Tabulation of Bids_AZ FTBR SALT 80(1) Horse Mesa Bridge .pdf

PDF 658 KB Posted

Attached to
AZ FTBR SALT 80(1) Horse Mesa Bridge
Solicitation number
6982AF22B000034
Issued by

About this file

This document contains a tabulation of bids report and related federal contract opportunity notice for the AZ FTBR SALT 80(1) Horse Mesa Bridge project. The tabulation of bids report details seven bids received in response to Solicitation Number 6982AF22B000034 for construction of a bridge and approach roads. Responsive Technology Construction, Inc. provided the lowest bid at $1,570,000. The project is managed by the Department of Transportation Federal Highway Administration and involves construction of a 16' x 98' pre-fabricated steel bridge, roadway and approach work, soil erosion controls, and temporary traffic management. The notice specifies the solicitation and opportunity types as an Invitation for Bid and Solicitation, respectively. No organized site visit will be held, and interested parties should contact the listed point of contact to schedule an independent visit.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 11/04/22

1 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF22B000034

Division: Central Federal Lands

State: AZ County: Maricopa

Federal Land: Tonto National Forest Opened at: Lakewood

Opened by: Sheri Walsh

Date: 11/01/22

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Technology Construction, Inc. $1,570,000.00 5430 Side Road Prescott, AZ 86301

Whelcon Contractors LLC. $1,827,676.43 1430 West Date Street Tucson , AZ 85704

Larison Contracting Corp. $2,484,236.25 3268 Cherry Ave.

Long Beach, CA 90807

Meridian Engineering Company $3,064,775.50 3855 N. Business Center Drive Tucson, AZ 85705

Engineer's Estimate $1,690,000.00

2 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0001 15101-0000 MOBILIZATION

Technology Construction, Inc. Lump Sum $46,000.00 Whelcon Contractors LLC. Lump Sum $18,308.04 Larison Contracting Corp. Lump Sum $223,000.00 Meridian Engineering Company Lump Sum $295,000.00 Engineer's Estimate ALL LPSM Lump Sum $245,565.00

A0021 15214-1000 SURVEY AND STAKING, BRIDGE

Technology Construction, Inc. Lump Sum $15,000.00 Whelcon Contractors LLC. Lump Sum $17,413.61 Larison Contracting Corp. Lump Sum $21,000.00 Meridian Engineering Company Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A0041 15215-1000 SURVEY AND STAKING, APPROACH ROAD

Technology Construction, Inc. $4,528.38 $9,056.76 Whelcon Contractors LLC. $5,804.54 $11,609.08 Larison Contracting Corp. $7,560.00 $15,120.00 Meridian Engineering Company $5,000.00 $10,000.00 Engineer's Estimate 2 EACH $1,300.00 $2,600.00

A0061 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Technology Construction, Inc. $179,503.24 $6,641.62 Whelcon Contractors LLC. $98,049.63 $3,627.84 Larison Contracting Corp. $413,000.00 $15,281.00 Meridian Engineering Company $52,000.00 $1,924.00 Engineer's Estimate 0.037 MILE $30,000.00 $1,110.00

A0081 15236-2000 SURVEY CONTROL, GRADE FINISHING

Technology Construction, Inc. $179,503.24 $6,641.62 Whelcon Contractors LLC. $78,439.70 $2,902.27 Larison Contracting Corp. $496,000.00 $18,352.00 Meridian Engineering Company $52,000.00 $1,924.00 Engineer's Estimate 0.037 MILE $15,000.00 $555.00

A0101 15301-0000 CONTRACTOR QUALITY CONTROL

Technology Construction, Inc. Lump Sum $30,000.00 Whelcon Contractors LLC. Lump Sum $36,301.64 Larison Contracting Corp. Lump Sum $62,000.00 Meridian Engineering Company Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

3 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0121 15401-0000 CONTRACTOR TESTING

Technology Construction, Inc. Lump Sum $45,000.00 Whelcon Contractors LLC. Lump Sum $32,345.79 Larison Contracting Corp. Lump Sum $20,000.00 Meridian Engineering Company Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $40,000.00

A0141 15501-0000 CONSTRUCTION SCHEDULE

Technology Construction, Inc. Lump Sum $15,000.00 Whelcon Contractors LLC. Lump Sum $1,451.13 Larison Contracting Corp. Lump Sum $20,000.00 Meridian Engineering Company Lump Sum $92,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0161 15701-0000 SOIL EROSION CONTROL

Technology Construction, Inc. Lump Sum $10,000.00 Whelcon Contractors LLC. Lump Sum $14,004.19 Larison Contracting Corp. Lump Sum $35,000.00 Meridian Engineering Company Lump Sum $15,000.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00

A0181 15802-0000 WATERING FOR DUST CONTROL

Technology Construction, Inc. Lump Sum $54,963.64 Whelcon Contractors LLC. Lump Sum $32,885.18 Larison Contracting Corp. Lump Sum $38,000.00 Meridian Engineering Company Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

