Tabulation of Bids_AZ FTBR SALT 80(1) Horse Mesa Bridge .pdf
PDF 658 KB Posted
- Attached to
- AZ FTBR SALT 80(1) Horse Mesa Bridge
- Solicitation number
- 6982AF22B000034
About this file
This document contains a tabulation of bids report and related federal contract opportunity notice for the AZ FTBR SALT 80(1) Horse Mesa Bridge project. The tabulation of bids report details seven bids received in response to Solicitation Number 6982AF22B000034 for construction of a bridge and approach roads. Responsive Technology Construction, Inc. provided the lowest bid at $1,570,000. The project is managed by the Department of Transportation Federal Highway Administration and involves construction of a 16' x 98' pre-fabricated steel bridge, roadway and approach work, soil erosion controls, and temporary traffic management. The notice specifies the solicitation and opportunity types as an Invitation for Bid and Solicitation, respectively. No organized site visit will be held, and interested parties should contact the listed point of contact to schedule an independent visit.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 11/04/22
1 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Solcitation No: 6982AF22B000034
Division: Central Federal Lands
State: AZ County: Maricopa
Federal Land: Tonto National Forest Opened at: Lakewood
Opened by: Sheri Walsh
Date: 11/01/22
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Technology Construction, Inc. $1,570,000.00 5430 Side Road Prescott, AZ 86301
Whelcon Contractors LLC. $1,827,676.43 1430 West Date Street Tucson , AZ 85704
Larison Contracting Corp. $2,484,236.25 3268 Cherry Ave.
Long Beach, CA 90807
Meridian Engineering Company $3,064,775.50 3855 N. Business Center Drive Tucson, AZ 85705
Engineer's Estimate $1,690,000.00
2 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0001 15101-0000 MOBILIZATION
Technology Construction, Inc. Lump Sum $46,000.00 Whelcon Contractors LLC. Lump Sum $18,308.04 Larison Contracting Corp. Lump Sum $223,000.00 Meridian Engineering Company Lump Sum $295,000.00 Engineer's Estimate ALL LPSM Lump Sum $245,565.00
A0021 15214-1000 SURVEY AND STAKING, BRIDGE
Technology Construction, Inc. Lump Sum $15,000.00 Whelcon Contractors LLC. Lump Sum $17,413.61 Larison Contracting Corp. Lump Sum $21,000.00 Meridian Engineering Company Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
A0041 15215-1000 SURVEY AND STAKING, APPROACH ROAD
Technology Construction, Inc. $4,528.38 $9,056.76 Whelcon Contractors LLC. $5,804.54 $11,609.08 Larison Contracting Corp. $7,560.00 $15,120.00 Meridian Engineering Company $5,000.00 $10,000.00 Engineer's Estimate 2 EACH $1,300.00 $2,600.00
A0061 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
Technology Construction, Inc. $179,503.24 $6,641.62 Whelcon Contractors LLC. $98,049.63 $3,627.84 Larison Contracting Corp. $413,000.00 $15,281.00 Meridian Engineering Company $52,000.00 $1,924.00 Engineer's Estimate 0.037 MILE $30,000.00 $1,110.00
A0081 15236-2000 SURVEY CONTROL, GRADE FINISHING
Technology Construction, Inc. $179,503.24 $6,641.62 Whelcon Contractors LLC. $78,439.70 $2,902.27 Larison Contracting Corp. $496,000.00 $18,352.00 Meridian Engineering Company $52,000.00 $1,924.00 Engineer's Estimate 0.037 MILE $15,000.00 $555.00
A0101 15301-0000 CONTRACTOR QUALITY CONTROL
Technology Construction, Inc. Lump Sum $30,000.00 Whelcon Contractors LLC. Lump Sum $36,301.64 Larison Contracting Corp. Lump Sum $62,000.00 Meridian Engineering Company Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00
3 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0121 15401-0000 CONTRACTOR TESTING
Technology Construction, Inc. Lump Sum $45,000.00 Whelcon Contractors LLC. Lump Sum $32,345.79 Larison Contracting Corp. Lump Sum $20,000.00 Meridian Engineering Company Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
A0141 15501-0000 CONSTRUCTION SCHEDULE
Technology Construction, Inc. Lump Sum $15,000.00 Whelcon Contractors LLC. Lump Sum $1,451.13 Larison Contracting Corp. Lump Sum $20,000.00 Meridian Engineering Company Lump Sum $92,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0161 15701-0000 SOIL EROSION CONTROL
Technology Construction, Inc. Lump Sum $10,000.00 Whelcon Contractors LLC. Lump Sum $14,004.19 Larison Contracting Corp. Lump Sum $35,000.00 Meridian Engineering Company Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00
