, with a focus on improving infrastructure and traffic capacity along 34th Street.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

34TH STREET PAVING IMPROVEMENTS

UPLAND AVE TO MILWAUKEE AVE

PROJECT MANUAL

August 2025

August 2025 SPECIAL CONDITIONS SC - 1

SPECIAL CONDITIONS

34th STREET PAVING IMPROVEMENTS

ALCOVE AVENUE TO UPLAND AVENUE

SC-1 SUBSTANTIALLY COMPLETED

Add the following to paragraph 9, Substantially Complete, of the General Conditions of the Agreement:

For this project, Milestones will be enforced and will be considered Substantially Complete according to the following:

Milestone A – All curb and gutter and roadway paving along 34th Street complete from begin project west of Upland Avenue to Milwaukee Avenue and all lanes of traffic, striped with permanent pavement markings and open to traffic.

Milestone B – All remaining items in the contract complete and ready for punch list walk-through.

Final Completion - Reach Final Completion of the contract including addressing all items identified during the Punch List walk-through within 30 (thirty) CONSECUTIVE CALENDAR DAYS from the completion of the Punch List walk-through.

SC-2 CONTRACTOR’S LAYOUT OF WORK

Add the following to paragraph 10, Layout, of the General Conditions of the Agreement:

The Contractor’s responsibility for laying out all work shall include, but not be limited to, surveying services and equipment as needed for horizontal and vertical location and control of the work. A list of vertical and horizontal control points or bench marks in the project vicinity will be furnished to the Contractor.

SC-3 KEEPING OF PLANS AND SPECIFICATIONS ACCESSIBLE

Add the following to paragraph 11, Keeping of Plans and Specifications Accessible:

The Contractor will be furnished ten (10) copies of the plans and specifications. Additional sets of plans and specifications may be purchased by Contractor at Contractor’s expense.

SC-4 LINES AND GRADES

Add the following to Paragraph 13, Lines and Grades:

Lines and grades are indicated in the drawings for the Contractor’s layout of the work, therefore the Owner’s Representative has furnished lines and grades to the Contractor, as part of the Contract Documents.

August 2025 SPECIAL CONDITIONS SC - 2

SC-5 SUPERINTENDENCE AND INSPECTION

Add the following to paragraph 15, Superintendence and Inspection, of the General Conditions of the Agreement:

The Owner’s Representative may also appoint contracted individuals and business entities to serve in the capacity of subordinate engineers, supervisors or inspectors. ENGINEER OF RECORD (EOR) is Kimley-Horn and will be available in the following capacities:

SC-5.2 Shop Drawings and Samples:

Receive samples which are furnished at the site by CONTRACTOR, and notify ENGINEER of availability of samples for examination.

Advise ENGINEER and CONTRACTOR of the commencement of any Work requiring a Shop Drawing or sample if the submittal has not been approved by the ENGINEER.

SC-5.3 Review of Work, Rejection of Defective Work, Inspections and Tests:

Conduct on-site observations of the Work in progress to assist OWNER in determining if the Work is in general proceeding in accordance with the Contract Documents.

SC-5.4 Reports:

ENGINEER will review periodic reports as required of progress of the Work and of CONTRACTOR's compliance with the progress schedule and schedule of Shop Drawing and sample submittals.

SC-6 CONTRACTOR’S DUTY AND SUPERINTENDENCE

Add the following to paragraph 16, Contractor’s Duty and Superintendence, of the General Conditions of the Agreement.

The person representing the Contractor (i.e., superintendent) shall be considered the single, authorized point of contact between the Owner’s Representative and the Contractor. Designations of different persons of contact, or contact designations that divide, or attempt to divide, the Contractor’s accountability and responsibility under the contract documents shall be grounds for suspending the operations of the Contractor without recourse on the part of the Contractor. The Contractor’s designated superintendent shall be physically and locally present until such time as the Owner issues notice of final completion.

SC-7 CHARACTER OF WORKERS

Add the following to paragraph 18, Character of Workers, of the General Conditions of the Agreement:

The provisions regarding the character of workmen shall also include persons of female gender wherever the words “man” or “men” are used. The provisions for character of workmen shall be construed to include, but not be limited to, the Contractor’s superintendent, Contractor’s subcontracted work forces, subcontractor superintendents, laborers, and supervisors.

August 2025 SPECIAL CONDITIONS SC - 3

When such workmen are discharged from the work, such workmen shall not be associated with the work in any capacity or function whatsoever.

SC-8 OBSERVATION AND TESTING

General Condition Paragraph 21 is retained in its entirety. Add the following to General Condition Paragraph 21, Observation and Testing:

Verification sampling and testing shall be performed at the location and frequency established in the “TxDOT Guide Schedule of Sampling and Testing.”

SC-9 DEFINITIONS

For the following paragraphs of these Special Conditions, ENGINEER shall be defined as the Owner’s primary consultant which is “Prime Consultant” and consultants to “Prime”, namely “Sub-Consultant”.

