This is a Post-Award Schedule attachment for an AAAP (Alternation, Alteration, Repair, and Prospecting) Project Specific Advertisement (PSA) that outlines the design and construction timeline for a federal lease agreement. The schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100).

The post-award schedule commences within 5 working days of lease award and establishes a 140 working day timeline from lease award to government acceptance. Key milestones include: Lessor-Provided Design Intent Drawings (10 days), Government review and approval of design drawings (15 days), Lessor preparation and submission of construction documents (10 days), Government review of construction drawings (5 days), Lessor submission of Tenant Improvement (TI) and Building Standard Alterations and Contingency (BSAC) price proposal (10 days), Government review, negotiation, and approval of pricing (15 days), Government issuance of Notice to Proceed with construction (5 days), Lessor obtainment of construction permit (30 days), Lessor completion of TI and other required construction work (30 days), Government inspection of finished space (5 days), and Lessor completion of punchlist with Government acceptance (5 days). This schedule manages the complete design and construction process concluding at the date of space acceptance.

View the file

Other files

File Type Posted
6NY0732 Delineated Area Exhibit.pdf PDF
6NY0732 Delineated Area.pdf PDF
6NY0732 Space Breakdown.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 10

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15

Lessor Preparation and Submission of Construction Documents 10

Government Review of Construction Drawings 5

Lessor Preparation and Submission of the TI and BSAC Price Proposal 10

Government Reviews, Negotiates, and Approves Pricing 15

Government Issues Notice to Proceed with Construction 5

Lessor Obtains Construction Permit 30

Lessor Completes Construction of TIs and Completion of Other Required Construction Work 30

Government Inspects Finished Space 5

Lessor Completes Punchlist and Government Accepts Finished Space 5

Total Work Days from Lease Award to Government Acceptance 140

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)