QnA 10.26.23.pdf
PDF 297 KB Posted
- Solicitation number
- 6982AF23B000029
About this file
This document contains questions and answers from a pre-bid meeting for a federal construction contract to improve trails and install trail crossings at the Rocky Flats National Wildlife Refuge in Colorado.
The contract involves constructing new aggregate surface trails, installing prefabricated pedestrian bridges over Woman Creek and Rock Creek, constructing a precast concrete box culvert underpass of State Highway 128, and installing related signs and fencing. The work must be completed by April 1, 2025 with liquidated damages of $3,500 per day for delays. Bids were due on November 1, 2023. The Federal Highway Administration is the contracting agency. Access to the project site is controlled by the Refuge and arrangements must be made in advance. No temporary work areas or access roads beyond what is shown in the plans will be permitted.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for CO FTFW ROFL TRAILS(1) – CO FLAP JEF128(1): ROCKY FLATS NWR TRAILS – TRAIL CROSSINGS
6982AF23B000029
October 2, 2023
Questions Answers 1 Is it possible to set up a site visit?
For access to the site, please contact the Refuge at (303) 289-0232 at least 24 hours in advance.
Refer to Amendment A001
October 3, 2023
Is there water available for use as dust control onsite?
No, there is not water source on site for dust control.
2 What is the thickness of the existing SH128? No details of depths of aggregate base & asphalt were provide in the drawings, specifications, nor geotechnical report.
Contractor will be responsible for determining existing thickness and match.
3 Can excess excavated materials be left onsite? If so what location?
The excess excavated material cannot be left beside the road or trail. The FWS Refuge can accept about 100 CY of excavated material to be stockpiled within the Refuge at the location identified by FWS.
4 Will Cast-In-Place Headwalls, Toewalls, and Wingwalls be allowed in lieu of Pre-Cast on the box culvert?
No, please follow the plans and specification. See Sheet S1 and SCR 602.03
5 Please confirm the size of rip-rap to be placed at the Woman Creek bridge. RG3255-A shows Class 3 while RG3255-E shows Class 1?
The proposed rip-rap at the Woman Creek bridge should be Class 3. The rip-rap shown on RG3255-E should be Class 3.
6 Cement industry has converted over to produce a Type IL cement locally in lieu of a Type I/II cement. Please confirm this is acceptable?
Type IL cement is acceptable. Plan sheet S-2 has been revised accordingly.
7 What is the schedule for the Trails by Others to be installed? Will they be installed before or after this project is complete?
The Trails By Others is anticipated to be complete by Spring 2024.
8 Is there a designated route to access the section of new trail East of Indiana St? There appears to be a gate to access along the powerlines that could be utilized.
The gate on the east side of Indiana St is owned by Westminster. During the project development, project team has gained access to the area by contacting Joe Reale jreale@cityofwestminster.us 303-658-2142 (office) 303-919-0990 (mobile).
October 4, 2023
1 Will a CAD file be provided?
CFL will provide CAD information to the successful bidder as listed in Section 152.
2 Can an RCP pipe and manhole/catch basin profiles be provided for the proposed 18” RCP pipe sections? Sheets C1 & C2 (and T1) reference these runs briefly but do not appear to show where they tie in to on the upstream side. Are these to daylight at the “berm with ditch” or are they plugged at the ends as shown on sheet T1?
Profiles are shown on Sheet Z1. They are to daylight at the ditch behind the berm.
3 Can more info be provided on the 5’ x 5’ resting interval? Is this a square section/pad of aggregate? Or does this refer to a physical structure of some sort for hikers to rest?
See Typical section on A8
4 Can you provide profiles of the pipe run to include inlet and manhole heights?
Profiles are shown on Sheet Z1.
5 The ITB SOE indicates we cannot start he project until September 2024 and must be complete by April 2024. What is the reasoning for the project starting a year after the project has bid and can we start it earlier?
The contract completion date for the project is April 1, 2025. The reasons for issuing a Notice to Proceed in advance of the start of on-site ground disturbing work are the lead time for the bridge superstructures, to avoid multiple mobilizations and minimizing the amount of onsite construction activities. CFL will evaluate revision of the proposed construction schedule from the successful bidder.
6 Will the FWHA allow us to submit cost escalation after award, if any, with the contract start date being a year after the project bids?
No, this is a firm fixed price contract.
mailto:jreale@cityofwestminster.us
7 During the site visit on 10/3/23 we noticed that Woman Creek and Rock Creek bridges are very difficult to access, with rock creek being almost impossible. We also noted in the bid schedule that the line item for site remediation is very small. Will FHWA allow the awarded contractor to build temporary access roads. If so where should these costs for construction of temp roads and reclaiming the area of temp roads go in the bid form? We assume this would be lumped in with the cost of the bridges under those line item numbers, is that correct?