SC-10 DOCUMENT OWNERSHIP

Contractor, and any Subcontractor or Supplier or any other person or organization performing or furnishing any of the work under a direct or indirect contract with Owner (i) shall not have or acquire any title to or ownership rights in any of the drawings, specifications or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer, and (ii) shall not reuse any of such drawings, specifications, other documents or copies on extensions of the project or any other project without written consent of the Owner and ENGINEER and specific written verification or adaptation by

ENGINEER.

SC-11 SUBSURFACE UTILITY INVESTIGATION

The ENGINEER conducted subsurface utility investigations through The Rios Group, Inc. and were surveyed by Hugo Reed and Associates, Inc.

These subsurface investigations were prepared for design purposes, and any reliance on the data by the Contractor is at the sole risk of the Contractor. Any conclusions, interpretations or opinions based on the data are the sole province of the Contractor. Neither the Owner nor the ENGINEER assumes any liability or responsibility for the various differing subsurface utilities that may be encountered, whether or not shown in samples, soil subsurface utility reports, or Contract Documents.

Contractor may not rely upon or make any claim against Owner or Engineer with respect to:

• the completeness of such reports and drawings for CONTRACTOR’s purposes, including but not limited to, any aspects of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and program incident thereto, or

• other data, interpretations, opinions and information contained in such reports or shown or indicated in such drawings, or

• any CONTRACTOR interpretation of or conclusion drawn from any “technical data” or any such data, interpretations, opinions or information.

August 2025 SPECIAL CONDITIONS SC - 4

SC-12 UNDERGROUND FACILITIES

For the purpose of this Special Provision, Underground Facilities shall be defined as all pipelines, conduits, ducts, wires, cables, manholes, vaults, tunnels or other such facilities or attachments, and any encasements containing such facilities which have been installed underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, sewage and drainage removal, traffic or other control systems or water.

The information and data shown or indicated in the Contract Documents with respect to existing Underground Facilities at or contiguous to the site is based on information and data furnished to OWNER or ENGINEER by the owners of such Underground Facilities or by others. Unless it is otherwise expressly provided in the General Conditions of the Agreement:

• OWNER and ENGINEER shall not be responsible for the accuracy or completeness of any such information or data; and

• The cost of all the following will be included in the Contract Price and CONTRACTOR shall have full responsibility for:

• (i) reviewing and checking all such information and data,

• (ii) locating all Underground Facilities shown or indicated in the Contract Documents,

• (iii) coordination of the Work with the owners of such Underground Facilities during construction, and

• (iv) the safety and protection of all such Underground Facilities as provided in paragraph 21 of the General Instructions to Bidders and repairing, to the satisfaction of the facility owner, any damage thereto resulting from the Work.

If an Underground Facility is uncovered or revealed at or contiguous to the site which was not shown or indicated in the Contract Documents, CONTRACTOR shall, promptly after becoming aware thereof and before further disturbing conditions affected thereby of performing any Work in connection therewith (except in an emergency as required to prevent injury, loss of life, or damage to property), identify the owner of such Underground Facility and give written notice to that owner and to OWNER and ENGINEER.

SC-13 SUBSTITUTES AND “OR-EQUAL” ITEMS

SC-13.1 Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function and quality required.

Unless the specification or description contains or is followed by words reading that no like, equivalent or “or-equal” item, or no substitution is permitted, other items of material or equipment of other Suppliers may be accepted by Engineer under the following circumstances:

SC-13.2 “Or-Equal”:

If in ENGINEER’S sole discretion an item of material or equipment proposed by CONTRACTOR is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by ENGINEER as an “or-equal” item, in which case review and approval of the proposed item may, in ENGINEER’s sole discretion, be accomplished without compliance with some or all of the requirements for acceptance of proposed substitute items.

August 2025 SPECIAL CONDITIONS SC - 5

SC-13.3 Substitute Items:

If in ENGINEER’s sole discretion an item of material or equipment proposed by CONTRACTOR does not qualify as an “or-equal” item under subparagraph SC-12.2, it will be considered a proposed substitute item. CONTRACTOR shall submit sufficient information as provided below to allow ENGINEER to determine that the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. The procedure for review by the ENGINEER will include the following as supplemented in the General Requirements and as ENGINEER may decide is appropriate under the circumstances. Requests for the review of proposed substitute items of material or equipment will not be accepted by ENGINEER from anyone other than CONTRACTOR. If CONTRACTOR wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall first make written application to ENGINEER for acceptance thereof, certifying that the proposed substitute will perform adequately the functions and achieve the results called for by the general design, be similar in substance to that specified and be suited to the same use as that specified. The application will state the extent, if any, to which the evaluation and acceptance of the proposed substitute will prejudice CONTRACTOR’s achievement of Substantial Completion on time, whether or not acceptance of the substitute for use in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) to adapt the design to the proposed substitute and whether or not incorporation or use of the substitute in connection with the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute from that specified will be identified in the application and available maintenance, repair and replacement service will be indicated. The application will also contain an itemized estimate of all costs or credits that will result directly or indirectly from acceptance of such substitute, including costs of redesign and claims of other contractors affected by the resulting change, all of which will be considered by ENGINEER in evaluating the proposed substitute. ENGINEER may require CONTRACTOR to furnish additional data about the proposed substitute.

