This document is a set of Questions and Answers related to Solicitation Number 6982AF24Q000012 for a Geotech Drilling project on California FLAP SR89(3) near Lassen Peak. The project consists of geotechnical drilling along 4.4 miles of State Route 89 in Tehama County, California. The drilling locations will be at 0.30-mile increments, alternating between the two traffic lanes. The agency is the Department of Transportation Federal Highway Administration. Key details include:
- 18 drilling locations are required, with 10 five-gallon buckets needed for subgrade samples (not every boring will require a sample).
- 6-inch augers may be used instead of 8-inch augers.
- No official start date is provided, but the work is planned for September or October.
- No cost estimate or budget information is provided, as this is a simplified acquisition.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6982AF24Q000012
Ques�on and Answer
Geotech Drilling – CA FLAP SR89(3) Lassen Peak July 30, 2024
Question Answer
1. Question regarding the locations of the borings.
Will they be on one side of the roadway?
Or say nine on the north bound and nine on the south bound.
This affects the time to move the traffic control devices which will affect the time frame to complete the drilling.
This information is necessary to obtain a cost from the firm who will be performing the traffic control and prepare the traffic plan.
The road will be drilled at 0.30-mile increments with the borings alternating between the two drive lanes.
2. The scope of work states 18 drilling locations, but the text says 10 five-gallon buckets. Does that supposed to be 18 five-gallon buckets?
We need 10 five-gallon buckets. Subgrade samples will not be collected for every boring.
3. Our drill rig is equipped with 6” auger. Is there an issue with 6” augers. It does not affect the drilling or sampling.
A 6” auger may be used instead of an 8” auger.
4. Is there a cost estimate, budget or ballpark figure for the project listed?
We do not provide cost estimates for simplified acquisitions.
5. Is there an actual start date for the project?
There is no official start date. Work will be accomplished either in September or October.