FWS has provided use of their access roads as shown on the site map Sheet A4. No temporary roads are anticipated. Also, the Trails by Others are scheduled to be complete by Spring 2024.
8 There is a lump sum item for soil erosion control on the bid schedule, but there are no erosion control items shown on the plans. Are we required to design the erosion control measures ourselves?
Yes. See Section 157 of the Special Contract Requirements and Pay item 15720-0000.
9 Several of the items on page 2 of 5 on the plan set for the CO 128 Pedestrian Underpass are not practical or needed with precast box, or are already addressed by the appropriate CDOT and ASTM specs. Given this can you confirm that a precast box culvert per ASTM C1577 and CDOT M603-3 with joints per ASTM C990 is acceptable, with no other requirements deemed to apply?
CDOT details may be used if they meet the requirements listed in the plans and specifications.
10 The details on sheet 4 of 5 depict box culvert with no haunches in the lower corners. In order to allow for a precast box culvert, can haunches in all 4 corners be acceptable?
Yes. Please refer to revised Sheet S4 and S5.
11 Details on sheets 4 and 5 of 5 depict box culvert with precast headwalls, wingwalls and toe walls. Would it be acceptable for the precast box to be supplied with 12” of exposed reinforcing to be tied into reinforcing for cast in place headwalls, wingwalls and toe walls?
No, please follow the plans and specification. See Sheet S1 and SCR 602.03
October 5, 2023
1 Q1: Will there be any allowance for camber?
Q1 Note: Matching the straight-line profile of the trail can be problematic for the final design. Allowance for some % of camber, no matter how small, can greatly benefit the geometry of the bridge. (Reference Spec Section 555.03-F-5 for bid note on bridge camber)
Please see general notes on Plan Sheet S7,S16, and S25
2 Q2: Will the 2” min. concrete cover dimension apply to the top of the concrete slab only?
Q2 Note: There are guide spec allowances for reinforcement adjacent to stay-in-place steel deck forms that would be less than the 2” stated on the plans. (See Reinforcing Steel note on sheet General Notes & Estimate-All Bridges for min. dimension)
Concrete cover note is for typical cast-in-place concrete.
Exceptions per design specifications for steel deck forms are permitted.
3 Q3: Is there additional info regarding the design and location of the pedestrian fence?
Q3 Note: I see no other details or specifications for a pay item resembling a pedestrian fence located on the prefabricated bridge. (See Prefabricated Steel Bridge note on sheet General Notes & Estimate-All Bridges for pedestrian fence reference)
Note is intended for all elements that make up the truss. No additional fence is meant to be attached to the bridge.
4 Q4: Does the steel handrail located 42” above the deck need to be ADA rail? Should the 3’-6” height dimension be to the middle of the handrail, as shown on the plans, or to the top of the handrail as typically measured?
Q4 Note: The available detail shows something more in line with a non- ADA rubrail, with height measured to the center of the rial. We want to clarify rail style due to the specific usage of “handrail” in multiple locations which would usually imply ADA style rail requirements. Also we hope to clarify the height offset measurement. (See railing detail from bid documents below)
ADA style rail is not intended for these bridges. The railing shown on the plans is intended to be a rubrail with the height to the top of rail.
5 Q5: Is there a min./max gap dimension between the 6” kick plate and concrete deck?
Q5 Note: The available detail shows an angle flush to the deck. Is this angle acting as a curb element? Should a gap be assumed between the bottom of the kick plate and the top of the concrete deck for drainage?
(See kick plate detail from bid documents below)
Kick plate is meant to act as curb that is flush with the deck.
6 Q6: Is there allowance for a steel end dam section that would be adjacent to the bridge expansion joint seal? Will a cover plate over the joint opening be required?
The joint filler is meant to be in lieu of a cover plate and end dam, contract plans should be followed, with no cover plate necessary.
Q6 Note: The available detail shows a preformed joint filler installed adjacent to a concrete deck slab with no cover plate. (See joint detail from bid documents below)
7 Q7: Will the final trail elevation account for the difference of a crowned bridge deck and the level top of backwall?
Q7 Note: There will be a slight elevation change on the trail if the two segments do not have similar elevation finishes (i.e. both level or both crowned).
Backwall elevations on contract plans follow crowned bridge section.
Questions Answers 1 Would it possible to push the bid date back on this project by 1-2 weeks? Bid opening has been extended to 11/1/2023
October 11, 2023 Questions Answers
1 Can the QCM be a member of the subcontracting team or does the QCM need to be employed by the Prime Contractor?
QCM can be a member of the subcontracting team.