SC-13.4 CONTRACTOR’S Expense:

All data to be provided by CONTRACTOR in support of any proposed “or-equal” or substitute item will be at CONTRACTOR’s expense.

SC-13.5 Substitute Construction Methods or Procedures:

If a specific means, method, technique, sequence or procedure of construction is shown or indicated in and expressly required by the Contract Documents, CONTRACTOR may furnish or utilize a substitute means, method, technique, sequence or procedure of construction acceptable to ENGINEER. CONTRACTOR shall submit sufficient information to allow ENGINEER, in ENGINEER’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. The procedure for review by ENGINEER will be similar to that provided in subparagraph SC-12.3.

SC-13.6 Engineer’s Evaluation:

ENGINEER will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to paragraphs SC-12.3 and SC-12.5. ENGINEER will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized without ENGINEER’s prior written acceptance which will be evidenced by either a Change

August 2025 SPECIAL CONDITIONS SC - 6

Order or an approved Shop Drawing. OWNER may require CONTRACTOR to furnish at CONTRACTOR’s expense a special performance guarantee of other surety with respect to any “or-equal” or substitute. ENGINEER will record time required by ENGINEER and ENGINEER’s Consultants in evaluating substitutes proposed or submitted by CONTRACTOR pursuant to paragraphs SC-12.3 and SC-12.5 and in making changes in the Contract Documents (or in the provisions of any other direct contract with OWNER for work on the Project) occasioned thereby. Whether or not ENGINEER accepts a substitute item so proposed or submitted by CONTRACTOR, CONTRACTOR shall reimburse OWNER for the charges of ENGINEER and ENGINEER’s Consultants for evaluating each such proposed substitute item.

SC-14 RECORD DOCUMENTS

CONTRACTOR shall maintain in a safe place at the site one record copy of all Drawings, Specifications, Addenda, Written Amendments, Change Orders, Work Change Directives, Field Orders and written interpretations and clarifications in good order and annotated to show all changes made during construction. These record documents together with all approved Samples and a counterpart of all approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, these record documents, Samples and Shop Drawings will be delivered to ENGINEER for

OWNER.

Failure to maintain and safeguard these required documents shall be grounds for the Owner to issue a non-compliance directive to the Contractor and withhold all payments until such non-compliance is remedied.

SC-15 SUBMITTAL REVIEW

One initial submittal of shop drawings, samples, “or-equal” items and other required submittals and one resubmittal of the same item will be reviewed by the Engineer at no cost to the Contractor. Subsequent reviews for resubmittals of the same item will be reviewed at a cost to the Contractor of $100.00 per man-hour (with a minimum of one man-hour per submittal). Such cost shall be deducted from progress payments to the Contractor and result in a reduction of total contract price.

SC-16 PARTIAL PAYMENTS

Add the following to paragraph 42, Partial Payments, of the General Conditions of the Agreement:

Partial payments requested by the Contractor may include materials delivered, but not yet incorporated into the project. If payment is requested on the basis of materials and equipment not incorporated in the work but delivered and suitably stored at the site, or at another location agreed to in writing, then the application for payment shall also be accompanied by a bill of sale or invoice warranting that the equipment and materials are free and clear of all liens and evidence that the materials and equipment are covered by the appropriate property insurance and other arrangements to protect the Owner’s interest therein. Materials and equipment shall not be considered for partial payment if stored where the Owner cannot confirm the quantities or otherwise seize and secure the equipment and materials in the event that the Contractor defaults on the work. Materials and equipment that are eligible for partial payment will be carried as “Materials on Hand” on the partial pay estimates and then moved from “Materials on Hand” to completed items of the work once those materials and equipment are incorporated into the work. Partial payments for completed items of work will reflect adjustments for prior partial payments made to the Contractor, for the same completed items of work, for “Materials on Hand”. Partial payments for “Materials on Hand” shall be subject to the five-percent retainage. Only actual invoice

August 2025 SPECIAL CONDITIONS SC - 7 amounts and actual freight invoice amounts for delivered items to the locations stated above will be eligible for partial payment as “Materials on Hand”. Materials on hand shall be limited to materials manufactured at a manufacturing facility such as precast reinforced concrete pipe (or box), fiberglass pipe, precast manholes, manhole frames and covers, valves, grates, signal masts/arms, light poles, and so forth. Items not considered as materials on hand are those items which require further processing for use in the project such as cements, aggregates, asphalts, fill materials, concrete, riprap, topsoil, sod, seed, earthen materials, paint, glass beads, raised pavement markers, etc. The final determination of whether a substance or item qualifies as materials on hand is the sole province of the Owners representative under General Conditions Paragraph 14.

