6991PE24Q000003 SOW 01.25.24.pdf

PDF 153 KB Posted

Attached to
Suisun Bay Reserve Fleet (SBRF) Laboratory Analysis Services
Solicitation number
6991PE24Q000003
Issued by

About this file

This statement of work outlines laboratory analysis services required by the U.S. Department of Transportation Maritime Administration's Suisun Bay Reserve Fleet in Benicia, California. The laboratory must analyze samples of potable water, vessel bilge water, stormwater runoff, paint waste, solid and liquid polychlorinated biphenyls, and presumed asbestos-containing materials. Specific tests are identified for each sample type, along with required accreditations, sample collection and reporting timelines. The performance period is one base year plus four optional one-year extensions, with an additional optional six month extension. Laboratories must be located within 60 miles of the Suisun Bay Reserve Fleet.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lab Analysis Services SOW Page 1

Statement of Work Laboratory Analysis Services

Provide laboratory services to perform analyses of potable water, vessel bilge water, stormwater runoff, paint waste, solid and liquid Polychlorinated Biphenyls (PCBs) and presumed asbestos containing material as described below. The laboratory must have an accreditation for lead analysis (American Industrial Hygiene Association Environmental Lead Laboratory Accreditation Program (AIHA ELLAP), National Lead Laboratory Accreditation Program (NLLAP) or other lead accreditation) and also have California Environmental Laboratory Accreditation Program (ELAP) or equivalent certification.

In all cases, samples will be obtained by personnel of US DOT Maritime Administration, Suisun Bay Reserve Fleet (SBRF), 2595 Lake Herman Road, Benicia, CA 94510.

The Contractor is to provide sample collection containers, labels and pre-prepared chain of custody forms, pick up the samples from SBRF according to the timeframes specified below, perform analytical testing, and provide reports for following tasks.

Potable Water

Analyze potable water samples for the following:

• Total Coliform and E-Coli

• CAM-17 metals

• Chlorine

• Total Dissolved Solids

• Total Organic Carbons

Maximum number of samples to be tested per year: 24

Contractor must prepare and supply, with the appropriate preservatives as applicable, sample collection kits for the above tests. Contractor must deliver up to four sample collection container kits to SBRF upon request. Contractor must pick up the sample collection containers within 24 hours (except weekends and government holidays) upon notice from

SBRF.

For each potable water sampling, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor must provide a written report to the Contracting Officer’s Representative (COR) of sample test results within ten (10) days of receipt of the samples from SBRF.

These services must be requested as needed.

Bilge Water

Lab Analysis Services SOW Page 2

Analyze bilge water samples for the pollutants listed in Table 1, City of Benicia Public Owned Treatment Works (POTW) Required Testing, according to the methods and minimum detection limits shown in the table.

Maximum number of sampling events to be tested per year: 10

Contractor must prepare and supply, with the appropriate preservatives as applicable, sample collection kits for the above tests. Contractor must deliver up to four sample collection container kits to SBRF upon request. Contractor must pick up the sample collection containers within 24 hours (except weekends and government holidays) upon notice from

SBRF.

For each bilge water sampling, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor must provide a written report to the COR of sample test results within five (5) days of receipt of the samples from SBRF.

These services will be requested as needed.

Storm Water, including Total Metals

Analyze storm water samples for the constituents listed in Table 2, Parameter Benchmark Values. Of the metals listed, testing will be for Total Metals only.

The method for metals shall be Environmental Protection Agency EPA 200.8 (metals) and EPA 1631 (mercury), so that the Practical Quantitation Limits (equipment detection limits) and Reporting limits are equal to or less than the Target Levels/Benchmarks.

Maximum number of samples to be tested per year: 44

Contractor must prepare and supply, with the appropriate preservatives as applicable, sample collection kits for the above tests. Contractor must deliver up to 12 sample collection container kits to SBRF upon request. Contractor must pick up as many as 10 filled sample collection container kits within 24 hours (except weekends and government holidays) upon notice from SBRF. Please do not analyze mercury under EPA 200.8 method and only use method EPA 1631 for mercury analysis.

For each storm water sampling event, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor must provide a written report to the COR of sample test results within ten (10) days of receipt of the samples from SBRF. Additionally, contractor msut provide both a reporting limit and a method detection limit for all stormwater sample analysis.

Lab Analysis Services SOW Page 3

These services will be requested a few days before and immediately following a qualifying rain event.

