Questions and Answers NM FS SNTFE310 263(1) Gallinas Canyon Road 8-26-26.pdf
PDF 141 KB Posted
- Attached to
- NM FS SNTFE310 263(1) Gallinas Canyon Road
- Solicitation number
- 6982AF26Q000019
About this file
This is a Questions and Answers document for federal contract opportunity 6982AF26Q000019, issued by the New Mexico Forest Service for the SNTFE310 263(1) Gallinas Canyon Road project, dated August 26, 2026.
The document addresses three clarifications received from potential offerors between August 19-25, 2026. First, regarding a quantity discrepancy for core drilling services, the government confirmed that offerors must use 210 linear feet of HQ3 core drilling for pricing and evaluation purposes, resolving a conflict between the Part II Schedule of Services and the detailed scope. Second, the government clarified that limited traffic control is required despite not appearing explicitly in the Statement of Work, specifying that while active measures such as flaggers or pilot cars are not necessary, contractors must furnish, post, and maintain advance warning signs in accordance with MUTCD standards and project specifications, and must maintain safe, continuous access for local residential traffic during timed windows since private residences exist along the corridor. Third, the government approved extending working and closure hours from one hour before dawn to one hour after dusk, contingent upon preservation of dedicated access windows for residents. These clarifications are binding amendments to the solicitation requirements for all offerors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A001.pdf | ||
| 6982AF26Q000019 NM FS SNTFE310 263 1 Gallinas Canyon Road.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6982AF26Q000019
NM FS SNTFE310 263(1) Gallinas Canyon Road
QuesƟons and Answers August 26, 2026
QuesƟons Answers
RECEIVED 8/19/2026
1. We noted a quanƟty discrepancy for core drilling. The Part II Schedule of Services lists
Core Drilling at 210 feet, while the detailed scope on page 20 states an esƟmated 201 linear feet of HQ3 core drilling.
Please confirm which quanƟty offerors should use for pricing and evaluaƟon purposes.
The correct quanƟty to use is 210 feet.
RECEIVED 8/25/2026
2. Traffic Control - It is not showing in the
SOW as being required but is showing on the bid schedule. Is it needed?
Yes, limited traffic control is required for this scope of work. While acƟve traffic control measures such as flaggers or pilot cars are not required, the Contractor must furnish, post, and maintain advance warning signs in accordance with the MUTCD and project specificaƟons. AddiƟonally, although the corridor is currently closed to the general public, private residences are located along the route. The contractor must maintain safe, conƟnuous access for local residenƟal traffic during Ɵmed windows.
3. Regarding working hours, can they be changed to 1 hour before dawn and 1 hour aŌer dusk?
Yes, extending the working and closure hours from one hour before dawn to one hour aŌer dusk is acceptable provided dedicated access windows for residents are preserved.