Addendum No. 2 to RFP #6-B143-P-00148-00.doc
DOC document 147 KB Posted
- Solicitation number
- 6-B143-P-00148-00
- Issued by
-
Department of Energy Office of Science
About this file
This is Addendum No. 2 to Request for Proposal (RFP) No. 6-B143-P-00148-00 for the ALCF Artemis Compute Cluster, issued by Argonne National Laboratory on June 3, 2026. The addendum clarifies and updates key specifications previously provided in Addendum No. 1. The primary changes address installation requirements and component handling procedures for the proposed compute cluster solution.
The addendum modifies the rack installation requirement from five (5) existing HPE P9K58A racks to four (4) racks in Building 240 Data Center, each equipped with four (4) HPE R4N79A Power Distribution Units (PDUs). Each PDU provides twenty-four (24) IEC 60320/C13 outlets at 12A @208V L-L (15A Peak) and twelve (12) C-series outlets at 16A @208V L-L (20A Peak). Additionally, the addendum clarifies the spare components policy, specifying that non-volatile storage components (SSDs, HDDs, SDCards, etc.) may not be shipped back to the Original Equipment Manufacturer (OEM), while other non-storage components may be shipped back and their handling terms may be negotiated as part of the contract award. Offerors are required to acknowledge receipt of this addendum by returning a signed copy to the Procurement Specialist at atkinson@anl.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum No. 1 to RFP #6-B143-P-00148-00.doc | DOC document | |
| Enclosure No. 5 - ANL-70B.pdf | ||
| Enclosure No. 2A - Appendix A ANL-71COM.pdf | ||
| Enclosure No. 4 - Evaluation Criteria.docx | DOCX document | |
| Enclosure No. 6 - Tax Exemption Certificate.pdf | ||
| Enclosure No. 2C - Appendix E ANL-366M.pdf | ||
| Enclosure No. 1 - RFP Cover Letter, Instructions, & Notices.docx | DOCX document | |
| Enclosure No. 2B - Appendix B Statement of Work.docx | DOCX document | |
| Enclosure No. 2 - Draft ANL-71 Purchase Order.doc | DOC document | |
| Enclosure No. 2D - Appendix E.1 ANL-366TCSB.pdf | ||
| Enclosure No. 3 - Pricing Proposal Form.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Court Atkinson Procurement Specialist Financial Management and Procurement Services (FMPS) Argonne National Laboratory
9700 South Cass Avenue, Bldg. 201
Lemont, IL 60439
630-252-3388 atkinson@anl.gov
June 3, 2026
TO ALL OFFERORS:
Subject:
ALCF Artemis Compute Cluster
Request for Proposal (RFP) No. 6-B143-P-00148-00 Addendum No. One (2)
Attached herewith for your information and use in preparing your proposal for subject project is Addendum No. 2.
Kindly acknowledge receipt of this Addendum by signing and returning one (1) copy of this letter to atkinson@anl.gov.
Sincerely, Court Atkinson
Procurement Specialist
Argonne National Laboratory FMPS
Receipt Acknowledged:
Company:
By:
Addendum No. TWO (2)
TO
REQUEST FOR PROPOSAL (RFP) 6-B143-P-00148-00
FOR
ALCF Artemis Compute Cluster
Date of Addendum: June 3, 2026 This addendum is being issued to modify the subject RFP as follows:
I. Clarifications and Offeror Questions
The following clarifications are made to responses previously issued under Addendum No. 1:
Q: What type of power – C13/C14 or C19/C20?
Original response: Proposals must include on-site services for installation into a set of five (5) existing racks (HPE P9K58A) in the Building 240 Data Center, each with four (4) PDUs (HPE R4N79A). The HPE R4N79A provides (24) x IEC 60320/C13 ≤ 12A @208V L-L (15A Peak) and (12) x Cx ≤ 16A @208V L-L (20A Peak).
Updated response: Proposals must include on-site services for installation into a set of four (4) existing racks (HPE P9K58A) in the Building 240 Data Center, each with four (4) PDUs (HPE R4N79A). The HPE R4N79A provides (24) x IEC 60320/C13 ≤ 12A @208V L-L (15A Peak) and (12) x Cx ≤ 16A @208V L-L (20A Peak).
Q: SOW Section 3.4 - When a part is replaced from the spares kit, is it allowed to be sent back to the OEM or is it expected to stay with the customer?
Original response: It is not allowed for storage components to be shipped back to the OEM. Shipping other non-storage components is allowed and may be negotiated as part of the award.
Updated response: It is not allowed for non-volatile storage components (SSDs, HDDs, SDCards, etc.) to be shipped back to the OEM. Shipping other components are allowed and may be negotiated as part of the award.