QnA 04.28.2026 COLM.pdf
PDF 81 KB Posted
- Attached to
- CO NP COLM 10(5), GUARDRAIL IMPROVEMENT
- Solicitation number
- 6982AF26Q000007
About this file
This is a Questions and Answers document issued on April 28, 2026, for the CO NP COLM 10(5) Guardrail Improvement solicitation.
The document addresses a discrepancy between items listed on SAM.gov and those in the bid schedule. The question raised that the SAM.gov solicitations page listed a Sign System (Solar Radar Flashing Speed Sign) requiring 1 each, while the bid schedule specified only wood posts requiring 5 each. The contracting officer clarified that a decision was made to use chevrons instead of the solar radar sign, which was subsequently removed from the RFQ. Bidders are instructed to use the bid schedule as the controlling document for pricing and quantities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment A002.pdf | ||
| QnA 05.01.2026 COLM.pdf | ||
| Amendment A001.pdf | ||
| CO NP COLM 10(5) Guardrail Improvement Plans.pdf | ||
| 6982AF26Q000007 RFQ .pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO NP COLM 10(5) Guardrail Improvement
April 28, 2026
Questions Answers 1 The items listed on the Sam.gov solicitations page vary from the items in the price schedule. Sign System (Solar Radar Flashing Speed Sign) calls for 1 EA on Sam.gov.
On the bid schedule, the only sign system is wood posts, and it calls for 5 EA.
It was decided later to use chevrons instead of the solar radar sign, so that was removed from the RFQ. Use the bid schedule.