SC-17 DUST CONTROL

Sprinkling for dust control shall consist of the authorized application of water or other material approved by the OWNER on those portions of the project as shown on the plans or as directed and as herein specified. It shall be the responsibility of the CONTRACTOR to take preventative measures to eliminate, reduce, or alleviate dust nuisance in the work area. The OWNER will approve the method used. Should the CONTRACTOR fail to control dust as outlined above the OWNER may suspend the work until corrective measures are taken. Water or other material approved by the OWNER shall be furnished by the CONTRACTOR and shall be clean, free from industrial waste and other objectionable matter. Emulsions may be allowed with prior approval by the OWNER. The CONTRACTOR shall furnish and operate a sprinkler equipped truck with positive and rapidly working cutoff valves and approved spray bars, which shall insure the distribution of material in a uniform and controllable rate of application. It shall be the CONTRACTOR’S continuous responsibility to be on call at all times including nights, holidays, weekends, etc. and respond in a timely manner, until acceptance of the project by the OWNER, to maintain the project free of dust in a manner which shall cause the least inconvenience to the public. Dust Control shall be considered as incidental work and shall not be paid for as a separate item; the cost thereof shall be included in such contract pay items as are provided.

END SPECIAL CONDITIONS

August 2025 TABLE OF CONTENTS TC - 1

TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS # of Pages

01020 Measurement and Payment 01027 Applications for Payment 01028 Change Order Procedures 01039 Coordination and Meetings 01140 Work Restrictions 01310 Progress Schedules 01322 Photographic Documentation 01330 Submittal Procedures 01356 Storm Water Pollution Prevention 01400 Quality Requirements 01420 References 01500 Temporary Facilities and Controls 01555 Barricades, Signs and Traffic Handling 01576 Waste Material Disposal 01600 Product Requirements 01700 Contract Closeout

DIVISION 2 - SITE WORK

02221 Removing Existing Pavements 02260 Excavation Support and Protection 02300 Earthwork 02318 Borrow 02810 Automatic Irrigation Systems 02900 Seeding 02920 Lawns and Grasses

DIVISION 3 – CONCRETE

03300 Cast in Place Concrete

DIVISION 4 - 16 – Not Used

APPLICABLE TxDOT SPECIFICATIONS

Item 100 Preparing ROW Item 103 Disposal of Wells Item 104 Removing Concrete Item 105 Removing Treated and Untreated Base and Asphalt Pavement Item 110 Excavation Item 132 Embankment Item 160 Topsoil Item 162 Sodding for Erosion Control Item 164 Seeding for Erosion Control Item 169 Soil Retention Blankets Item 247 Flexible Base Item 251 Reworking Base Courses Item 292 Asphalt Treatment (Plant Mixed) Item 310 Prime Coat

August 2025 TABLE OF CONTENTS TC - 2

Item 341 Dense-Graded Hot Mix Asphalt Item 360 Concrete Pavement Item 400 Excavation and Backfill for Structure Item 416 Drilled Shaft Foundations Item 432 Riprap Item 450 Railing Item 459 Gabions and Gabion Mattresses Item 462 Concrete Box Culverts and Drains Item 464 Reinforced Concrete Pipe Item 465 Junction Boxes, Manholes, and Inlets Item 466 Headwalls and Wingwalls Item 467 Safety End Treatments Item 468 Thermoplastic Pipe Culverts and Drains Item 479 Adjusting Manholes Item 481 Pipe for Drains Item 496 Removing Structures Item 503 Portable Changeable Message Sign Item 505 Truck Mounted Attenuator (TMA) and Trailer Attenuator (TA) Item 506 Temporary Erosion Sedimentation and Environmental Controls Item 512 Portable Traffic Barrier Item 529 Concrete Curb, Gutter, and Combined Curb and Gutter Item 530 Intersections, Driveways, and Turnouts Item 531 Sidewalks Item 536 Concrete Medians and Directional Islands Item 610 Road Illumination Assemblies Item 618 Conduit Item 620 Electrical Conductors Item 623 Intelligent Transportation System (ITS) Ground Boxes Item 624 Ground Boxes Item 628 Electrical Services Item 636 Signs Item 644 Small Roadside Sign Supports and Assemblies Item 662 Work Zone Pavement Markings Item 666 Reflectorized Pavement Markings Item 668 Prefabricated Pavement Markings Item 672 Raised Pavement Markers Item 677 Eliminating Existing Pavement Markings and Markers Item 678 Pavement Surface Preparation for Markings Item 680 Highway Traffic Signals Item 682 Vehicle and Pedestrian Signal Heads Item 684 Traffic Signal Cables Item 686 Traffic Signal Pole Assemblies Item 687 Pedestal Pole Assemblies Item 690 Maintenance of Traffic Signals and Illumination Special Specification 6006 Video Imaging Vehicle Detection System Special Specification 6186 Intelligent Transportation System (ITS) Ground Box

APPENDIX A – Items and Pertinent Specifications APPENDIX B – TxDOT Guide Schedule of Sampling and Testing APPENDIX C – Geotechnical Report APPENDIX D – Temporary Construction Licenses (TCL)

August 2025 TABLE OF CONTENTS TC - 3

REFERENCES

City of Lubbock Engineering Minimum Design Standards and Specifications (2023) TxDOT Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (2024) Texas Manual on Uniform Traffic Control Devices (TMUTCD 2011 – Revision 2)

August 2025 DIVISION 1 – GENERAL REQUIREMENTS

DIVISION 1 – GENERAL REQUIREMENTS

August 2025 MEASUREMENT AND PAYMENT 01020 - 1

SECTION 01020

MEASUREMENT AND PAYMENT

PART 1 -GENERAL

SCOPE

The following sections shall be used to define measurements and payments for this project. The unit price bid on each item as stated in the bid proposal shall include furnishing all labor, superintendence, machinery, equipment, and materials except as otherwise specified, necessary or incidental to complete the various items of work in accordance with the plans and specifications. Cost of work or materials shown on the plans or called for in the specifications for which no separate bid item is indicated shall be considered subsidiary to the various bid items. Payment will not be made for any item that is not complete, including all associated incidental work. Only those items indicated on bid documents and plan sheets will be included for construction and payment.