2 Do you want QCM resume to be provided within the technical requirements on bidders information page, because it does not request it? Only Project Manager and superintendent are requested. QCM is requested on page 83 of the solicitation.
No
3 Can the superintendent and the project manager be the same individual? The superintendent and the project manager can be the same individual.
4 In bidders information form #8 Contracts in force can we just list the contracts in force that are relevant? Or do you want all the actual contracts in force at the moment?
All contracts currently in force
5 Can the proposal be turned in electronically via email? Please see page A-i Pre-Bid information and A-ii Modifications to Bid
6 If the proposal can be turned in electronically can the bond be turned in electronically with the proposal submission
No, please see page A-ii- Bid Guarantee
October 16, 2023
1 For the Bid submission – Section 8a of the Bidders Information – are these contracts in force as of the date of submission or contracts that will be in force once construction begin in September 2024?
All contracts currently in force as of date of bid submission
2 The staging plans for the SH128 underpass show a single 10’ lane, however there is no traffic control plan sheets. Can Traffic Control Plan sheets be provided to assist in generating quantities or please clarify the expectation of traffic control on SH128 and Indiana?
The contractor will be responsible to generate traffic control plans.
Phasing plans for the construction of the CBC on Indiana Street have been provided on Sheet S3.
3 How is the excavation for the SH128 underpass paid? Excavation for the underpass will be paid with the CBC pay item 60220-4150.
October 18, 2023
1 Manufacturers are telling us that they cannot and will not provide pre-cast concrete box culverts without haunches on the bottom as shown on the drawings. Will the FHWA reconsider their stance on this issue?
Yes. Please refer to revised Sheet S4 and S5.
2 Bridge manufacturers have questioned that the Indiana Bridge is crossing a major street and the design does not currently show fence above the roadway. Typically, there is fencing that is required where bridges cross existing streets and minimum of 8’ above the concrete deck to prevent pedestrians from throwing things to the roadway below. Please confirm that this is not required on this project.
Typical section details minimum height of truss with a full height steel grid for pedestrian protection over roadway.
3 Per the Q&A’s responded to already #7 states “no temporary roads will be anticipated”. Does this mean they will not be allowed? The access to Rock Creek will require significant work to allow Drill Rigs, Concrete Trucks, Concrete Pump Truck, & Bridge Delivery/installation. The existing accesses are steep, have excess cross slope, and drainage crossings that will need to be remedied prior to construction starting.
The FWS access roads as shown on the site map Sheet A4 provide access to the south side of the creek. The contractor should consider approach and size vehicles for a soft-surface roadway. No additional temporary roadways would be allowed within the Refuge.
October 24, 2023
1 Per Solicitation Section 107.10 Environmental Protection, a.4., “do not ford running steams with construction equipment. Obtain approval from the CO to use temporary bridges or other structures whenever crossing are necessary”.
This section is the only mention of “temporary bridges”. Please confirm the temporary bridges mentioned are for contractor use only, and temporary bridges/alternate trail routes for the Rocky Flats employees or public are not to be included in the scope.
The temporary bridges mentioned in Section 107.10 a(4) are for contractor use only. Temporary bridges/alternate trail routes for the Rocky Flats employees or public are not to be included in the scope of this project.
2 Per Solicitation Section 157.02. Contractor is to conform to the listed subsections. “Water 725.01(b)” is listed but no further information on
725.01 is found. Watering For Dust Control is listed (Solicitation A-7) on the Bid Schedule.
Is there a hydrant / fill location on site that the Owner will allow the contractor to use?
i. If yes, will there be fee’s associated with the water used?
ii. If no, is there further specifications that can be provided on the subsection 725.01 for acceptable water to be used on site?
There is no water source available within the project area.
Please refer to Standard Specification for Construction of Roads and Bridges on Federal Highway Projects (FP-14) Section 725.01(b) for Water requirements.
3 Per Solicitation “Standard Form 1442” box #11. Contractor is to begin performance with 10 calendar days and complete it within ‘refer to subsection 108.01’ calendar days after receiving notice to proceed.” And also states contractors are to hold pricing for 60 calendar days. Subsection 108.01 contains information stating “no on-site ground disturbing until September 9, 2024” but does not refer to any Period of Performance end date. Section 52.211-12 states there are liquidated damages of $3,500.00 per each calendar day of delay.
• Please provide more detail on the contract Period of Performance.
• Are contractors to hold pricing for 60 calendars days or hold pricing until September 9th, 2024?
Please refer to Section 108.01 for the contract completion date.
60 calendars from the bid opening date, the bid bond guarantees the bidder will honor prices for up to 60 days. The prices are set at time of award.