This is a pre-bid presentation PowerPoint for the UT FLAP WEB 10(1) Causey Reservoir Access project, a Federal Highway Administration (FHWA) Central Federal Lands Highway Division contract. The project involves road reconstruction and infrastructure improvements in Weber County, Utah, focusing on Causey Road, Wheat Grass Canyon Road, and Skull Crack Road. The solicitation is a full and open competition with a HUBZone price preference, with a bid opening scheduled for November 18, 2025 at 2:00 PM MDT.

The project scope includes four primary components: Schedule A (0.65 miles of road reconstruction with intersection improvements and mechanically stabilized earth walls), Option X (Beaver Creek structure replacement), Option Y (0.56 miles of road improvements on Skull Crack Road), and Option Z (1.39 miles of road rehabilitation on Causey Road). Key project objectives include improving safety, sight distance, road geometry, drainage, and environmental compliance. Contractors must submit prices for all schedules and options, with the contract award going to the lowest responsible bidder. The project has a contract completion date of October 21, 2027, with no ground-disturbing work permitted prior to April 27, 2026.

View the file

Other files for this federal contract opportunity

Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UT FLAP WEB 10(1) Causey Reservoir Access Notice ID: 6982AF25B000014 Pre-Bid SHOWING October 7, 2025 US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Presentation Outline Project Partners Project Introduction Project Scope Details Contract Requirements & Solicitation Notes Questions US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Project Partners: Roles & Responsibilities Central Federal Lands Highway Division Project Manager: Tammy Eggers Designer: Roxannie Gonzalez-Sosa Geotech: Brendan McGarity Contracting Officer: Leslie Karsten Contract Specialist: Laura Slauter Construction Operations Engineer: Kevin Vanzo Project Engineer: Mike Dance

Federal Land Management Agency

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division Applicant and Maintaining Agency

Project Introduction: Location

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Project Introduction: Purpose & Need Modernize the corridor to meet current safety, environmental, and durability standards while preserving recreational access.

Need:

Safety: Improve sight distance, geometrics, and pavement to reduce crashes.

Ride quality & predictability: Create a consistent, comfortable corridor.

Infrastructure: Upgrade drainage, culverts, roadway integrity, and construct walls to provide a consistent corridor along Wheat Grass Canyon Road.

Environmental: Improve aquatic organism passage and environmental compliance.

Asset longevity: Extend service life and reduce long-term maintenance.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Schedule A Scope Details

Causey Road Reconstruction (Red): Three-way intersection improvements: Causey Road will be realigned to change the through movement traffic pattern to Causey Dam Overlook Road instead of Wheat Grass Canyon Road. This realignment would improve the sight distance, promote travel across the dam, and produce on-site material.

Wheat Grass Canyon Road Reconstruction (Orange): Proposed improvements for the first 0.46-miles will provide a 22-foot width through the paved areas and 5 (five) mechanically stabilized earth (MSE) walls (ranging from 9 to 19 feet tall) are required to provide a full two-lane roadway width at locations of severe outboard slope erosion. The proposed improvements will enhance driver safety, expectations, and ride quality by addressing existing conditions where the roadway transitions from two lanes to one and where pavement and aggregate surfaces vary.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Schedule A: Typical Section

Schedule A: Causey Road Reconstruction

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Schedule A: Wheat Grass Canyon Road Reconstruction

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option X Scope Details

Beaver Creek is conveyed through Causey Road via a bridge, 30-feet wide by 18-feet long, with a 7-ft tall concrete frame structure. The existing roadway width is 20-feet. The existing structure is approximately 50 years old and is located on Causey Road outside the forest. Bridge railings are functionally obsolete. Proposed improvements will replace the bridge with a 36-feet long, 22-feet span precast reinforced concrete three-sided culvert with precast reinforced concrete headwalls and wingwalls. Concrete seals will be required due to depth of foundations below water table.

Proposed crossing replacement will be a 3-sided prefabricated structure.

Shallow foundation design bearing on soil: Bearing capacity of soil and design parameters for earth pressures to aid in wingwall design are detailed in the geotechnical report.

One 3-week closure will be permitted between early September and mid-October or mid-November through late February. Road closures are to be coordinated with Bureau of Reclamation and Weber Basin Authority to ensure Causey Dam is accessible.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option X: Beaver Creek Crossing

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option X & Z:

Typical Section across Beaver Creek

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option Y Scope Details Skull Crack Road is currently aggregate surface and will be reconstructed to have consistent 22-foot typical section.

Minor roadway geometric improvements are needed to meet current design and safety standards.

The existing deteriorated 72-inch corrugated metal pipe is to be replaced with 12-ft span by 8-ft rise, concrete box culvert.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option Y: Typical Section

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option Y:

Existing Spillway Bridge Single-span bridge 27.5-feet in length with a clear width of 12-feet and an out-to-out width of 17-feet.