ROADWAY PAY ITEMS

1.1 REMOVE CONC (SIDEWALKS)

Removing concrete sidewalks will be measured by the square yard (regardless of thickness). The unit price bid is full compensation for breaking the concrete, incidental asphalt repair, loading, hauling and salvaging or legally disposing of the material, equipment, labor, tools and incidentals necessary to complete the work. The Contractor shall ensure that the Owner has the opportunity to measure the area of concrete prior to removal. If concrete is removed without measurement by the Owner, no payment will be made for that removal.

1.2 REMOVE CONC (CURB AND GUTTER)

Removing concrete curb and gutter will be measured by the linear foot (regardless of thickness).

The unit price bid is full compensation for breaking the concrete, incidental asphalt repair, loading, hauling and salvaging or legally disposing of the material, equipment, labor, tools and incidentals necessary to complete the work. The Contractor shall ensure that the Owner has the opportunity to measure the linear footage of concrete prior to removal. If concrete is removed without measurement by the Owner, no payment will be made for that removal.

1.3 REMOVE CONC (MISCELLANEOUS)

Removing miscellaneous concrete will be measured by the square yard (regardless of thickness).

The unit price bid is full compensation for breaking the concrete, incidental asphalt repair, loading, hauling and salvaging or legally disposing of the material, equipment, labor, tools and incidentals necessary to complete the work. The Contractor shall ensure that the Owner has the opportunity to measure the area of concrete prior to removal. If concrete is removed without measurement by the Owner, no payment will be made for that removal.

1.4 REMOVING CONC (FLUME)

Removing concrete flumes will be measured by the square yard (regardless of thickness). The unit price bid is full compensation for breaking the concrete, incidental asphalt repair, loading, hauling and salvaging or legally disposing of the material, equipment, labor, tools and incidentals necessary to complete the work. The Contractor shall ensure that the Owner has the opportunity

August 2025 MEASUREMENT AND PAYMENT 01020 - 2 to measure the area of concrete prior to removal. If concrete is removed without measurement by the Owner, no payment will be made for that removal.

1.5 DRILL SEEDING (PERM) (URBAN) (CLAY)

This item will be measured by square yard complete in place. The work performed and the materials furnished in accordance with this item will include furnishing seed, mulch, fertilizer, top soil preparation and watering until Owner determines that grass is established, all materials, equipment, labor, tools and incidentals, planted in place.

1.6 BLOCK SODDING

This item will be measured by square yard complete in place. The work performed and the materials furnished in accordance with this item will include furnishing sod, fertilizer, top soil preparation and watering until Owner determines that grass is established, all materials, equipment, labor, tools and incidentals, planted in place.

1.7 ADJUSTING MANHOLES AND WATER VALVES

Measurement will be made by each manhole or water valve to be adjusted. Payment for adjustments 12” or less will be subsidiary to the most pertinent items. Payment for adjustments greater than 12” vertically up or down will be paid at the unit price bid per each manhole or water valve adjusted.

1.8 4” TYPE B HMAC

Measurement will be made of the area, in square yards, of asphalt paving actually constructed.

Payment will be made at the unit price bid per square yard for the depth shown on the typical sections. The unit price bid shall include furnishing and installing all materials, prime coat, compaction and all incidentals necessary to complete the work. For additional information refer to TxDOT Specification Item 341 – Dense-Graded Hot-Mix Asphalt.

1.9 2” TYPE C HMAC

Measurement will be made of the area, in square yards, of asphalt paving actually constructed.

Payment will be made at the unit price bid per square yard for the depth shown on the typical sections. The unit price bid shall include furnishing and installing all materials, tack coats, compaction and all incidentals necessary to complete the work. For additional information refer to TxDOT Specification Item 341 – Dense-Graded Hot-Mix Asphalt.

1.10 9” CONTINUALLY REFINFORCED CONCRETE PAVEMENT

Measurement will be made of the area, in square yards, of concrete paving actually constructed.

Payment will be made at the unit price bid per square yard for the depth shown on the typical sections. The unit price bid shall include furnishing and installing all materials, compaction and all incidentals necessary to complete the work. For additional information refer to TxDOT Specification Item 360 – Concrete Pavement.

1.11 CONCRETE DRIVEWAYS

Measurement will be made of the area, in square yards, of driveways. Driveways will be paid for at the unit price bid per square yard. Curb on driveways will be included in the area measured for the slab and will not be paid as a separate item. The unit price bid shall include furnishing and installing all materials, excavation, filling, backfilling, curbing, reinforcement, forming, finishing, joint cutting, joint sealing, and all incidentals necessary to complete the work.

