This is a Questions and Answers document for a federal contract opportunity for OK FW TSM 10(1) NFH Entrance Road and Parking Improvements in Tishomingo, Oklahoma (Solicitation Number 6982AF27B000002). The document addresses inquiries submitted during the advertisement period from October 20 through November 10, 2026, and clarifies requirements related to survey and design coordination, asphalt specifications, personnel qualifications, project timeline, site conditions, gate specifications, and utility availability.

Key clarifications include: no existing survey control points are available on the site, and contractors must establish control per SCR and FP-24 section 152; the Government will not provide survey-grade design files, as-built survey data, or extend the bid deadline to accommodate missing grading information; asphalt mix design requirements are specified in SCR and FP-24 section 403; single personnel cannot hold multiple management roles simultaneously per FP-24 section 153.04; the period of performance cannot be extended post-award for material lead times per FP-24 and SCR section 108; no site visit was conducted; soil boring reports are addressed in Amendment A001; the project is subject to federal, state, and local taxes per RFO 52.229-3; gate dimensions are clarified as one 20-foot gate and one 40-foot gate per Amendment A002; bi-parting 40-foot gates should operate together; no safeties, high/low photo eyes, or exit loops are required; and barbed wire is not needed on gate tops. Water availability for construction operations is referenced in SCR section 105.02(a).

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6982AF27B000002

OK FW TSM 10(1) NFH Entrance Road and Parking Improvements

Questions and Answers During Advertisement

October 20, 2026

Questions Answers 1 Do you have structural plans showing the bridge loads so I can design a helical pile for the project in Tishomingo, OK?

There are no bridges or helical piles on this project.

October 22, 2026

2 The design appears to be traced over an aerial photograph referenced to the Oklahoma State Plane coordinate system or WGS 84. Please confirm the horizontal datum, coordinate system (including zone), and units used for the design.

Refer to the C sheets in the plans and SCR 102.02A for information on the coordinate system used for design data.

3 Are there existing survey control points on the site that the design points are tied to? If so, please provide their coordinates, descriptions, and locations.

There are no existing survey control points on the project site that the design points are tied to.

4 If no control points were established before design, who is responsible for establishing them? Will the Government or the design engineer provide them, or does the contractor need to?

Refer to SCR and FP-24 section 152 for construction survey and staking requirements.

5 Superimposing design data over an aerial image that is only approximately in State Plane coordinates is not sufficient for survey and layout. Will the Government provide a survey-grade, control-based design file (for example CAD or LandXML) that can be used to stake the work?

No.

6 Will the Government or design engineer collect as-built (existing conditions) survey data on the ground, tied to established control, so the design can be accurately overlaid on the site?

No.

7 Is the engineer of record responsible for tying the design to ground control? Establishing that tie is a design engineering function, not a surveyor's function. Please confirm who will perform it.

Refer to SCR and FP-24 section 152 for construction survey and staking requirements.

8 If control points were set before design, please provide the control data and the survey that supports the design. A surveyor could then use those points to lay out the work.

There are no existing survey control points on the project site that the design points are tied to.

9 The plans do not show grades or grading information. Please provide proposed grades, finished elevations, spot elevations, contours, slopes, and cross-sections.

Refer to the typical sections in the plans for grading information.

10 What vertical datum applies (NAVD 88, for example), and what benchmark(s) should be used for elevation control?

Refer to SCR and FP-24 section 152 for construction survey and staking requirements.

11 Without grading information, no elevation data can be established for layout or staking. Will revised plans with full grading data be issued by addendum?

No.

12 Will the Government extend the bid or submission deadline until this information is provided, so the contractor can price and plan the work accurately?

No.

13 If this information cannot be provided before award, how will the Government handle costs and time for any survey control, as-built collection, or design revisions the contractor must perform?

Refer to SCR and FP-24 section 109 for measurement and payment.

October 26, 2026

14 Can an S4 64-22 insoluble ODOT approved mix design be used for the Type 1 Asphalt? If not is there a preference of an ODOT approved mix that can be used?

Refer to SCR and FP-24 section 403 for asphalt requirements.

November 10, 2026

15 Can one person "triple hat" as Superintendent, SSHO and QC

Manager?

Refer to FP-24 section 153.04

16 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Refer to FP-24 and SCR section 108 for prosecution and progress of work restrictions.

17 Please provide the site visit attendee sign in sheet. No site visit was conducted 18 Are soil boring reports available? If not, confirm discovery of rocks and obstructions during excavation will be treated as differing site conditions under FAR 52.236‑2 or addressed as a change under FAR 52.243‑4.

Refer to Amendment A001

19 Is this project tax exempt? Refer to RFO 52.229-3 Federal, State, and Local Taxes 20 When do you anticipate on site work starting? Refer to FP-24 and SCR section 108 for prosecution and progress of work restrictions.

21 Are third party inspections required? Refer to FP-24 and SCR section 153 and 154 for quality, testing, and inspection requirements.

22 Please provide staking data points for the project. Refer to the design physical data and reports in the solicitation and SCR section 102.02A for government-provided physical data 23 Are red, yellow, and blue tops required? Refer to FP-24 and SCR section 152 24 Is the contractor required to design and stamp structural drawings for the gate foundations? If contractor is not responsible please provide dimensions for estimating purposes.

Refer to SCR section 619.03 for footing requirements.

25 On the Misc. Summaries on sheet B4, item numbers 61902-1500 and 61902-2200, call for (1) 18' metal gate and (1) 34' metal gate.

However, elsewhere in plans and specifications it calls for (1) 20' metal gate and (1) 40' wide metal gate. Such as on the Summary of Quantities - Schedule A (line items A0620 & A0640) on sheet B1, sheet C1, sheet C3, sheet T5. Please confirm what gate sizes are correct.

Refer to Amendment A002.

26 Are the operators for the bi-parting 40' gate supposed to work together or separate?

The gates should work together.

27 Are safeties required for both gates? Such as an outside safety loop in case a semi or longer vehicle is in the path of the gate?

No

28 Are high and low photo eyes required for both gates (for semi trucks)? Or just the standard photo eye location @ 24"?

High and low photo eyes are not required.

29 Are exit loops required for both gates? No 30 Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

Refer to SCR section 105.02(a) for water availability.

31 The gate details on 619-A show barbed wire on top of the gates but it is not written anywhere. Do the gates need barbed wire at the top? If so, does the 8' nominal height include the barbed wire?

No, barbed wire is not needed