This document is a Questions and Answers file for the OK ERFO NP CHIC 2024-1(1) Veterans Lake Trail Bridge federal contract opportunity. The document contains two questions from potential bidders and the corresponding government responses, dated April 17 and 18, 2025. The first question seeks additional information about the submerged existing bridge, with the government noting the bridge's weight is roughly estimated at 70,000 lb, but its condition and underwater characteristics are unknown. The agency directs bidders to SCR Subsection 203.04 for requirements on developing a bridge removal plan. The second question inquires about warranty periods, to which the government plainly states "There are no warranties for the project." Both responses indicate significant uncertainty around the existing bridge's condition and minimal guarantees for the contract work.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for OK ERFO NP CHIC 2024-1(1) Veterans Lake Trail Bridge
April 17, 2025
Questions Answers 1 Can you please provide additional information on the Submerged
Bridge? The drawings give the length and width of the bridge.
We need to be able to calculate the Weight of the submerged bridge.
If the original submittals are available, they would provide all the necessary information. We suspect this was a performance specification from looking at the drawings as there is very little information provided.
The weight of the existing bridge is unknown, but roughly estimated to be 70,000 lb; with, the bridge condition and underwater weight/buoyancy also unknown. It is unknown if the existing bridge is intact, or if it is lodged in the lakebed. The only information known about the existing bridge is provided in the physical data as listed in FAR Clause 52.236-4. Refer to SCR Subsection 203.04 for requirements to develop a bridge removal plan, including assessment and documentation of existing bridge conditions.
April 18, 2025
Questions Answers 2 We can find no reference within the bid documents to the required warranty period associated with this contract, and the typical government FAR clauses which address warranty (FAR 52.246- 21 or Subpart 46.7) do not seem to be included by reference. Can you please clarify the required warranty period associated with this contract or direct the bidders where this information can be found?
There are no warranties for the project.