August 2025 MEASUREMENT AND PAYMENT 01020 - 3

OTHER PAY ITEMS

1.12 BARRICADES, SIGNS AND TRAFFIC HANDLING

Payment will be made at the unit price bid per month for traffic control measures actually installed in accordance with Division 1 Section 01555. Partial payment will be made on a pro-rata basis as a percentage of the construction contract duration. The sum of the partial payments made for traffic control shall not exceed 90% of the extended bid price for traffic control prior to the termination of the construction contract. No partial payment will be made for partial traffic control measures. Payment shall not be made for this item where the Owner determines a lack of evidence that traffic control was used, or that the measures installed do not meet the requirements of the plans. No additional payments will be allowed where traffic control is required because of work being remedied due to not meeting the requirements of the plans and specifications. The contractor shall provide two project signs as part of this pay item. Work zone pavement markings and associated striping and buttoning for the movement of traffic during construction phasing shall be subsidiary to this pay item. Any positive concrete barrier and associated end treatments shall be subsidiary to this pay item.

1.13 TEMPORARY PAVEMENT

Measurement will be made of the area, in square yards, of temporary pavement placed. Quantity shall not exceed that which is shown on the plans with approval by the engineer. Temporary pavement, used for traffic control purposes, shall consist of 2” HMAC and 4” Flex Base. The unit price bid shall include furnishing and installing all materials, prime coats, compaction and all incidentals necessary to complete the work. It is the responsibility of the contractor to maintain temporary pavement throughout construction. At all times, temporary roadways shall be smooth, traversable, and built to the dimensions shown on the plans.

1.14 REMOVE STR (WOOD FENCE WITH BRICK POSTS)

Measurement will be paid for, in linear feet (LF), of wooden fence removed. Payment will be made at the unit price bid per linear foot of fence removed. The unit bid price shall include the demolition and disposal of all fence components and associated substructures, including all concrete foundations.

1.15 RIPRAP CONC (5 IN)

Measurement will be paid for, in square yard (SY), of actual concrete constructed. Payment will be made at the unit price bid per square yard for the depth shown on the plans. The unit price bid shall include furnishing and installing all materials, subgrade preparation and compaction, fine grading, fill, formwork, and construction of all toe walls as shown in the plans. Toe walls, and any incidental work associated with the construction of the toe walls, will not be paid for separately but will be subsidiary to this item.

1.16 MOBILIZATION

A. The cost for mobilization shall be limited to no more than 5% of the Contract amount for construction items (materials and labor) bid for this project.

B. Mobilization shall include costs associated with move-in related equipment and labor, bid bond, performance and construction bonds and insurance related for this project. This would include the establishment and removal of offices, plants and facilities, movement of personnel, equipment, and supplies to and from the project or the vicinity of the project site to begin work or complete work on Contract Items. This Item will be measured by the lump sum as the work progresses.

August 2025 MEASUREMENT AND PAYMENT 01020 - 4

C. Payment. Partial payments of the lump sum bid for mobilization will be as follows. The adjusted Contract amount for construction Items as used below is defined as the total Contract amount less the lump sum for mobilization.

1. Payment will be made upon presentation of a paid invoice for the payment bond, performance bond, and required insurance. The combined payment for bonds and insurance will be no more than 10% of the mobilization lump sum.

3. When 1% of the adjusted Contract amount for construction Items is earned, 50% of the mobilization lump sum bid will be paid. Previous payments under this Item will be deducted from this amount.

4. When 5% of the adjusted Contract amount for construction Items is earned, 75% of the mobilization lump sum bid will be paid. Previous payments under the Item will be deducted from this amount.

5. When 10% of the adjusted Contract amount for construction Items is earned, 90% of the mobilization lump sum bid will be paid. Previous payments under this Item will be deducted from this amount.

6. Payment for the remainder of the lump sum bid for “Mobilization” will be made on the final estimate after final acceptance of the project.

PART 2 -PRODUCTS

Not Used

PART 3 -EXECUTION

Not Used

END OF SECTION 01020

August 2024 APPLICATIONS FOR PAYMENT 01027 - 1

SECTION 01027

APPLICATIONS FOR PAYMENT

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, General Conditions of the Contract for Construction, Supplementary Conditions and Division 1 -General Requirements apply to work of this section.

1.2 SECTION INCLUDES

A. Procedures for preparation and submittal of Applications for Payment.

1.3 RELATED SECTIONS

A. Agreement: Contract Sum/Price and unit prices.

B. General Conditions: Progress Payments and Final Payment.

C. Section 01020 - Measurement and Payment.

D. Section 01028 - Change Order Procedures.

E. Section 01330 - Submittal procedures.

F. Section 01700 - Contract Closeout.

1.4 FORMAT

A. EJCDC 1910-8-E -Application for Payment including continuation sheets when required, or Owner forms, or Owner-approved form of the Contractor.

B. For each item, provide a column for listing: Item Number; Description of work; Scheduled Value, Previous Applications; Work in Place; Authorized Change Orders; Total Completed;

Percentage of Completion; Balance to Finish; and Retainage.

