CO FLAP CR300(1) Browns Pre-Bid Meeting V2.pdf
PDF 5 MB Posted
- Solicitation number
- 6982AF24B000008
About this file
This document is a pre-bid presentation for a federal construction project to improve the main access road to the Browns Canyon National Monument in Colorado. The project aims to widen the narrow "Narrows" section of the road from 10 feet to 24 feet, improve sight lines and surface conditions, and remove a blind curve. Key details include:
The project has a set completion date of December 11, 2024, with restrictions on the timing of ground disturbing activities, closures, and blasting operations. Key contract requirements address prosecution and progress, public traffic, and erosion/sediment control. The procurement schedule includes a pre-bid presentation on April 4, 2024, with bids due by April 16, 2024 and a tentative contract award in May 2024. The project is a Total Small Business Set-Aside, with the award to be made to the lowest responsive, responsible bidder. Bid documents include construction plans, specifications, a geotechnical report, and required forms.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CO FLAP CR300(1)
Browns Canyon National Monument Access Road
NOTICE ID: 6982AF24B000008
PRE-BID MEETING
APRIL 4 , 2024
1US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION https://sam.gov/opp/dd8f631fdf6646bd8bbc07da18831198/view#general
Presentation Outline Project Partners
Project Introduction
Project Scope Details
Project Photo Log
Contract Requirements & Solicitation Notes
Questions
2US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Project Partners: Roles & Responsibilities
Central Federal Lands Highway Division
◦ Project Manager: Tammy Eggers
◦ Designer: Matt Steiner & Heidi Hirsbrunner
◦ Geotech: James Arthurs
◦ Contracting Officer: Leslie Karsten
◦ Contract Specialist: Eric Grosskreuz
◦ Construction Operations Engineer: Ryan Balchuck
Land Management Agency
Applicant
Maintaining Agency
3US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Project Introduction: Location
4US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Project Introduction: Purpose & Need Improve the main access road to Brown’s Canyon National Monument, the only federal public land recreation site in Chaffee County.
Improve severe safety deficiencies through the “Narrows”
◦ Widen the “Narrows” from 10 feet to 24 feet & provide consistent lane widths
◦ Improve sight line, width, and surface conditions. Remove the blind curve
5US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Project Introduction: Scope Details The project corridor has difficult and limited working areas, geotechnical hazards, and more technical work elements to include:
◦ Rock excavation (blasting) adjacent to environmental sensitive resources
◦ Rock scaling near environmental sensitive resources
◦ Replacement of aggregate surfacing, approximately 0.10 miles
High level of stakeholder coordination, along with associated scrutiny during construction activities
◦ Browns Canyon National Monument Visitors
◦ Commercial rafting companies
6US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Construction Plans: Typical Section & C Sheet
7US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Construction Plans: D Sheet
8US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Construction Plans: Grading Summary
9US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Final Geotechnical Report: September 2022 Section 2: Geology & Seismicity
◦ Several different geologic regions
◦ Geologic hazards: flooding & rockfall
Section 3: Field Exploration
Section 4: Analysis & Recommendations
◦ Rock Slopes
◦ Rock Slope Rounding
◦ Subexcavation allowance
◦ Potential for shallow groundwater
10US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Contract Requirements 108: Prosecution & Progress
◦ No ground disturbing activities until after 9.02.2024.
◦ No closures until after 9.08.2024.
◦ No weekend work allowed from notice to proceed through 10.31.2024.
◦ Once drilling and blasting operations begin, complete all drilling, and rock blasting work in a 4 week period.
◦ Complete work by 12.11.2024
156: Public Traffic
◦ Public Information Officer
◦ River Monitor
◦ Public notice at least 2 weeks in advance of blasting
◦ 2 week look ahead
◦ Closures: Weekdays requires 12-1 pass through
157: Soil Erosion Control, Sediment Control, & Stormwater Pollution Prevention Plan
11US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Contract Requirements 203: Removal of Structures & Obstructions
◦ Deliver the removal of the existing traffic signal system, including buried conduit, pipes, and signs to Chaffee
County, Staging Yard (613 Gregg Dr., Buena Vista, CO 81211)
◦ Haul excess material generated from excavation to Chaffee County Staging Yard
205: Rock Excavation
◦ Cushion Blasting
◦ General Blasting Plan
◦ No ammonium nitrate and fuel oil (ANFO) for controlled blasting
◦ Do not use blasted material for embankment
260: Rock Bolts and Dowels
625: Turf Establishment: Seeding window is 10.15.2024 to 11.15.2024
12US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Photo Log: General Conditions
13US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Photo Log: General Conditions (Cont.)