A0201 20101-0000 CLEARING AND GRUBBING

Technology Construction, Inc. $12,000.00 $4,200.00 Whelcon Contractors LLC. $18,896.99 $6,613.95 Larison Contracting Corp. $10,325.00 $3,613.75 Meridian Engineering Company $55,000.00 $19,250.00 Engineer's Estimate 0.35 ACRE $3,000.00 $1,050.00

A0221 20301-2300 REMOVAL OF SIGN/MARKER

Technology Construction, Inc. $350.00 $1,050.00 Whelcon Contractors LLC. $117.71 $353.13 Larison Contracting Corp. $3,200.00 $9,600.00 Meridian Engineering Company $1,500.00 $4,500.00 Engineer's Estimate 3 EACH $180.00 $540.00

4 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0241 20302-0500 REMOVAL OF CURB, CONCRETE

Technology Construction, Inc. $350.00 $57,750.00 Whelcon Contractors LLC. $54.73 $9,030.45 Larison Contracting Corp. $56.50 $9,322.50 Meridian Engineering Company $100.00 $16,500.00 Engineer's Estimate 165 LNFT $15.00 $2,475.00

A0261 20302-1200 REMOVAL OF GUARDRAIL

Technology Construction, Inc. $350.00 $3,500.00 Whelcon Contractors LLC. $84.82 $848.20 Larison Contracting Corp. $157.00 $1,570.00 Meridian Engineering Company $250.00 $2,500.00 Engineer's Estimate 10.0 LNFT $48.00 $480.00

A0281 20401-0000 ROADWAY EXCAVATION

Technology Construction, Inc. $250.00 $92,500.00 Whelcon Contractors LLC. $171.83 $63,577.10 Larison Contracting Corp. $136.50 $50,505.00 Meridian Engineering Company $350.00 $129,500.00 Engineer's Estimate 370 CUYD $76.00 $28,120.00

A0301 20801-0000 STRUCTURE EXCAVATION

Technology Construction, Inc. $50.00 $6,500.00 Whelcon Contractors LLC. $196.22 $25,508.60 Larison Contracting Corp. $425.00 $55,250.00 Meridian Engineering Company $400.00 $52,000.00 Engineer's Estimate 130 CUYD $500.00 $65,000.00

A0321 20803-0000 STRUCTURAL BACKFILL

Technology Construction, Inc. $600.00 $27,000.00 Whelcon Contractors LLC. $458.52 $20,633.40 Larison Contracting Corp. $575.00 $25,875.00 Meridian Engineering Company $250.00 $11,250.00 Engineer's Estimate 45 CUYD $300.00 $13,500.00

A0341 25801-0000 REINFORCED CONCRETE RETAINING WALL

Technology Construction, Inc. $150.00 $61,500.00 Whelcon Contractors LLC. $73.28 $30,044.80 Larison Contracting Corp. $69.00 $28,290.00 Meridian Engineering Company $350.00 $143,500.00 Engineer's Estimate 410 SQFT $150.00 $61,500.00

5 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0361 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE

Technology Construction, Inc. $200.00 $48,400.00 Whelcon Contractors LLC. $144.19 $34,893.98 Larison Contracting Corp. $156.00 $37,752.00 Meridian Engineering Company $275.00 $66,550.00 Engineer's Estimate 242 TON $150.00 $36,300.00

A0381 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)

Technology Construction, Inc. $2,000.00 $56,000.00 Whelcon Contractors LLC. $1,915.34 $53,629.52 Larison Contracting Corp. $2,620.00 $73,360.00 Meridian Engineering Company $5,900.00 $165,200.00 Engineer's Estimate 28 CUYD $3,500.00 $98,000.00

A0401 55401-1000 REINFORCING STEEL

Technology Construction, Inc. $6.00 $21,600.00 Whelcon Contractors LLC. $5.49 $19,764.00 Larison Contracting Corp. $14.70 $52,920.00 Meridian Engineering Company $10.00 $36,000.00 Engineer's Estimate 3,600 LB $6.00 $21,600.00

A0421 55504-0000 PRE-FABRICATED STEEL BRIDGE (16'x98')

Technology Construction, Inc. Lump Sum $777,187.86 Whelcon Contractors LLC. Lump Sum $1,292,639.27 Larison Contracting Corp. Lump Sum $1,562,000.00 Meridian Engineering Company Lump Sum $1,600,000.00 Engineer's Estimate ALL LPSM Lump Sum $750,000.00

A0441 60101-0000 CONCRETE

Technology Construction, Inc. $2,500.00 $25,000.00 Whelcon Contractors LLC. $1,825.65 $18,256.50 Larison Contracting Corp. $1,443.00 $14,430.00 Meridian Engineering Company $4,500.00 $45,000.00 Engineer's Estimate 10 CUYD $2,500.00 $25,000.00

A0461 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY

Technology Construction, Inc. $218.00 $4,360.00 Whelcon Contractors LLC. $229.95 $4,599.00 Larison Contracting Corp. $190.00 $3,800.00 Meridian Engineering Company $200.00 $4,000.00 Engineer's Estimate 20 HOUR $140.00 $2,800.00