1.5 PREPARATION OF APPLICATIONS

A. Present required information in typewritten form or computer generated Excel Spreadsheet.

B. Execute certification by signature of authorized officer.

C. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

D. List each authorized Change Order as an extension on continuation sheet, listing Change

Order number and dollar amount as for an original item of Work.

E. Prepare Application for Final Payment as specified in Section 01700.

1.6 SUBMITTAL PROCEDURES

A. Submit four copies of each Application for Payment.

B. Submit an updated construction schedule with each Application for Payment. Payment will not be made until an up-to-date schedule is received.

C. Payment Period: Submit at intervals stipulated in the Agreement.

August 2024 APPLICATIONS FOR PAYMENT 01027 - 2

1.7 SUBSTANTIATING DATA

A. When Engineer requires substantiating information, submit data justifying dollar amounts in question.

B. Provide one copy of data with cover letter for each copy of submittal. Show Application number and date, and line item by number and description.

PART 2 -PRODUCTS

Not Used

PART 3 -EXECUTION

END OF SECTION

August 2025 CHANGE ORDER PROCEDURES 01028 - 1

SECTION 01028

CHANGE ORDER PROCEDURES

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, General Conditions of the Contract for Construction, Supplementary Conditions and Division 1 -General Requirements apply to work of this section.

1.2 SECTION INCLUDES

A. Submittals.

B. Documentation of change in Contract Sum/Price and Contract Time.

C. Change procedures.

D. Construction Change Authorization E. Stipulated Price change order.

F. Unit price change order.

G. Time and material change order.

H. Execution of change orders.

I. Correlation of Contractor submittals.

1.3 RELATED SECTIONS

A. Section 01027 -Applications for Payment.

B. Section 01330 -Submittal Procedures.

C. Section 01600 -Product Requirements.

D. Section 01700 -Contract Closeout.

1.4 SUBMITTALS

A. Submit name of the individual authorized to receive change documents, and be responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Change Order Forms: EJCDC 1910-8-B Change Order, Owner’s form, or other form approved by Owner.

1.5 DOCUMENTATION OF CHANGE IN CONTRACT SUM/PRICE AND CONTRACT TIME

A. Maintain detailed records of work done on a time and material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs of changes in the Work.

B. Document each quotation for a change in cost or time with sufficient data to allow evaluation of the quotation.

C. Provide additional data to support computations:

1. Quantities of products, labor, and equipment.

2. Taxes, insurance and bonds.

August 2025 CHANGE ORDER PROCEDURES 01028 - 2

3. Overhead and profit.

4. Justification for any change in Contract Time.

5. Credit for deletions from Contract, similarly documented.

6. If subcontracted, provide subcontractor documentation according to General Contract

Conditions and this specification. Show Contractor markup on subcontractor changes.

D. Support each claim for additional costs, and for work done on a time and material basis, with additional information:

1. Origin and date of claim.

2. Dates and times work was performed, and by whom.

3. Time records and wage rates paid.

4. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

Show Contractor markup on subcontractor work.

1.6 CHANGE PROCEDURES

A. The Engineer will advise of minor changes in the Work not involving an adjustment to Contract Sum/Price or Contract Time as authorized by the Contract by issuing supplemental instructions by letter.

B. The Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications and a change in Contract Time for executing the change. Contractor will prepare and submit an estimate within 7 days.

C. The Contractor may propose a change by submitting a request for change to the Engineer, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum/Price and Contract Time with full documentation and a statement describing the effect on Work by separate or other contractors. Document any requested substitutions in accordance with Section 01600.

1.7 CONSTRUCTION CHANGE AUTHORIZATION

A. Engineer may issue a document, signed by the Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

B. The document will describe changes in the Work, and will designate method of determining any change in Contract Sum/Price or Contract Time.

C. Promptly execute the change in Work.

1.8 STIPULATED PRICE CHANGE ORDER

A. Based on Proposal Request and Contractor's maximum price quotation or Contractor's request for a Change Order as approved by Engineer.

1.9 UNIT PRICE CHANGE ORDER

A. For pre-determined unit prices and quantities, the Change Order will be executed on a fixed unit price basis.

August 2025 CHANGE ORDER PROCEDURES 01028 - 3

B. For unit costs or quantities of units of work which are not pre-determined, execute Work under a Construction Change Authorization.

C. Changes in Contract Sum/Price or Contract Time will be computed as specified for Time and Material Change Order.

1.10 TIME AND MATERIAL CHANGE ORDER

A. Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

B. Engineer will determine the change allowable in Contract Sum/Price and Contract Time as provided in the Contract Documents.

C. Maintain detailed records of work done on Time and Material basis.

D. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

1.11 EXECUTION OF CHANGE ORDERS

A. Execution of Change Orders: Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.12 CORRELATION OF CONTRACTOR SUBMITTALS

A. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum/Price.

B. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust time for other items of work affected by the change, and resubmit.