Tight curve approaches Load/width limits may restrict equipment access and affect Skull Crack Road production rates 2022 Inspection Report indicated the design was for HS20+Mod

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option Y: Project Coordination

Overflow Parking Lot Construction Season: 10.2025 through 12.2025 Contractor: K2 Excavation Construction LLC

Skull Crack Parking Lot & Boat Ramp Advertisement: Fall 2025 Construction Season: TBD Contractor: TBD

For additional information contact the Ogden Ranger District, 385-405-7100.

For project information visit: https://www.fs.usda.gov/r04/uinta-wasatch-cache

Amendment is forthcoming

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Project Introduction: Option Z Scope Details

Proposed improvements for Causey Road include rehabilitation of the existing roadway to provide 1.46 miles of 22-foot uniform paved roadway width to address deteriorated pavement. Culverts and guardrails will be replaced where necessary, and ditches will be rehabilitated where feasible.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Option Z Considerations:

Stations 124+68, 166+07, and 169+11

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

FINAL Geotechnical Report: July 2025

Section 2: Geology & Seismicity (FLAP & FLTP) Regional & site geology Geologic hazards: slope instability & rockfall Section 3: Subsurface Investigation (FLAP & FLTP) Summary of drilling investigation and laboratory test results Summary of site conditions Section 4: Analysis & Recommendations (FLAP only) Box Culvert Design & Culvert Retaining Structures Mechanically Stabilize Earth Wall Design Rock excavation anticipated at Wall 5 Temporary shoring likely necessary at taller wall segments Geomembrane and curb Earthworks (permanent and temporary), including rockfall catchment Construction considerations

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

FINAL Pavement & Materials Report: July 2025

Section 6: Pavement Recommendations & Discussions Rehabilitation Reconstruction Subexcavation Not in the Report, but in the plans/SCRs 403: Type 2 for temporary asphalt, no quantity Option Z Culverts: No FDR Causey Road Culverts

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

FINAL Hydraulics Report: May 2025

Section 5: Beaver Creek Section 6: Additional Considerations Major Drainage Culvert Cross Sections Embankment Protection Ditches Section 7: Recommendations Entrance treatment Outlet Protection

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Hydraulics Considerations All minor drainage structures will either be HDPE or concrete pipe. CMP culverts are not to be installed due to corrosive soils in the area.

Turf reinforcement mat has been specified for culverts discharging on slopes steeper than 1V:2H.

The major crossings at 107+03 (Beaver Creek) and 329+53 are both designed with aquatic organism passage (AOP) considerations. Streambed material will be required to install a low flow channel within each structure.

Due to the structure at 107+03 being an open bottom structure, foundations must be placed below the scour depths specified in project plans.

Along the northeast side of the 107+03 crossing, embankment protection is to be placed, tying into structure wingwall

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Special Contract Requirements (SCRs) 108: Prosecution & Progress The CO will issue a Notice to Proceed before commencement of any work. No ground disturbing work will occur prior to April 27, 2026.

The contract completion date is October 21, 2027.

If any or all of the Options (X, Y, and/or Z) are awarded, no additional contract time will be provided.

Stabilize all disturbed areas prior to the winter shutdown period 156: Public Traffic Request and obtain approval for full closures from CO at least 30 days in advance of intended use. CO must approve closures in writing prior to implementation. Provide public notice 15 days in advance of approved closure.

Restrictions on Causey Road and Wheat Grass Canyon Weber Basin Authority is the operators of Bureau of Reclamation Dam Boy Scouts of America 157: Soil Erosion Control, Sediment Control, & Stormwater Pollution Prevention Plan US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Contract Requirements 203: Removal of Structures & Obstructions 205: Rock Excavation Rock blasting not permitted due to vibration concerns with nearby dam structure Use alternative methods for controlled rock removal:

Mechanical removal: hydraulic splitting, hydraulic breakers Chemical removal: Non-explosive demolition agents (NEDA) Submit a general Rock Excavation Plan At least 21 days prior to excavation operations Allow 14 days for CO approval (FP-14 104.03 (a) (1)) US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

255: Mechanically-Stabilized Earth Walls Wall fascia: Segmental Retaining Wall Unit (SRWU) or Concrete Panel Contractor to select wall facing type by pre-design conference. Provide photos, details, and color options (SCR 257).

Provide physical sample of selected unit and color for final approval prior to wall construction.

Provide temporary rockfall protection for the spillway and other facilities beneath the construction area of Wall 1 (SCR 651).

