This document is a set of Questions and Answers related to a federal contract opportunity for the CO FLAP CR300(1) Browns Canyon Access Road (Solicitation Number 6982AF24B000008). The project scope is to widen 0.10 miles of an existing roadway to a consistent 22-foot gravel surface and provide geometry and sight distance improvements. Key details include:
Blasting is anticipated for the project, with rock bolts to be installed as needed. The solicitation has a seeding window of 10/15/24 to 11/15/24 and a contract completion date of 12/11/2024. There will be river monitoring and limitations on river traffic during blasting activities. The solicitation was originally due on 4/16/24 but has been extended, with a notice to proceed anticipated approximately 2 weeks after contract award in mid to late May. Bidders must submit a printed copy of the bid with original bid bonds. There are no designated staging areas or water sources, which are the contractor's responsibility.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO FLAP CR300(1) Browns Canyon Access Road
6982AF24B000008
March 20, 2024
Questions Answers 1 Is Blasting anticipated on this project? Yes, blasting is anticipated. For more information, refer to
SCR 108, 156, 205, 206,
Construction Plans: B3, C1, D1 & cross sections Geotech Report
Pre-Bid Meeting April 4, 2024
2 Is there any chance we could submit the original bid online? No, submit a printed copy of your bid with original bid bonds according to Sheet A-i of the Invitation for bid.
3 The plans says the swell factor is 160%, is that correct? What method is used to measure area and quantity of rock excavation?
Correct, the swell factor for measuring rock excavation is 160% based on a loose placement. Refer to the grading summary on Plan Sheet B3.
Prismoidal surface to surface volume was used for calculations.
4 Is there storage for materials on site? Refer to Special Contract Requirements Subsection 105.04 in the IFB.
Storage areas are to be secured by the contractor.
5 Where are the rock bolts intended to be installed? The rock bolt placement is at direction of the CO, so it will be based on field conditions as exposed during rock excavation during construction.
They are included in the contract to stabilize rocks that are unstable but cannot be removed by traditional slope scaling activities. Refer to Sheet B1 in the plans.
6 If the road closure is after September 2nd, how is the weather during that time?
Weather during this time of season was vetted with the partners. Weather will be getting colder, and some snow may happen. The project is south facing, so if there is any snowfall, it should melt quickly. Refer to FP-14 Subsection 108.03 for weather delay information.
7 Are there predetermined staging areas and source of water that's also 105?
There are no designated water sources. The contractor is responsible for sourcing water. Refer to Section 105.04 of the FP-14 and SCR’s.
8 Please confirm the seeding window. The seeding window is 10/15/24 to 11/15/24. Refer to Subsection 625.11 of the SCR’s.
9 When is the anticipated notice to proceed? Notice to Proceed will be given approximately 2 weeks after award of the contract (award will be in accordance with the Basis for award on Sheet A-4 of the IFB, and NTP is dependant upon contractor returning required acceptable documents in a timely fashion). Contract award is anticipated mid to late May. Ground disturbing activities will commence in accordance with SCR Subsection 108.01.
10 The disposal area for the excavated materials, how far is that exactly from the site of blasting?
It is approximately 8 miles.
11 What is the construction duration from September? Ground disturbing activities will start after September 2, 2024, and the contract completion date is December 11, 2024. Refer to Subsection 108.01 of the SCR’s.
12 For the river monitoring, I guess I'm not familiar with that river.
How heavy is the river traffic and I presume we'll just have to wait for an open window for blasting opportunities or will there be a way to stop river traffic?
Refer to SCR’s Subsection 156.04 for the Public Information Officer, river monitor, and the duties required. The Public Information Officer will provide a blasting schedule to the county and partner, and they will help notify the public and rafting companies of closures related to the blasting activities. There will also be a river monitor 1500 feet upriver to waive any public river users to the shore.
13 So, there will be some limitation with the commercial companies in regards to rafting at times of blasting?
Yes, there will be.
14 Is there possibility that that the invitation for bid will get extended past April 16th.
Refer to Amendment A001.
Questions received April 5, 2024
15 Is there any staking currently on site? No 16 Is the top of the cut currently staked on site? No 17 Can you show the cut line on the photos from sheet D1 in the drawings?
No, the photos are to provide visual context of the existing material to be excavated.