6 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0481 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH

Technology Construction, Inc. $150.00 $3,000.00 Whelcon Contractors LLC. $147.15 $2,943.00 Larison Contracting Corp. $210.00 $4,200.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $190.00 $3,800.00

A0501 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY

Technology Construction, Inc. $345.00 $6,900.00 Whelcon Contractors LLC. $167.16 $3,343.20 Larison Contracting Corp. $250.00 $5,000.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $140.00 $2,800.00

A0521 62201-2750 MOTOR GRADER

Technology Construction, Inc. $484.00 $9,680.00 Whelcon Contractors LLC. $409.15 $8,183.00 Larison Contracting Corp. $260.00 $5,200.00 Meridian Engineering Company $150.00 $3,000.00 Engineer's Estimate 20 HOUR $190.00 $3,800.00

A0541 62201-3350 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY

Technology Construction, Inc. $496.00 $9,920.00 Whelcon Contractors LLC. $228.09 $4,561.80 Larison Contracting Corp. $330.00 $6,600.00 Meridian Engineering Company $200.00 $4,000.00 Engineer's Estimate 20 HOUR $230.00 $4,600.00

A0561 62301-0000 GENERAL LABOR

Technology Construction, Inc. $118.00 $4,720.00 Whelcon Contractors LLC. $57.56 $2,302.40 Larison Contracting Corp. $110.00 $4,400.00 Meridian Engineering Company $50.00 $2,000.00 Engineer's Estimate 40 HOUR $80.00 $3,200.00

A0581 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Technology Construction, Inc. $188.00 $7,520.00 Whelcon Contractors LLC. $328.41 $13,136.40 Larison Contracting Corp. $200.00 $8,000.00 Meridian Engineering Company $350.00 $14,000.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

7 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0601 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Technology Construction, Inc. $280.00 $11,200.00 Whelcon Contractors LLC. $394.14 $15,765.60 Larison Contracting Corp. $200.00 $8,000.00 Meridian Engineering Company $300.00 $12,000.00 Engineer's Estimate 40 HOUR $210.00 $8,400.00

A0621 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGIST)

Technology Construction, Inc. Lump Sum $8,453.00 Whelcon Contractors LLC. Lump Sum $5,441.75 Larison Contracting Corp. Lump Sum $12,500.00 Meridian Engineering Company Lump Sum $7,500.00 Engineer's Estimate ALL LPSM Lump Sum $1,600.00

A0641 62511-2000 SEEDING, HYDRAULIC METHOD

Technology Construction, Inc. $7.40 $6,327.00 Whelcon Contractors LLC. $5.94 $5,078.70 Larison Contracting Corp. $6.00 $5,130.00 Meridian Engineering Company $1.50 $1,282.50 Engineer's Estimate 855 SQYD $3.00 $2,565.00

A0661 62516-2000 MULCHING, HYDRAULIC METHOD

Technology Construction, Inc. $6.70 $5,728.50 Whelcon Contractors LLC. $5.94 $5,078.70 Larison Contracting Corp. $6.00 $5,130.00 Meridian Engineering Company $1.00 $855.00 Engineer's Estimate 855 SQYD $4.00 $3,420.00

A0681 63308-3000 OBJECT MARKER, TYPE 3

Technology Construction, Inc. $640.00 $2,560.00 Whelcon Contractors LLC. $344.48 $1,377.92 Larison Contracting Corp. $815.00 $3,260.00 Meridian Engineering Company $60.00 $240.00 Engineer's Estimate 4 EACH $250.00 $1,000.00

A0701 63309-0000 DELINEATOR

Technology Construction, Inc. $640.00 $640.00 Whelcon Contractors LLC. $344.48 $344.48 Larison Contracting Corp. $25.00 $25.00 Meridian Engineering Company $300.00 $300.00 Engineer's Estimate 1 EACH $290.00 $290.00

8 out of 8Source Selection Information - See FAR 2.101 & 3.104

Project No: AZ FTBR SALT 80(1)

Project Name: Horse Mesa Bridge

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0721 63316-1000 REMOVE AND RESET SIGN

Technology Construction, Inc. $500.00 $500.00 Whelcon Contractors LLC. $232.48 $232.48 Larison Contracting Corp. $1,200.00 $1,200.00 Meridian Engineering Company $2,000.00 $2,000.00 Engineer's Estimate 1 EACH $330.00 $330.00

A0741 63501-0000 TEMPORARY TRAFFIC CONTROL

Technology Construction, Inc. Lump Sum $68,000.00 Whelcon Contractors LLC. Lump Sum $8,646.34 Larison Contracting Corp. Lump Sum $19,550.00 Meridian Engineering Company Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

Total Schedule - All Items

Technology Construction, Inc. $1,570,000.00 Whelcon Contractors LLC. $1,827,676.43 Larison Contracting Corp. $2,484,236.25 Meridian Engineering Company $3,064,775.50 Engineer's Estimate $1,690,000.00

2022-11-04T08:30:25-0600
JOSEPHINE P HELMS