C. Promptly enter changes in Project Record Documents.

PART 2 -PRODUCTS

Not Used

PART 3 -EXECUTION

August 2025 COORDINATION AND MEETINGS 01039 - 1

SECTION 01039

COORDINATION AND MEETINGS

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, General Conditions of the Contract for Construction, Supplementary Conditions and Division 1 -General Requirements apply to work of this section.

1.2 SECTION INCLUDES

A. Coordination.

B. Preconstruction meeting.

C. Progress meetings.

1.3 COORDINATION

A. Coordinate scheduling, submittals, and work of the various Sections of the Specifications to assure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate completion and clean up of Work of separate Sections in preparation for Substantial Completion.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

1.4 PRECONSTRUCTION MEETING

A. Contractor will schedule a meeting with the required attendees.

B. Attendance Required: Owner, Engineer, Contractor and major Subcontractors.

C. Agenda:

1. Distribution of executed Contract Documents.

2. Submission of list of Subcontractors, list of products and progress schedule.

3. Designation of personnel representing the parties in Contract and the Engineer.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders and Contract closeout procedures.

5. Schedules.

6. Scheduling activities of construction testing lab.

7. Use of premises by Owner and Contractor.

8. Owner's requirements.

9. Construction facilities and controls provided by Owner.

10. Security and housekeeping procedures.

11. Procedures for testing.

12. Procedures for maintaining record documents.

August 2025 COORDINATION AND MEETINGS 01039 - 2

13. Inspection and acceptance of equipment or improvements put into service during construction period.

14. Other items as deemed necessary by Owner or Engineer.

D. Contractor will record minutes and distribute copies to participants.

1.5 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-weekly intervals.

B. Contractor will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Owner’s representative, Job superintendent, major Subcontractors and suppliers, Engineer, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Contractor will record minutes and distribute copies to participants.

PART 2 -PRODUCTS

Not Used

PART 3 -EXECUTION

August 2025 WORK RESTRICTIONS 01140 - 1

SECTION 01140

WORK RESTRICTIONS

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings, General Conditions of the Contract for Construction, Supplementary Conditions and Division 1 - General Requirements apply to work of this section.

1.2 SECTION INCLUDES

A. Use of premises.

B. Special scheduling requirements.

C. Working period.

D. Noise restrictions.

E. Advance Notice.

F. Water for Construction.

1.3 USE OF PREMISES

A. Use of Site: Limit use of premises to work within defined right-of-way and easements shown on the plans. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to employees and emergency vehicles at all times, except when construction is immediately at that vicinity. Do not use these areas for parking or storage of materials.

a. Schedule construction to minimize obstruction of driveways and entrances.

1.4 SPECIAL SCHEDULING REQUIREMENTS

A. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

B. Permission to interrupt any utility service shall be requested in writing a minimum of 14 calendar days prior to the desired date of interruption.

C. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.

1.5 WORKING PERIOD

A. Working Hours -Regular working hours shall be within an 11-hour period between 7:00 a.m. and 6:00 p.m., Monday through Friday, and an eight-hour period between 9:00 a.m. and 5:00 p.m. on Saturday. Saturday work shall be restricted to those activities that do not require observation by the Owner. The Owner reserves the right, at the Owner’s discretion, to not allow work when it interferes with holiday times. No work shall be performed on the following holiday periods or days:

1. New Year’s Day (observed)

August 2025 WORK RESTRICTIONS 01140 - 2

2. Memorial Day Holiday (observed)

3. Independence Day Holiday (observed)

4. Labor Day Holiday (observed)

5. Thanksgiving Day Holiday plus the day before and the three days following

Thanksgiving Day.

6. Christmas week. If Christmas Day falls on a Saturday, this will be defined as the week leading to Christmas Day. If Christmas Day falls on a Sunday, this will be defined as the week following Christmas Day plus the Friday and Saturday prior to Christmas Day.

B. Work Outside Regular Hours -Work outside regular working hours requires Owner’s approval. Make application 21 calendar days prior to such work to allow arrangements to be made by the Owner for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Owner may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Owner. Lighting shall be such that it does not cause nuisance conditions.

C. The drawings contain specific requirements that affect certain areas of the work.

1.6 NOISE RESTRICTIONS

A. 75 dB limit at face of nearest structure during normal daylight hours.

B. 65 dB limit at face of nearest structure during evening and nighttime hours in or near residential areas and for 24-hour working conditions that have received Owner approval.

Evening and nighttime hours shall be defined as 6:00 p.m. to 7:00 a.m.

C. Contractor shall keep on site OSHA-approved hand portable sound measurement equipment for both the Owner’s and the Contractor’s use for measuring noise levels.

1.7 ADVANCE NOTICE

A. Contractor shall provide a minimum of five business days advance written notice of construction to businesses and residences along the construction route.

1. The advance written notice shall be in the form of a single-page flyer to be placed by hand by the Contractor’s forces in mailboxes, door handles or handed to applicable individuals at each route building.

2. The text for the advance written notice will be provided by the Owner in written form and electronic form.

3. Reproduction shall be at the Contractor’s expense.

4. Distribution shall be at the Contractor’s expense.

5. Single-page flyers shall be of a paper or post-card color other than white to direct the recipient’s attention to the information.

6. The text shall contain…