This document is a Questions and Answers (Q&A) file for the AZ FLAP PIM FR510(1) Sabino Canyon Park Road project, dated August 18, 2025. The Q&A addresses 23 technical and procedural inquiries from potential contractors, covering topics such as construction water sources, gabion wall measurements, hydro-seeding specifications, project phasing, and work constraints. Key details include a potential contract award in September 2025, a Notice to Proceed typically issued 30-44 days after bid opening, and specific environmental restrictions, such as limitations on stream work during gabion wall installation and considerations for Mexican Spotted Owl habitat. The document provides guidance on various technical specifications, including concrete placement, restroom installation timelines, and hydro-seeding requirements, with references to specific federal specifications (FP-14 and SCR sections) for detailed compliance.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6982AF25B000006

AZ FLAP PIM FR510(1) Sabino Canyon Park Road

Questions and Answers August 18, 2025

Questions Answers

RECEIVED 8/11/2025

1. Michael Stanley with Mt. Lemmon Water District was contacted and Nathan returned the call stating that Stage 3 Water restrictions are in place and construction water is not available. Will it be possible to pull construction water from Rose Canyon Lake?

Contractor responsible for identifying construction water source.

2. Item Number A0520 GABIONS is paid by the square foot. FP-14 253.10, " When measuring gabions by the cubic yard (cubic meter), measure in the structure. Measure foundation fill under Section 208." The bid schedule does not have a line item for 208 Structural excavation and backfill. Please define the measurement for Gabions? Is it the front face of the wall excluding footings or including footings? If it excludes, are footings incidental or to be paid under another item?

A0520 Gabions is to be paid as stated in section 253.10 of the FP-14. In situations where there is lack of a pay item, all work associated with A0520 should be considered incidental with all aspects of inspection and testing requirements to be met.

In addition, the pay item for gabions is by square foot intentionally as the width of foundation grading and granular backfill is based on the bottom gabion dimensions which will be up to the contractor and their design. The area provided excludes the footings.

3. Currently lead times on CXT vault restrooms are 120 - 150 days. Assuming the contract is awarded September 18th and restrooms are submitted and approved by October 18th. 150 days puts delivery on March 17th. This only allows 34 working days to install the restrooms and all surrounding work. Can the contract completion date be pushed into June.

To be coordinated with CO. Current restrictions to Mexican Spotted Owl habit could conflict with contract completion date extension.

4. Please confirm for concrete placements using a hydration stabilizer admixture that FP- 14 552.03 (I) (3) "maximum allowable design discharge time is 3½ hours," will not apply.

Bid as advertised. FP-14 552.03(I)(3) will apply on this contract. The project is not that remote. 1.5 hours from Tucson. The 3.5-hour discharge time should not be a problem.

Questions and Answers August 18, 2023

That the manufacturer's recommendation on delay will apply.

5. 566.11 Acceptance. "For the sculpted shotcrete, upon approval of shop drawings, construct a 48 inch x 48 inch architectural shotcrete mockup panel for approval. Contact CO a minimum 48 hours prior to inspection."

Can these test panels be constructed at a contractor yard in Tucson?

Time and location to be discussed and agreed upon by Contractor and CO or CO’s on-site representative.

RECEIVED 8/12/2025

6. Hydro-seeding Questions:

1. A1400/ 62510-2000 Seeding Hydraulic Method 2.10-acre area

2. A1420/ 62515-3000 Mulching Hydraulic Method, Bonded fiber matrix 2.10 – acre area

Are they looking for a price for both types of applications? To determine which one to go with? Or Will We be performing both applications? Meaning will seeding Hydraulic method then go back and Hydraulic mulching a second application over the first application?

3. I do not see any seeding specifications regarding

. What type of fertilizer if any to be used and the application rate . How many pounds of wood fiber mulch per acre area . How many pounds of fiber matrix per acre area . How many pounds of ADOT Compost mix per acre if any . Will there be any lime application? If so, how many pounds per acre area

Here Is a standard application mix

Answer for 1 & 2: Yes. They should price applications for both seeding and mulching.

Answer for 3: Perform seeding hydraulic method to meet the requirements of FP-14

625.07 and 713.04, 625 and SCR 713.04 and

625. Perform mulching hydraulic method, bonded fiber matrix to meet the requirements of FP-14 625.08 and SCR

713.05 (g)

Questions and Answers

. Wood fiber mulch 2,000 pound per acre area . 16-2-0 fertilizer 300 pounds per acre area . ADOT Compost 300-400 pounds per acre area . Lime at 300 pounds per acre area

7. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

Follow specification FP-14 section 153.02(a)(1).

8. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Refer to FAR Clause 52.249-14 Excusable Delays

9. Please provide the site visit registration information.

There is no organized site visit.

10. Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

Contractor responsible for identifying construction water source.

11. Does this project require phasing? No phasing of the construction is required.

See SCR 108.01 and 156.07 for limitations and requirements regarding timing and public access.

12. Please provide lay down/staging area for construction.

Refer SCR 105.04

13. Can we shut down roadway access or do we need to maintain one lane for travel?

Refer SCR 156.07

14. Confirm traffic can be rerouted to detour as shown in the plans.

Refer to Temporary Traffic Control Plan Sheets and SCR 156.07

15 What are the limitations for construction intervals (for proposed road work)?

Refer SCR 156.07

16. Is there an anticipated start date? The CO will issue a Notice to Proceed – Typically 30 days between bid opening and award and 14 days between award and NTP.

**Subject to change.

17. Is testing required? Refer to SCR’s for testing requirements

18. Is an SWPPP required? Refer SCR 157

19. Is silt fencing required along each side of the roadway?

Determining the BMPs for the SWPPP will be the responsibility of the contractor.

Questions and Answers

20. Please further define line A1340 62302-

1000 SPECIAL LABOR, HIRED TECHNICAL

SERVICES from the pricing schedule.

Intent of the line item is to be used for labor necessary to perform work outside that which is framed by the contract documents.

Use of this line item must be discussed and confirmed with the CO prior to its use.

21. What in-water work window, access constraints, dewatering/flow-bypass measures, and BMPs apply to constructing the gabion wall adjacent to Sabino Creek?

1. The only PCN authorized activity is placing rip rap as permanent impacts in the stream. That is allowed and equipment that makes temporary impacts can be used to place riprap. Work should occur during low flow season.

2. All impacts to the stream during rip rap placement must be completely restored.

3. No activity is authorized in the stream regarding gabion wall installation – so no stream work is permitted in the stream during wall placement.

4. No activity is authorized like stream diversions or bypasses.

5. No activity is authorized for stream dewatering.

22. Are archaeological services required for this project? If so, is the contractor required to provide these?

No

23. Please provide details for the Kiosk that is required. Is this to be government furnished/ contractor installed?

Is this a pre fabricated item?

Refer SCR 646.05 and 713.22 and Kiosk Plan Details