A0181 15802-0000 WATERING FOR DUST CONTROL
Technology Construction, Inc. Lump Sum $54,963.64 Whelcon Contractors LLC. Lump Sum $32,885.18 Larison Contracting Corp. Lump Sum $38,000.00 Meridian Engineering Company Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
A0201 20101-0000 CLEARING AND GRUBBING
Technology Construction, Inc. $12,000.00 $4,200.00 Whelcon Contractors LLC. $18,896.99 $6,613.95 Larison Contracting Corp. $10,325.00 $3,613.75 Meridian Engineering Company $55,000.00 $19,250.00 Engineer's Estimate 0.35 ACRE $3,000.00 $1,050.00
A0221 20301-2300 REMOVAL OF SIGN/MARKER
Technology Construction, Inc. $350.00 $1,050.00 Whelcon Contractors LLC. $117.71 $353.13 Larison Contracting Corp. $3,200.00 $9,600.00 Meridian Engineering Company $1,500.00 $4,500.00 Engineer's Estimate 3 EACH $180.00 $540.00
4 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0241 20302-0500 REMOVAL OF CURB, CONCRETE
Technology Construction, Inc. $350.00 $57,750.00 Whelcon Contractors LLC. $54.73 $9,030.45 Larison Contracting Corp. $56.50 $9,322.50 Meridian Engineering Company $100.00 $16,500.00 Engineer's Estimate 165 LNFT $15.00 $2,475.00
A0261 20302-1200 REMOVAL OF GUARDRAIL
Technology Construction, Inc. $350.00 $3,500.00 Whelcon Contractors LLC. $84.82 $848.20 Larison Contracting Corp. $157.00 $1,570.00 Meridian Engineering Company $250.00 $2,500.00 Engineer's Estimate 10.0 LNFT $48.00 $480.00
A0281 20401-0000 ROADWAY EXCAVATION
Technology Construction, Inc. $250.00 $92,500.00 Whelcon Contractors LLC. $171.83 $63,577.10 Larison Contracting Corp. $136.50 $50,505.00 Meridian Engineering Company $350.00 $129,500.00 Engineer's Estimate 370 CUYD $76.00 $28,120.00
A0301 20801-0000 STRUCTURE EXCAVATION
Technology Construction, Inc. $50.00 $6,500.00 Whelcon Contractors LLC. $196.22 $25,508.60 Larison Contracting Corp. $425.00 $55,250.00 Meridian Engineering Company $400.00 $52,000.00 Engineer's Estimate 130 CUYD $500.00 $65,000.00
A0321 20803-0000 STRUCTURAL BACKFILL
Technology Construction, Inc. $600.00 $27,000.00 Whelcon Contractors LLC. $458.52 $20,633.40 Larison Contracting Corp. $575.00 $25,875.00 Meridian Engineering Company $250.00 $11,250.00 Engineer's Estimate 45 CUYD $300.00 $13,500.00
A0341 25801-0000 REINFORCED CONCRETE RETAINING WALL
Technology Construction, Inc. $150.00 $61,500.00 Whelcon Contractors LLC. $73.28 $30,044.80 Larison Contracting Corp. $69.00 $28,290.00 Meridian Engineering Company $350.00 $143,500.00 Engineer's Estimate 410 SQFT $150.00 $61,500.00
5 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0361 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE
Technology Construction, Inc. $200.00 $48,400.00 Whelcon Contractors LLC. $144.19 $34,893.98 Larison Contracting Corp. $156.00 $37,752.00 Meridian Engineering Company $275.00 $66,550.00 Engineer's Estimate 242 TON $150.00 $36,300.00
A0381 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
Technology Construction, Inc. $2,000.00 $56,000.00 Whelcon Contractors LLC. $1,915.34 $53,629.52 Larison Contracting Corp. $2,620.00 $73,360.00 Meridian Engineering Company $5,900.00 $165,200.00 Engineer's Estimate 28 CUYD $3,500.00 $98,000.00
A0401 55401-1000 REINFORCING STEEL
Technology Construction, Inc. $6.00 $21,600.00 Whelcon Contractors LLC. $5.49 $19,764.00 Larison Contracting Corp. $14.70 $52,920.00 Meridian Engineering Company $10.00 $36,000.00 Engineer's Estimate 3,600 LB $6.00 $21,600.00
A0421 55504-0000 PRE-FABRICATED STEEL BRIDGE (16'x98')
Technology Construction, Inc. Lump Sum $777,187.86 Whelcon Contractors LLC. Lump Sum $1,292,639.27 Larison Contracting Corp. Lump Sum $1,562,000.00 Meridian Engineering Company Lump Sum $1,600,000.00 Engineer's Estimate ALL LPSM Lump Sum $750,000.00
A0441 60101-0000 CONCRETE
Technology Construction, Inc. $2,500.00 $25,000.00 Whelcon Contractors LLC. $1,825.65 $18,256.50 Larison Contracting Corp. $1,443.00 $14,430.00 Meridian Engineering Company $4,500.00 $45,000.00 Engineer's Estimate 10 CUYD $2,500.00 $25,000.00
A0461 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
Technology Construction, Inc. $218.00 $4,360.00 Whelcon Contractors LLC. $229.95 $4,599.00 Larison Contracting Corp. $190.00 $3,800.00 Meridian Engineering Company $200.00 $4,000.00 Engineer's Estimate 20 HOUR $140.00 $2,800.00