Appropriate closures of the reservoir, or other measures, to be implemented by USFS for public safety during construction of walls 2 – 5. Coordinate with CO at least 30 days prior to excavation of walls 2 – 5.

257: Contractor-Designed Retaining Walls Provide submittal at least 90 days before starting construction Allow 30 days for CO approval (FP-14 104.03 (a) (2))

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

625: Turf Establishment: Perform all seeding between October 15 and November 30, between May 5 and May 30 or both.

628: Temporary Stream Diversions 647: Streambed Material Mitigation for Beaver Creek and Skull Crack box culvert replacements 651: Temporary Rockfall Protection to provide work site safety, protect equipment, existing infrastructure (spillway) and Causey reservoir recreational users.

Contractor responsibility: Temporary rockfall protection for existing infrastructure beneath the Wall 1 excavation USFS responsibility: Walls 2 – 5 (SCR 255) Submit temporary rockfall protection plan At least 14 days prior to beginning excavation of Wall 1 Allow 14 days for CO approval (FP-14 104.03 (a) (2)) US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Procurement Schedule October 2, 2025: Project Advertisement October 7, 2025: Pre-Bid Presentation and Site Visit 11/10/2025: Deadline for Technical Questions Tentative Dates & Subject to Change 11/18/2025 2:00 PM MDT (Refer to Sheet A-1 in IFB): Bid Opening Date 02/02/2026 (Refer to page A-3 in the IFB): Guaranteed NTP Date

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

This is procurement schedule, is the restriction O& completion dates necessary for this slide? Compare with the last version to see the changes.

Bid Documents and Physical Data Project Plans and Cross Sections Invitation for Bid with Appendix Standard Specifications (FP-14) FINAL Geotechnical Report FINAL Pavement & Materials Report FINAL Hydraulics Report Design Physical Data & Reports (Section 152)

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Solicitation Notes Procurement Competition: FULL & OPEN COMPETITION (with HUBZone Price Preference) Basis for Award: Refer to page A-5 in the Invitation for Bid (IFB).

"To be eligible for award of contract, the offeror shall submit prices for each item in Bid Schedule A, Option X, Option Y, and Option Z. Accordingly, contract award will be made to the lowest responsible bidder conforming to the solicitation, provided funds are available and the Contracting Officer determines the price to be reasonable. In addition, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for Schedule A. Evaluation of options will not obligate the Government to exercise the options.

FAR 52.214-6 Explanation to Prospective Bidders Technical questions accepted until November 10, 2025 at 4:00 PM MDT.

Email questions to CFLContracts@dot.gov Refer to Sheet A-iii in IFB Submit all questions in writing to CFLContracts@dot.gov. Questions will be answered, and posted on www.sam.gov

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Solicitation Notes Documents to include with bid (refer to page A-i in IFB):

SF1442 signed (pages A-1 in IFB) Acknowledge amendments on SF-1442 Amendments will be posted to sam.gov Indication of interest of formal Partnering (page A-6 in IFB) Bid Schedule with prices for all items (pages A-7 to A-21 in IFB) Completed Authority to Bind certificate (pages A-22 to A-26 in IFB) Buy American Act & Hazardous Materials (pages A-27 and A-28 in IFB) Bid guarantee, FAR Clause 52.228-1, bid bonds must be originals (pages B-1 and B-2) Completed Bidders Information (pages B-3 to B-6 in IFB) Completed VETS-4212 declaration (page A-ii in IFB) Also, please see Notice of SAM Registration on page A-ii

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Bid Opening

Bid Opening Time on page A-1 of IFB, box 13. Currently scheduled for November 18, 2025 at 2:00 PM MDT. Originals must be received by this time.

Bid Opening Location in box 8 of page A-1 of IFB Bid Modifications submitted by Contractors: Follow instructions on sheet A-ii of IFB. Electronic modifications to bids are allowed up until bid opening time.

Bid results will be posted to sam.gov immediately after bid opening. You may attend bid opening in person if you prefer.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Questions Thank you for your interest in this project.

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Site Visit Etiquette

Meet at Weber Memorial Park Entrance at 1pm.

Consolidate vehicles to extent practical as parking is limited.

Questions must be asked to FHWA-CFLHD and to the Group to ensure fair opportunity.

Last stop at Beaver Creek

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

US Department of Transportation | Federal Highway Administration | Central Federal Lands Highway Division

Meet at Weber Memorial Park Entrance at 1pm.

Consolidate vehicles to extent practical as parking is limited.

Questions must be asked to FHWA-CFLHD and to the Group to ensure fair opportunity.

image1.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image20.png image21.png image22.png image23.png image24.png image25.png image26.png image27.png image28.png image29.jpeg image30.png image31.png image32.png image33.png image34.png image35.png image36.png image37.png image38.png image39.png