14US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Photo Log: General Conditions (Cont.)
15US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Procurement Schedule
• March 15, 2024: Project Advertisement
• April 4, 2024 2:00 PM MDT: Virtual Pre-Bid Presentation
• April 9, 2024 at 4:00 PM MDT: Deadline for Technical Questions
• Tentative Dates & Subject to Change
• April 16, 2024 2:00 PM MDT (Refer to Sheet A-1 in IFB): Bid Opening Date
• Week of May 13, 2024: Contract Award
16US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Bid Documents and Physical Data
• Project Plans and Cross Sections
• Invitation for Bid with Appendix
• Standard Specifications (FP-14)
• Geotechnical Report
• Pavement Memo
17US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Solicitation Notes
• Procurement Competition: Total Small Business Set-Aside (FAR 19.5)
• Basis for Award: Refer to page A-4 in the Invitation for Bid (IFB).
◦ "To be eligible for award of contract, the offeror shall submit prices for each item necessary to complete all contract work in Schedule A. Accordingly, award of contract, if made, will be made to the lowest responsive, responsible bidder, if funds are available and the Contracting Officer determines the price to be reasonable."
• FAR 52.214-6 Explanation to Prospective Bidders
• Technical questions accepted until April 9, 2024 at 4:00 PM MDT.
• Email questions to CFLContracts@dot.gov
• Refer to Sheet A-ii in IFB
• Submit all questions in writing to CFLContracts@dot.gov. Questions will be answered, and posted on www.sam.gov
18US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION mailto:CFLContracts@dot.gov
• Documents to include with bid (refer to page A-i in IFB):
• SF1442 signed (pages A-1 in IFB)
• Acknowledge amendments on SF-1442
• Amendments will be posted to sam.gov
• Indication of interest of formal Partnering (page A-9 in IFB)
• Bid Schedule with prices for all items (pages A-6 to A-8 in IFB)
• Completed Authority to Bind certificate (pages A-10 to A-14 in IFB)
• Buy American Act & Hazardous Materials (pages A-15 and A-16 in IFB)
• Bid guarantee, FAR Clause 52.228-1, bid bonds must be originals (pages B-1 and B-2)
• Completed Bidders Information (pages B-3 to B-6 in IFB)
• Completed VETS-4212 declaration (page A-ii in IFB)
19US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
• Bid Opening:
• Bid Opening Time on page A-1 of IFB, box 13. Currently scheduled for April 16, 2024 at 2:00 PM MDT. Originals must be received by this time.
• Bid Opening Location in box 8 of page A-1 of IFB
• Bid Modifications: Follow instructions on sheet A-ii of IFB. Electronic modifications to bids are allowed up until bid opening time.
• Bid results will be posted to sam.gov immediately after bid opening. You may attend bid opening in person if you prefer.
20US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
Questions THANK YOU FOR
YOUR INTEREST IN
THIS PROJECT.
21US DEPARTMENT OF TRANSPORTATION | FEDERAL HIGHWAY ADMINISTRATION | CENTRAL FEDERAL LANDS HIGHWAY DIVISION
| CO FLAP CR300(1) Browns Canyon National Monument Access Road |
| Presentation Outline |
| Project Partners: Roles & Responsibilities |
| Project Introduction: Location |
| Project Introduction: Purpose & Need |
| Project Introduction: Scope Details |
| Construction Plans: Typical Section & C Sheet |
| Construction Plans: D Sheet |
| Construction Plans: Grading Summary |
| Final Geotechnical Report: September 2022 |
| Contract Requirements |
| Contract Requirements |
| Photo Log: General Conditions |
| Photo Log: General Conditions (Cont.) |
| Photo Log: General Conditions (Cont.) |
| Procurement Schedule |
| Bid Documents and Physical Data |
| Solicitation Notes |
| Solicitation Notes |
| Solicitation Notes |
| Questions |