6 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0481 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
Technology Construction, Inc. $150.00 $3,000.00 Whelcon Contractors LLC. $147.15 $2,943.00 Larison Contracting Corp. $210.00 $4,200.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $190.00 $3,800.00
A0501 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
Technology Construction, Inc. $345.00 $6,900.00 Whelcon Contractors LLC. $167.16 $3,343.20 Larison Contracting Corp. $250.00 $5,000.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $140.00 $2,800.00
A0521 62201-2750 MOTOR GRADER
Technology Construction, Inc. $484.00 $9,680.00 Whelcon Contractors LLC. $409.15 $8,183.00 Larison Contracting Corp. $260.00 $5,200.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $190.00 $3,800.00
A0541 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY
Technology Construction, Inc. $496.00 $9,920.00 Whelcon Contractors LLC. $228.09 $4,561.80 Larison Contracting Corp. $330.00 $6,600.00 Meridian Engineering Company $200.00 $4,000.00 Engineer's Estimate 20 HOUR $230.00 $4,600.00
A0561 62301-0000 GENERAL LABOR
Technology Construction, Inc. $118.00 $4,720.00 Whelcon Contractors LLC. $57.56 $2,302.40 Larison Contracting Corp. $110.00 $4,400.00 Meridian Engineering Company $50.00 $2,000.00 Engineer's Estimate 40 HOUR $80.00 $3,200.00
A0581 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
Technology Construction, Inc. $188.00 $7,520.00 Whelcon Contractors LLC. $328.41 $13,136.40 Larison Contracting Corp. $200.00 $8,000.00 Meridian Engineering Company $350.00 $14,000.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00
7 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0601 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
Technology Construction, Inc. $280.00 $11,200.00 Whelcon Contractors LLC. $394.14 $15,765.60 Larison Contracting Corp. $200.00 $8,000.00 Meridian Engineering Company $300.00 $12,000.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00
A0621 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGIST)
Technology Construction, Inc. Lump Sum $8,453.00 Whelcon Contractors LLC. Lump Sum $5,441.75 Larison Contracting Corp. Lump Sum $12,500.00 Meridian Engineering Company Lump Sum $7,500.00 Engineer's Estimate ALL LPSM Lump Sum $1,600.00
A0641 62511-2000 SEEDING, HYDRAULIC METHOD
Technology Construction, Inc. $7.40 $6,327.00 Whelcon Contractors LLC. $5.94 $5,078.70 Larison Contracting Corp. $6.00 $5,130.00 Meridian Engineering Company $1.50 $1,282.50 Engineer's Estimate 855 SQYD $3.00 $2,565.00
A0661 62516-2000 MULCHING, HYDRAULIC METHOD
Technology Construction, Inc. $6.70 $5,728.50 Whelcon Contractors LLC. $5.94 $5,078.70 Larison Contracting Corp. $6.00 $5,130.00 Meridian Engineering Company $1.00 $855.00 Engineer's Estimate 855 SQYD $4.00 $3,420.00
A0681 63308-3000 OBJECT MARKER, TYPE 3
Technology Construction, Inc. $640.00 $2,560.00 Whelcon Contractors LLC. $344.48 $1,377.92 Larison Contracting Corp. $815.00 $3,260.00 Meridian Engineering Company $60.00 $240.00 Engineer's Estimate 4 EACH $250.00 $1,000.00
A0701 63309-0000 DELINEATOR
Technology Construction, Inc. $640.00 $640.00 Whelcon Contractors LLC. $344.48 $344.48 Larison Contracting Corp. $25.00 $25.00 Meridian Engineering Company $300.00 $300.00 Engineer's Estimate 1 EACH $290.00 $290.00
8 out of 8Source Selection Information - See FAR 2.101 & 3.104
Project No: AZ FTBR SALT 80(1)
Project Name: Horse Mesa Bridge
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0721 63316-1000 REMOVE AND RESET SIGN
Technology Construction, Inc. $500.00 $500.00 Whelcon Contractors LLC. $232.48 $232.48 Larison Contracting Corp. $1,200.00 $1,200.00 Meridian Engineering Company $2,000.00 $2,000.00 Engineer's Estimate 1 EACH $330.00 $330.00
A0741 63501-0000 TEMPORARY TRAFFIC CONTROL
Technology Construction, Inc. Lump Sum $68,000.00 Whelcon Contractors LLC. Lump Sum $8,646.34 Larison Contracting Corp. Lump Sum $19,550.00 Meridian Engineering Company Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00
Total Schedule - All Items
Technology Construction, Inc. $1,570,000.00 Whelcon Contractors LLC. $1,827,676.43 Larison Contracting Corp. $2,484,236.25 Meridian Engineering Company $3,064,775.50 Engineer's Estimate $1,690,000.00
| 2022-11-04T08:30:25-0600 | |
| JOSEPHINE P HELMS |