Storm Water, including Total and Dissolved Metals

Analyze storm water samples for the constituents listed in Table 2, Parameter Benchmark Values. Of the metals listed, testing will be for both Total and Dissolved Metals.

The method for metals shall be EPA 200.8 (metals) and EPA 1631 (mercury), so that the Practical Quantitation Limits (equipment detection limits) are equal to or less than the Benchmark Values (BMVs) and Environmental Screening Levels (ESLs), whichever is less.

Please do not analyze mercury under EPA 200.8 method and only use method EPA 1631 for mercury analysis.

Maximum number of samples to be tested per year: 10

Contractor must prepare and supply, with the appropriate preservatives as applicable, sample collection kits for the above tests. Contractor must deliver up to four sample collection container kits to the SBRF upon request from SBRF. Contractor must pick up as many as four filled sample collection containers within 24 hours (except weekends and government holidays) upon notice from SBRF.

For each storm water sampling event, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor must provide a written report to the COR of sample test results within ten (10) days of receipt of the samples from SBRF.

These services will be requested a few days before and immediately following a qualifying storm event).

PCBs

Analyze waste (solid and liquid) for the following constituents:

• Polychlorinated Biphenyls, test for PCB 1016, 1221, 1232, 1242, 1248, 1254, 1260, 1262, 1268, 8082a and Total PCB’s.

Maximum number of tests per year: 10

Contractor must prepare and supply, with the appropriate preservatives as applicable, sample collection kits for the above tests. Contractor must deliver up to four sample collection container kits to SBRF upon request. Contractor must pick up sample collection containers within 24 hours (except weekends and government holidays) upon notice from SBRF.

Lab Analysis Services SOW Page 4

For each PCB sample, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor msut provide a written report to the COR of sample test results within ten (10) days of receipt of the samples from SBRF.

Paint Waste

Analyze paint waste (exfoliated, chipped, and other) samples(s) for the following constituents:

• CAM17: Constituents identified in Table 2. (results in µg/L)

• Polychlorinated Biphenyls, test for PCB 1016, 1221, 1232, 1242, 1248, 1254, 1260, 1262, 1268, 8082a and Total PCB’s (results in µg/L)

Maximum number of tests per year: 25

SBRF will provide the sample containers. Contractor must pick up sample collection containers within 24 hours (except weekends and government holidays) upon notice from

SBRF.

For each paint waste sample, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample testing results. Contractor must provide a written report to the COR of sample test results within ten (10) days of receipt of the samples from SBRF.

Asbestos, Expedited

Expedited analysis of various materials such as gaskets, pipe lagging, insulation, wall board, etc.) for:

• Asbestos content using Polarized Light Microscopy method

Maximum number of tests per year: 25

SBRF will provide the sample containers. Contractor must pick up sample collection containers within 24 hours (except weekends and government holidays) upon notice from

SBRF.

For each asbestos sample, the contractor must provide SBRF a lab analysis report with an original signature of a certified lab technician qualified to analyze and interpret sample

Lab Analysis Services SOW Page 5 testing results. Contractor must provide test results by email to the COR on the material tested within 48 hours after receipt of the material.

These services will be requested as needed.

Location and hours of operation for supplies being delivered:

Suisun Bay Reserve Fleet 2595 Lake Herman Road Benicia, CA 94510 (Phone) 707 745-0487 (Fax) 707 745-2508 Days and hours of operation are 07:00-17:30, Mon-Fri excluding Holidays.

SBRF observes all federal Holidays observed.

Period of Performance:

The period of performance is a one-year base period plus four (4) one-year option periods.

An option to extend services (FAR 52.217-8) to allow up to an additional six (6) months of optional performance is also included.

To the maximum extent possible and consistent with the Federal Acquisition Regulations Part 23, the Government requires during the performance of the work under this Statement of Work (SOW) the Contractor to provide or use products that are: energy efficient (ENERGY STAR® or Federal Energy Management Program (FEMA)-designated); water-efficient;

biobased; environmentally preferable (e.g., EPEAT-registered, or non-toxic or less toxic alternatives); non-ozone depleting; or made with recovered materials. Unless otherwise identified in this SOW, each recovered materials or biobased product provided and delivered must meet, but may exceed, the minimum recovered materials or biobased content of an EPA- or USDA-designated product. The sustainable acquisition requirements specified herein apply only to products that are required to be: (1) delivered to the Government during contract performance; (2) acquired by the contractor for use in performing services (including construction) at a Federally-controlled facility; (3) furnished by the contractor for use by the Government; or (4) specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance.